Question 1 of 10UDC Administration and Inspector Credentials (SPS 305, SPS 320)

A person holds a Wisconsin journeyman electrician license and wants a UDC-electrical inspector certification without taking the UDC-electrical examination. What does SPS 305.63(4)(b)2 allow?

Requirements at a glance

AgencyWisconsin Department of Safety and Professional Services (DSPS)
ExperienceNo experience requirement (SPS 305.63); exam waived for a Wisconsin journeyman, master or residential master electrician or an IAEI residential inspector
Exam90 questions, 3 hours, 70% to pass
Books allowedOne binder (SPS 305, SPS 316, SPS 320, SPS 324, notes), the 2023 NEC codebook or handbook, and up to two bound reference books
Fees$90 at Pearson VUE ($25 at a DSPS site), plus the credential fee ($40 plus $15 application, 24 CE hours, renews June 30)

Municipal and contract inspectors applying to DSPS for a UDC electrical inspector credential (SPS 305.63). There is no experience requirement; you apply, pay and pass.

How to get licensed, step by step

  1. Apply to DSPS

    Apply in LicensE for the UDC electrical inspector credential, then pay and pass the exam.

    Wisconsin Department of Safety and Professional Services (DSPS) (opens in a new tab)LicensE: apply for your credential (opens in a new tab)

  2. Schedule your exam

    Once your qualifications are met, DSPS sends an exam authorization. Schedule with Pearson VUE or, for electrical exams, a DSPS exam site. If you choose Pearson you cannot switch back. Plumbing and HVAC Qualifier exams are given only at Pearson centers.

    DSPS: trades exam information and fee schedule (opens in a new tab)Pearson VUE: Wisconsin DSPS Trades candidate handbook (PDF) (opens in a new tab)

  3. Take the exam

    90 questions, 3 hours, 70% to pass. Bring only the items DSPS lists; sticky notes, loose paper and removable tabs are not allowed.

    Wisconsin Admin. Code chapter SPS 316 (electrical) (opens in a new tab)DSPS permitted trades exam materials (PDF) (opens in a new tab)

  4. Results and licensing

    After you pass, wait 2 days, then submit your license application in LicensE. DSPS sends one exam authorization at a time, so a retake needs a new authorization. On two-part exams a failed part is retaken alone and all parts must be passed within 1 year.

    LicensE: apply for your credential (opens in a new tab)

How to prepare

  • Concentrate on one- and two-family dwelling wiring under the 2023 NEC, SPS 316 and the UDC electrical rules in SPS 324.
  • The exam uses the 2023 NEC. SPS 316.007 adopts it, and Wisconsin's changes are in SPS 316.080 and following: know where SPS 316 differs from the model NEC.
  • Put SPS 305 and SPS 316 in your binder with three-hole-punched notes, and tab your NEC with tabs that come with the bound book.
  • Every Wisconsin trades exam is open book, but DSPS limits what you can bring (a binder plus the listed books), and tabs must come with a bound book. Practice finding answers fast in your own binder.
  • DSPS publishes no content outline or topic weights, so our topic split is an estimate built from the reference lists DSPS prints. Counts and times come from DSPS's exam table.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the NEC and SPS 316. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

Official reference list (as published by the testing agency)
  • One binder with Wis. Admin. Code SPS 305, SPS 316, SPS 320 and SPS 324 and your printed notes
  • 2023 National Electrical Code (NEC) codebook or handbook
  • Up to two printed, bound reference books (for example Ugly's, Ferm's Fast Finder, Tom Henry or Mike Holt series)

What's on the exam

Estimated topic weighting. No official breakdown is published:

TopicQuestions
UDC Administration and Inspector Credentials (SPS 305, SPS 320)10
Electrical Service and Grounding (NEC Articles 230 and 250)16
Branch Circuits, Feeders and Calculations (NEC Articles 210 and 220)18
Wiring Methods and Boxes (NEC Chapters 3 and 314)16
Devices, Luminaires and Appliances (NEC Chapters 4 and 6)14
Wisconsin Electrical Code (SPS 316)12
Uniform Dwelling Code Electrical Standards (SPS 324)14

