Requirements at a glance
| Agency | West Virginia Contractor Licensing Board (Division of Labor); exams by Prov |
|---|---|
| When you need it | Contracting work of $5,000 or more residential or $25,000 or more commercial (W. Va. Code 30-42-3) |
| Exams | Manufactured home installation contractor exam: 65 questions, 3 hours, 70%, plus the Contractor Licensing Act exam |
| Books allowed | 24 CFR 3285 (printed hardcopy required), West Virginia Code 21-9 |
| Fees | $59.95 per Prov exam; $90 annual Board license fee (28 CSR 2, 5.5) |
Contractors applying for the West Virginia Manufactured Home Installation classification: soil analysis, site preparation, foundations, placement, utility connection, anchoring, ground moisture control and finish carpentry. It is in addition to any license required under W. Va. Code 21-9-1.
Official links
- West Virginia Contractor Licensing Board (Division of Labor) (opens in a new tab)
- Contractor Licensing Board candidate bulletin (Prov) (opens in a new tab)
- Register for your exam with Prov (opens in a new tab)
- West Virginia Code 30-42 (Contractor Licensing Act) (opens in a new tab)
- 28 CSR 2 (Contractor Licensing Board rule) (opens in a new tab)
How to get licensed, step by step
Pick your classification
Every contractor passes the Contractor Licensing Act exam plus a trade exam where one exists. Check the classification definitions in 28 CSR 2.
West Virginia Contractor Licensing Board (Division of Labor) (opens in a new tab)28 CSR 2 (Contractor Licensing Board rule) (opens in a new tab)
Apply to the Board
Apply through the Contractor Licensing Board at the Division of Labor, (304) 558-7890.
West Virginia Contractor Licensing Board (Division of Labor) (opens in a new tab)
Take your exams with Prov
Register at provexam.com or call (866) 720-7768. 3 hours per exam, 70% to pass, score on the spot, no waiting period before a retake.
Register for your exam with Prov (opens in a new tab)Contractor Licensing Board candidate bulletin (Prov) (opens in a new tab)
Get licensed
Send your results and the license fee to the Board.
West Virginia Contractor Licensing Board (Division of Labor) (opens in a new tab)West Virginia Code 30-42 (Contractor Licensing Act) (opens in a new tab)
How to prepare
- 24 CFR 3285 is 83% of the questions and you must bring a printed copy: tab the anchoring, foundation, piers and skirting sections.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below, and most questions come from 24 CFR 3285. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
24 CFR Part 3285, Model Manufactured Home Installation StandardsEssential
About 83% of the manufactured home exam. You must bring a printed hardcopy; online access is not available during the test.
West Virginia Manufactured Housing Construction and Safety Standards Act (W. Va. Code Chapter 21, Article 9)
About 9% of the manufactured home exam.
Official reference list (as published by the testing agency)
- 24 CFR Part 3285, Model Manufactured Home Installation Standards (73 pages), about 83% of questions. Bring a hardcopy; you cannot access it online during the test.
- West Virginia Manufactured Housing Construction and Safety Standards Act (W. Va. Code Chapter 21, Article 9), about 9%
What's on the exam
Official content outline from Prov, Inc. (number of questions per topic):
| Topic | Questions | |
|---|---|---|
| Anchors & Tie Downs | 12 | |
| Connections | 3 | |
| Footing & Foundations | 12 | |
| Placement | 3 | |
| Plan Reading & Estimating | 3 | |
| Sitework | 6 | |
| Skirting & Ventilation | 8 | |
| Support & Leveling | 12 | |
| Manufactured Home Administration | 6 |
Exam day details
- Administered by Prov, Inc. for the West Virginia Contractor Licensing Board.
- Fee: $59.95 to Prov per exam, whether first try or retake. Licensing board application and license fees are separate.
- 65 questions in 3 hours; 70% to pass.
- Pass the Contractor Licensing Act exam as well; every West Virginia contractor takes it.
- Open book: bring the references the bulletin lists (any older or newer edition of the same book is allowed, but the exam is scored on the edition shown in the bulletin). Prepare them only by highlighting and attaching permanent tabs; handwritten notes, moveable tabs and sticky notes are not allowed.
- Computer-based at a Prov testing center or at home with Examroom remote proctoring. Only a simple 4-function calculator is allowed.
- You get your score at the testing center. There is no waiting period between attempts and no limit on retakes; retake fees equal the first-try fee.
- Change or cancel at least 3 business days before your test date or you forfeit the fee. You can ask for a review of your exam after failing it at least twice with a score within 10 points of 70%.
Frequently asked questions
What's on the West Virginia manufactured home installation exam?
65 questions: anchors and tie downs 12, footing and foundations 12, support and leveling 12, skirting and ventilation 8, sitework 6, manufactured home administration 6, connections 3, placement 3 and plan reading and estimating 3.
Can I use 24 CFR 3285 on my screen during the test?
No. The bulletin says you must bring a printed hardcopy of 24 CFR 3285; online access is not available during testing.
Free questions with answers
Show all 10 free questions and answers
Under 24 CFR 3285.402(c)(1), what minimum ultimate load and working load must each installed ground anchor be capable of resisting, unless a reduced capacity is noted in the tables?
