Requirements at a glance
| Agency | Wisconsin Department of Safety and Professional Services (DSPS) |
|---|---|
| Experience | 5 years of 1,000 hours of industrial electrical wiring (a 2-year degree counts at most 2,000 hours), or an approved industrial electrical apprenticeship, which needs no exam; the license is limited to wiring within your employer's facilities |
| Exam | 100 questions, 4 hours, 70% to pass |
| Books allowed | One binder (SPS 305, SPS 316, printed notes), the 2023 NEC codebook or handbook, and up to two bound reference books |
| Fees | $95 at Pearson VUE ($30 at a DSPS site) per exam, plus the credential application fee; industrial journeyman credential $100 plus $35 application, 4-year term (renews June 30, 18 CE hours) |
Electricians applying to DSPS for an industrial journeyman license with 5 years of 1,000 hours of industrial electrical wiring. The license covers wiring within the facilities of the employer's business establishment. Completing an approved industrial electrical apprenticeship removes the exam.
Official links
- Wisconsin Department of Safety and Professional Services (DSPS) (opens in a new tab)
- DSPS: trades exam information and fee schedule (opens in a new tab)
- Pearson VUE: Wisconsin DSPS Trades candidate handbook (PDF) (opens in a new tab)
- Wisconsin Admin. Code chapter SPS 316 (electrical) (opens in a new tab)
- DSPS permitted trades exam materials (PDF) (opens in a new tab)
How to get licensed, step by step
Apply to DSPS
Apply in LicensE with proof of your industrial wiring experience or apprenticeship letter. DSPS issues exam instructions once your qualifications are met.
Wisconsin Department of Safety and Professional Services (DSPS) (opens in a new tab)LicensE: apply for your credential (opens in a new tab)
Schedule your exam
Once your qualifications are met, DSPS sends an exam authorization. Schedule with Pearson VUE or, for electrical exams, a DSPS exam site. If you choose Pearson you cannot switch back. Plumbing and HVAC Qualifier exams are given only at Pearson centers.
DSPS: trades exam information and fee schedule (opens in a new tab)Pearson VUE: Wisconsin DSPS Trades candidate handbook (PDF) (opens in a new tab)
Take the exam
100 questions, 4 hours, 70% to pass. Bring only the items DSPS lists; sticky notes, loose paper and removable tabs are not allowed.
Wisconsin Admin. Code chapter SPS 316 (electrical) (opens in a new tab)DSPS permitted trades exam materials (PDF) (opens in a new tab)
Results and licensing
After you pass, wait 2 days, then submit your license application in LicensE. DSPS sends one exam authorization at a time, so a retake needs a new authorization. On two-part exams a failed part is retaken alone and all parts must be passed within 1 year.
How to prepare
- The material is the same NEC and SPS 316 content as the journeyman exam, so the journeyman practice carries over.
- The exam uses the 2023 NEC. SPS 316.007 adopts it, and Wisconsin's changes are in SPS 316.080 and following: know where SPS 316 differs from the model NEC.
- Put SPS 305 and SPS 316 in your binder with three-hole-punched notes, and tab your NEC with tabs that come with the bound book.
- Every Wisconsin trades exam is open book, but DSPS limits what you can bring (a binder plus the listed books), and tabs must come with a bound book. Practice finding answers fast in your own binder.
- DSPS publishes no content outline or topic weights, so our topic split is an estimate built from the reference lists DSPS prints. Counts and times come from DSPS's exam table.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below, and most questions come from the NEC and SPS 316. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
NFPA 70: National Electrical Code (NEC), 2023 EditionEssential
DSPS lets you bring a 2023 NEC codebook or handbook. SPS 316.007 adopts the 2023 NEC; Wisconsin's changes are in SPS 316.080 and following.
NFPA store (opens in a new tab)Free online access (opens in a new tab)
Wisconsin Admin. Code chapters SPS 305 and SPS 316Essential
Both go in your binder. SPS 316 adopts the NEC and lists Wisconsin's changes; SPS 305 covers credential and exam rules.