Exam day details

  • Administered by the Wisconsin Department of Safety and Professional Services (DSPS); exams are given by Pearson VUE or at a DSPS exam site.
  • Fee: $90 at Pearson VUE ($25 at a DSPS exam site). The credential application fee is separate.
  • 90 questions in 3 hours (DSPS exam table); open book; 70% to pass.
  • Scope is SPS 316 and SPS 324 for one- and two-family dwellings. You can skip the exam if you hold a Wisconsin journeyman, master or residential master electrician license, or an IAEI residential inspector certification.
  • Open book: bring one binder (three-hole-punched printed notes and printed code), plus the other references DSPS lists for your exam. Loose paper, removable tabs, sticky notes and paperclips are not allowed; practice exams do not count as notes.
  • You can test at a Pearson VUE center or a DSPS exam site, but once you choose Pearson you cannot switch back. Plumbing and HVAC Qualifier exams are given only at Pearson centers.
  • The passing score is 70%. For two-part exams you need 70% in each part, a failed part is retaken alone, and all parts must be passed within 1 year (SPS 305.09(6)).
  • DSPS sends one exam authorization at a time. After you pass, wait 2 days, then apply for the license in LicensE.
  • DSPS publishes no content outline or topic weights (SPS 305.09(5) says the exams are based on a job analysis), so our topic split is an estimate built from the reference lists DSPS prints.

Note: DSPS publishes the question counts, time limits and permitted references but no content outline or topic weights, so our topic split is an estimate. Counts come from DSPS's exam table and were not checked against Pearson.

Frequently asked questions

Is there an experience requirement for UDC inspectors?

No. SPS 305.63 requires only an application, the fee and a passing exam score.

Who can skip the exam?

Holders of a Wisconsin journeyman, master or residential master electrician license, or an IAEI residential inspector certification.

Which references can I bring?

One binder (SPS 305, 316, 320, 324 and notes), a 2023 NEC codebook or handbook, and up to two bound reference books.

Free questions with answers

Show all 10 free questions and answers
  1. A person holds a Wisconsin journeyman electrician license and wants a UDC-electrical inspector certification without taking the UDC-electrical examination. What does SPS 305.63(4)(b)2 allow?

    Answer: Apply with evidence of the journeyman license, plus the application fee and certification fee

    SPS 305.63(4)(b)2 lets an applicant skip the exam by showing a journeyman electrician license (305.44), an IAEI/NFPA certified electrical inspector-residential certification, or a residential master electrician license (305.435), and paying the fees. Other credentials such as HVAC inspector or dwelling contractor qualifier are not on the list.

    Reference: Wisconsin Administrative Code SPS 305, SPS 305.63(4)(b)2

  2. During a service inspection at a new one-family dwelling, the inspector reads the nameplate on the main disconnect. What is the smallest rating allowed for the service disconnecting means under NEC 230.79?

    Answer: 100 amperes, 3-wire

    NEC 230.79(C) sets the minimum rating of the service disconnecting means for a one-family dwelling at 100 amperes, 3-wire. Lower ratings appear in 230.79(A) to (B) only for limited loads and are not used for a whole dwelling.

    Reference: NEC 2023 (NFPA 70), 230.79(C)

  3. A one-family dwelling has 4/0 AWG copper service-entrance conductors. The only grounding electrodes are two ground rods, and the grounding electrode conductor runs only to those rods. Table 250.66 would call for 2 AWG copper for 4/0 conductors. What is the smallest copper grounding electrode conductor the inspector must require for the rod connection?

    Answer: 6 AWG copper

    NEC 250.66(A) says that where the conductor connects only to rod, pipe or plate electrodes and does not extend to other electrode types, it need not be larger than 6 AWG copper. 4 AWG copper is the limit in 250.66(B) for concrete-encased electrodes, and 2 AWG is the unreduced table size.

    Reference: NEC 2023 (NFPA 70), 250.66(A)

  4. A dwelling has a dishwasher (1,200 VA), a disposal (900 VA), a microwave built into a wall cabinet and wired in place (1,500 VA) and a water heater (4,500 VA), all fastened in place and none an electric range, dryer or space heater. What demand load is used for these four appliances under NEC 220.53?