Answer: 4,725 lb ultimate and 3,150 lb working
Section 3285.402(c)(1) requires ground anchors to resist a minimum ultimate load of 4,725 lb and a working load of 3,150 lb as installed. The working load is the ultimate load divided by a safety factor of 1.5, so the working value can never exceed the ultimate value.
Reference: 24 CFR Part 3285 (eCFR), Section 3285.402(c)(1)
A ground anchor assembly is tested and its ultimate anchor load is 6,000 lb. Using the 1.5 factor of safety in 24 CFR 3285.402(b)(2), what is its working anchor load?
Answer: 4,000 lb
Working anchor load = ultimate load / 1.5 = 6,000 / 1.5 = 4,000 lb. Multiplying by 1.5 gives 9,000 lb, which is the wrong direction. 3,150 lb is the minimum required working load for any anchor, not this anchor's value.
Reference: 24 CFR Part 3285 (eCFR), Section 3285.402(b)(2)
Under 24 CFR 3285.312(a), what must support every pier of a manufactured home?
Answer: A footing placed on undisturbed soil or fill compacted to 90 percent of maximum relative density
Section 3285.312(a) states that a footing must support every pier and that footings are placed on undisturbed soil or fill compacted to 90 percent of maximum relative density.
Reference: 24 CFR Part 3285 (eCFR), Section 3285.312(a)
How must hollow-cell concrete blocks in a pier be stacked per 24 CFR 3285.304(a)(2) and (a)(3)?
Answer: Cells aligned vertically, with each layer at right angles to the one below when side-by-side
Blocks are stacked with hollow cells aligned vertically so loads go through the webs, and when blocks are stacked side by side each layer is placed at right angles to the preceding layer (Figure B to 3285.306).
Reference: 24 CFR Part 3285 (eCFR), Section 3285.304(a)(2)-(3)
Which material must be removed from the areas where footings will be placed, according to 24 CFR 3285.201?
Answer: Organic material such as grass, roots, twigs and wood scraps
To help prevent settling, all organic material must be removed from footing areas. The site is then graded or prepared for drainage under 3285.203.
Reference: 24 CFR Part 3285 (eCFR), Section 3285.201
A 28 ft by 60 ft home has skirting and no ground vapor retarder. What minimum net ventilation opening area is required under 24 CFR 3285.505(a)?
Answer: 11.2 square feet
Floor area = 28 x 60 = 1,680 ft2. Without a vapor retarder the rate is 1 ft2 per 150 ft2: 1,680 / 150 = 11.2 ft2. With a retarder the rate would be 1,680 / 1,500 = 1.12 ft2.
Reference: 24 CFR Part 3285 (eCFR), Section 3285.505(a)
In a flood hazard area, how must appliances installed on the site (such as an outdoor air conditioner) be set per 24 CFR 3285.102(d)(2)?
Answer: Anchored and elevated to or above the lowest floor elevation of the home
Appliances must be anchored and elevated at or above the lowest elevation of the lowest floor, and air inlets and exhausts must also be at or above that elevation.
Reference: 24 CFR Part 3285 (eCFR), Section 3285.102(d)(2)
What type of shutoff valve must be installed between the water supply and the home inlet under 24 CFR 3285.603(c)?
Answer: An identified, accessible full-flow gate or ball valve, or equivalent
The mandatory shutoff must be identified and accessible, with the water riser located under or adjacent to the home, and must be a full-flow gate or ball valve or equivalent.
Reference: 24 CFR Part 3285 (eCFR), Section 3285.603(c)
A home is 56 ft long. Under 24 CFR 3285.310(c), piers under one main rail must be no more than 24 inches from each end and no more than 120 inches center to center. What is the minimum number of piers under that rail?
Answer: 7
Length = 56 x 12 = 672 in. End piers at 24 in. from each end leave 672 - 48 = 624 in. between them. 624 / 120 = 5.2, which rounds up to 6 spaces, so 6 + 1 = 7 piers. Six piers would require 5 spaces of up to 120 in., which is only 600 in.
Reference: 24 CFR Part 3285 (eCFR), Section 3285.310(c)
Under W. Va. Code 21-9-9, until what date each year does a contractor license issued under the Manufactured Housing Construction and Safety Standards Act remain valid?
Answer: June 30
Section 21-9-9(b) says all licenses expire on June 30 of each year unless sooner revoked or suspended, and licenses must be granted or refused within 30 days after a proper and complete application.
Reference: West Virginia Code Chapter 21, Article 9, Code 21-9-9(b)
Sources
- Prov: West Virginia Contractor Licensing Board Candidate Information Bulletin (CIB 2026.05.07) (opens in a new tab)
- West Virginia Contractor Licensing Board (Division of Labor) (opens in a new tab)
- Prov: register for West Virginia exams (opens in a new tab)
- West Virginia Code Chapter 30, Article 42 (Contractor Licensing Act) (opens in a new tab)
- 28 CSR 2: Contractor Licensing Board rule (opens in a new tab)
- 24 CFR Part 3285 (eCFR) (opens in a new tab)
- West Virginia Code Chapter 21, Article 9 (Manufactured Housing) (opens in a new tab)
Questions last verified November 17, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.