Official reference list (as published by the testing agency)
- One binder with Wis. Admin. Code SPS 305 and SPS 316 and your printed notes
- 2023 National Electrical Code (NEC) codebook or handbook; SPS 316.007 adopts the 2023 NEC, and Wisconsin changes are in SPS 316.080 and following
- Up to two printed, bound reference books (for example Ugly's, Ferm's Fast Finder, Tom Henry or Mike Holt series)
What's on the exam
Estimated topic weighting. No official breakdown is published:
| Topic | Questions | |
|---|---|---|
| Electrical Theory and Calculations | 10 | |
| General Requirements and Definitions (NEC Articles 90 to 110) | 8 | |
| Wiring and Protection (NEC Chapter 2) | 18 | |
| Wiring Methods and Materials (NEC Chapter 3) | 18 | |
| Equipment for General Use (NEC Chapter 4) | 18 | |
| Special Occupancies, Equipment and Conditions (NEC Chapters 5 to 7) | 14 | |
| Wisconsin Electrical Code and Licensing (SPS 316 and SPS 305) | 14 |
Exam day details
- Administered by the Wisconsin Department of Safety and Professional Services (DSPS); exams are given by Pearson VUE or at a DSPS exam site.
- Fee: $95 at Pearson VUE ($30 at a DSPS exam site). The credential application fee is separate.
- 100 questions in 4 hours (DSPS exam table); open book; 70% to pass.
- The industrial license is limited to wiring within the facilities of the employer's business establishment (SPS 305.443, 305.40). The exam material is the same NEC and SPS 316 content as the journeyman exam.
- Open book: bring one binder (three-hole-punched printed notes and printed code), plus the other references DSPS lists for your exam. Loose paper, removable tabs, sticky notes and paperclips are not allowed; practice exams do not count as notes.
- You can test at a Pearson VUE center or a DSPS exam site, but once you choose Pearson you cannot switch back. Plumbing and HVAC Qualifier exams are given only at Pearson centers.
- The passing score is 70%. For two-part exams you need 70% in each part, a failed part is retaken alone, and all parts must be passed within 1 year (SPS 305.09(6)).
- DSPS sends one exam authorization at a time. After you pass, wait 2 days, then apply for the license in LicensE.
- DSPS publishes no content outline or topic weights (SPS 305.09(5) says the exams are based on a job analysis), so our topic split is an estimate built from the reference lists DSPS prints.
Note: DSPS publishes the question counts, time limits and permitted references but no content outline or topic weights, so our topic split is an estimate. Counts come from DSPS's exam table and were not checked against Pearson.
Frequently asked questions
Do I have to take the industrial journeyman exam?
Not if you complete an industrial electrical apprenticeship approved by the U.S. Department of Labor or the Wisconsin Department of Workforce Development. Otherwise you need 5 years of 1,000 hours of industrial electrical wiring and the exam.
Which NEC edition is on the exam?
The 2023 NEC. SPS 316.007 adopts it, and Wisconsin's changes are in SPS 316.080 and following.
How much does the exam cost?
$95 at Pearson VUE or $30 at a DSPS exam site. The credential fee is $100 plus a $35 application fee.
Free questions with answers
Show all 10 free questions and answers
What is the synchronous speed of an 8-pole, 60-hertz three-phase induction motor?
Answer: 900 rpm
Synchronous speed in rpm = 120 x frequency / number of poles = 120 x 60 / 8 = 900 rpm. 1,800 rpm is a 4-pole machine, 1,200 rpm is 6-pole, and 3,600 rpm is 2-pole.
Reference: Electrical theory (Ohm's law and power formulas), Synchronous speed = 120 x f / poles
A feeder-supplied distribution switchboard in a plant is rated 1,200 amperes. In addition to the general arc-flash warning, what does 110.16(B) require?
Answer: A permanent arc-flash label applied in the field or at the factory, including the date the label was applied
Section 110.16(B) adds, for other than dwelling units, a permanent arc-flash label on service equipment and feeder-supplied equipment rated 1,000 amperes or more. The label follows applicable industry practice, includes the date applied, and must meet 110.21(B). It covers feeder-supplied equipment, not only the service.
Reference: NFPA 70 National Electrical Code (NEC), 2023 edition, 110.16(B)
Which of these services must have ground-fault protection of equipment under 230.95, assuming no exception applies?
Answer: A 480Y/277-volt, three-phase, 4-wire solidly grounded wye service with a 1,200-ampere service disconnect
Section 230.95 applies to solidly grounded wye services of more than 150 volts to ground but not over 1,000 volts phase-to-phase, with each service disconnect rated 1,000 amperes or more. Only the 480Y/277 V (277 V to ground) 1,200 A service meets all three conditions. 208Y/120 V is only 120 V to ground, the delta service is not a wye, and 800 A is below the 1,000 A threshold.
Reference: NFPA 70 National Electrical Code (NEC), 2023 edition, 230.95
Unless it is designed and marked for a different interval, what is the maximum distance between supports for a busway under 368.30?