    Answer: 6,075 VA

    NEC 220.53 allows a 75 percent demand factor where four or more appliances are fastened in place, excluding ranges, dryers, space heating and air conditioning. The total is 1,200 + 900 + 1,500 + 4,500 = 8,100 VA, and 8,100 x 0.75 = 6,075 VA. 8,100 applies no factor and 4,050 uses 50 percent.

    Reference: NEC 2023 (NFPA 70), 220.53

  5. A box marked 12.5 cubic inches will hold nothing but 12 AWG insulated conductors, with no devices, fittings, clamps or grounding conductors counted. What is the maximum number of 12 AWG conductors under NEC 314.16?

    Answer: 5 conductors

    Table 314.16(B) allows 2.25 cubic inches for each 12 AWG conductor. 12.5 / 2.25 = 5.56, and the number of conductors must be rounded down to 5. Six would need 13.5 in3. Seven corresponds to 14 AWG at 2.00 in3, which would still need 14.0 in3.

    Reference: NEC 2023 (NFPA 70), 314.16(B)(1), Table 314.16(B)

  6. A paddle fan weighing 45 pounds is to hang from a ceiling outlet box in a new bedroom. What does NEC 314.27(C) require of the box?

    Answer: Listed and marked for fan support, with the fan weight marked on the box since it exceeds 35 pounds

    NEC 314.27(C) says a box used as the sole support of a ceiling-suspended fan must be listed and marked as suitable for that purpose, and may not support a fan over 70 lb. For fans over 35 lb, the total fan weight must be marked on the box as well.

    Reference: NEC 2023 (NFPA 70), 314.27(C)

  7. A rough inspection finds a new hallway light and a new bathroom light each controlled by a switch loop run with 2-wire cable, with no grounded conductor in the switch boxes. Under NEC 404.2(C), what is the inspector's finding?

    Answer: A correction is needed unless one of the listed conditions applies, since the grounded conductor is required at those switch locations

    NEC 404.2(C) requires the grounded circuit conductor at switch locations controlling lighting loads supplied by a grounded general-purpose branch circuit serving bathrooms, hallways, stairways, and habitable rooms or occupiable spaces, unless one of the listed conditions applies, such as conductors entering the box in a raceway with enough space to add one later. The switch-loop exception in 404.2(A) is for three-way and four-way wiring and does not remove this requirement.

    Reference: NEC 2023 (NFPA 70), 404.2(C)

  8. At final inspection, the inspector measures a wall switch at the top of a basement stairway. In its highest position, the center of the grip of the switch handle is 6 feet 10 inches above the landing. What is the finding under NEC 404.8(A)?

    Answer: A violation, since the limit is 6 feet 7 inches above the floor

    NEC 404.8(A) says switches and circuit breakers used as switches shall be installed so the center of the grip of the operating handle, in its highest position, is not more than 2.0 m (6 ft 7 in.) above the floor or working platform. At 6 ft 10 in. the switch is 3 inches too high. The 6 ft and 7 ft values are not the Code limit, and stairway landings are not exempt.

    Reference: NEC 2023 (NFPA 70), 404.8(A)

  9. A dwelling's old wiring is found to have a known defect that endangers life. What does SPS 316.021 require?

    Answer: It must be promptly repaired, permanently disconnected, or isolated until repairs can be made

    SPS 316.021 requires that any equipment or electrical wiring installation known to be defective so as to endanger life or property be promptly repaired, permanently disconnected or isolated until repairs can be made. It also requires cleaning and inspection at the intervals experience has shown to be necessary.

    Reference: Wisconsin Administrative Code SPS 316 (Register September 2026), SPS 316.021

  10. A homeowner replaces a failed branch-circuit cable in the wall of a house built in 2004 with no addition or alteration. Under SPS 320.05(3), does the UDC apply to this work?

    Answer: No, repairs and maintenance of electrical systems are exempt

    SPS 320.05(3) says the provisions of the UDC do not apply to repairs or maintenance of dwellings or dwelling units, or to the repair of electrical, plumbing, heating, ventilating, air conditioning and other systems installed in them. An alteration or addition would be different under SPS 320.04(2).

    Reference: Wisconsin Administrative Code SPS 320, SPS 320.05(3)