Answer: 5 feet
Section 368.30 says busways are to be securely supported at intervals not exceeding 5 ft unless otherwise designed and marked. The 10 ft and 15 ft figures belong to other raceways (the 10 ft limit between wireway supports and the 15 ft vertical wireway support interval in Article 376).
Reference: NFPA 70 National Electrical Code (NEC), 2023 edition, 368.30
A riser busway penetrates three dry floors of a manufacturing plant that qualifies as an industrial establishment. Which requirement in 368.10(C)(2)(b) applies to the floor openings?
Answer: The 4-inch curb required around the floor openings in other types of buildings is not required in an industrial establishment
Section 368.10(C)(2)(b) requires a minimum 4-in. curb, within 12 in. of the opening, where a vertical riser busway penetrates two or more dry floors, but the requirement applies in other than industrial establishments. The curb keeps liquids from entering the opening, and industrial buildings are excluded from the rule.
Reference: NFPA 70 National Electrical Code (NEC), 2023 edition, 368.10(C)(2)(b)
A 40-horsepower, 460-volt, three-phase motor (Table 430.250 full-load current 52 A) is fed by an adjustable-speed drive that is not marked 'Suitable for Output Motor Conductor Protection'. What is the minimum ampacity of the conductors between the drive and the motor under 430.122(B)?
Answer: 65 amperes
The conductors between the power conversion equipment and the motor must have an ampacity of at least 125 percent of the motor full-load current from 430.6(A) or (B) (430.122(B)). 1.25 x 52 A = 65 A. 52 A uses 100 percent, 58 A is a rounded 111 percent, and 78 A applies 150 percent.
Reference: NFPA 70 National Electrical Code (NEC), 2023 edition, 430.122(B), Table 430.250
A power factor correction capacitor is connected at the motor terminals, on the load side of the motor overload protective device. Under the exception to 460.8(B), what applies?
Answer: A separate overcurrent device is not required for that capacitor
Section 460.8(B) normally requires an overcurrent device in each ungrounded conductor for each capacitor bank, rated as low as practicable. The exception says a separate overcurrent device is not required for a capacitor connected on the load side of a motor overload protective device. Per 460.9, the overload setting must then be based on the improved power factor.
Reference: NFPA 70 National Electrical Code (NEC), 2023 edition, 460.8(B), Exception; 460.9
Under 500.6(A), which gas is the Class I, Group A material?
Answer: Acetylene
Section 500.6(A)(1) defines Group A as acetylene. Hydrogen is the typical Group B material, ethylene is the typical Group C material and propane is the typical Group D material, so equipment must be identified for the specific group of gas that will be present.
Reference: NFPA 70 National Electrical Code (NEC), 2023 edition, 500.6(A)(1)
An industrial machine has resistance heating loads of 16 A, a highest-rated motor of 20 A, and other motors and apparatus of 9 A and 5 A, all of which can run at the same time. Under 670.4(A), what is the minimum supply conductor ampacity?
Answer: 59 amperes (1.25 x 16 + 1.25 x 20 + 9 + 5)
Section 670.4(A) requires 125 percent of the heating load full-load current, plus 125 percent of the highest rated motor, plus the sum of the full-load currents of all other connected motors and apparatus that may operate at the same time. 1.25 x 16 = 20; 1.25 x 20 = 25; 9 + 5 = 14. Total = 20 + 25 + 14 = 59 A. 50 A uses no 125 percent factors, 54 A applies it only to the motor, and 63 A applies 125 percent to everything (1.25 x 50 = 62.5).
Reference: NFPA 70 National Electrical Code (NEC), 2023 edition, 670.4(A)
To facilitate inspection of a permitted installation, what do SPS 316.013(3)(b)1. and 2. require of the wiring before the inspection is done?
Answer: It must remain accessible and exposed, and may not be energized
Under SPS 316.013(3)(b), electrical wiring must stay accessible and exposed, and may not be energized, to allow inspection. The exception in (c) lets wiring other than a service be concealed or energized if the agency has not completed inspection within 2 business days after notice or by agreement.
Reference: Wis. Admin. Code SPS 316, SPS 316.013(3)(b)
Sources
- DSPS: trades exam information and fee schedule (opens in a new tab)
- Pearson VUE: Wisconsin DSPS Trades candidate handbook (opens in a new tab)
- Wisconsin Admin. Code chapter SPS 316 (electrical) (opens in a new tab)
Questions last verified November 10, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.