The Prov exam for West Virginia general building contractors: 80 open-book questions on plan reading, concrete, structural steel, masonry and carpentry, with the 2018 IBC as the main reference.

Questions
80
Time limit
3 hours
Passing score
70%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10Concrete

Under a heated warehouse slab on grade, which vapor retarder does IBC 1907.1 call for unless an approved equivalent or an exception applies?

Requirements at a glance

AgencyWest Virginia Contractor Licensing Board (Division of Labor); exams by Prov
When you need itContracting work of $5,000 or more residential or $25,000 or more commercial (W. Va. Code 30-42-3)
ExamsGeneral building contractor exam: 80 questions, 3 hours, 70%, plus the Contractor Licensing Act exam
Books allowedIBC 2018, Commercial Building Contractor study guide 2024, Study Guide for Structural Steel, Concrete Construction Level 2
Fees$59.95 per Prov exam; $90 annual Board license fee (28 CSR 2, 5.5)

Contractors applying for the West Virginia General Building Contractor classification, a commercial, business or industrial classification that applies to work using more than two contractor classifications.

How to get licensed, step by step

  1. Pick your classification

    Every contractor passes the Contractor Licensing Act exam plus a trade exam where one exists. Check the classification definitions in 28 CSR 2.

    West Virginia Contractor Licensing Board (Division of Labor) (opens in a new tab)28 CSR 2 (Contractor Licensing Board rule) (opens in a new tab)

  2. Apply to the Board

    Apply through the Contractor Licensing Board at the Division of Labor, (304) 558-7890.

    West Virginia Contractor Licensing Board (Division of Labor) (opens in a new tab)

  3. Take your exams with Prov

    Register at provexam.com or call (866) 720-7768. 3 hours per exam, 70% to pass, score on the spot, no waiting period before a retake.

    Register for your exam with Prov (opens in a new tab)Contractor Licensing Board candidate bulletin (Prov) (opens in a new tab)

How to prepare

  • The 2018 IBC supplies about 64% of the questions: tab the construction-type, concrete, masonry, steel and wood chapters.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the 2018 IBC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

Official reference list (as published by the testing agency)
  • International Building Code 2018 (ICC), about 64% of questions
  • Study Guide for Commercial Building Contractor, 2024 (Pearson), about 26%
  • Study Guide for Structural Steel, 2012 (Pearson), about 10%
  • Concrete Construction Level 2, 2021 (NCCER/Pearson), about 4%

What's on the exam

Official content outline from Prov, Inc. (number of questions per topic):

TopicQuestions
Plan Reading and Estimating8
Sitework8
Concrete12
Masonry8
Structural Steel12
Carpentry8
Roofing4
Doors Windows & Stairs4
Interior Finish4
Exterior Finish4
Safety-OSHA8

Exam day details

  • Administered by Prov, Inc. for the West Virginia Contractor Licensing Board.
  • Fee: $59.95 to Prov per exam, whether first try or retake. Licensing board application and license fees are separate.
  • 80 questions in 3 hours; 70% to pass.
  • Pass the Contractor Licensing Act exam as well; every West Virginia contractor takes it.
  • Open book: bring the references the bulletin lists (any older or newer edition of the same book is allowed, but the exam is scored on the edition shown in the bulletin). Prepare them only by highlighting and attaching permanent tabs; handwritten notes, moveable tabs and sticky notes are not allowed.
  • Computer-based at a Prov testing center or at home with Examroom remote proctoring. Only a simple 4-function calculator is allowed.
  • You get your score at the testing center. There is no waiting period between attempts and no limit on retakes; retake fees equal the first-try fee.
  • Change or cancel at least 3 business days before your test date or you forfeit the fee. You can ask for a review of your exam after failing it at least twice with a score within 10 points of 70%.

Frequently asked questions

What's on the West Virginia general building contractor exam?

80 questions: concrete 12, structural steel 12, plan reading and estimating 8, sitework 8, masonry 8, carpentry 8, safety (OSHA) 8, roofing 4, doors, windows and stairs 4, interior finish 4 and exterior finish 4.

Which book matters most?

The 2018 International Building Code, about 64% of the questions, followed by the Commercial Building Contractor study guide (26%).

Free questions with answers

Show all 10 free questions and answers
  1. Under a heated warehouse slab on grade, which vapor retarder does IBC 1907.1 call for unless an approved equivalent or an exception applies?

    Answer: 6-mil polyethylene with joints lapped at least 6 inches

    Section 1907.1 requires a 6-mil (0.006 inch) polyethylene vapor retarder with joints lapped not less than 6 inches between the base course or subgrade and the slab. A thinner film, short laps or butted joints do not meet the section. An exception applies only where moisture migration will not harm the occupancy.

    Reference: 2018 International Building Code, Section 1907.1

  2. Under IBC 2205.1, which standard governs the design, fabrication and erection of structural steel elements in buildings?

    Answer: AISC 360

    Section 2205.1 requires structural steel elements to be designed, fabricated and erected in accordance with AISC 360. AISC 341 is the seismic provisions (2205.2), AISI S100 covers cold-formed steel (2210.1) and SJI specifications cover open-web joists (2207.1).

    Reference: 2018 International Building Code, Section 2205.1

  3. A column carries 45,000 pounds of total load and will bear on sand (SW class) at the Table 1806.2 presumptive pressure. What is the minimum footing bearing area?

    Answer: 22.5 square feet

    Table 1806.2 gives 2,000 psf for sand, silty sand and clayey sand classes (SW, SP, SM, SC, GM, GC). Area = load / pressure = 45,000 / 2,000 = 22.5 square feet. 30 square feet results from using the clay value of 1,500 psf, and 15 square feet from using 3,000 psf for gravel.

    Reference: 2018 International Building Code, Table 1806.2

  4. On a site plan drawn at 1/8 inch = 1 foot, a building face scales 3 1/2 inches. How long is that face?

    Answer: 28 feet

    At 1/8 inch per foot each inch is 8 feet. 3.5 in x 8 = 28 feet. 14 feet would be a 1/4-inch scale reading and 56 feet would come from a 1/16-inch scale.

    Reference: General trade practice: architect's scale reading, General trade practice: architect's scale reading

  5. Under IBC 2103.1.1, when may second-hand masonry units be reused?

    Answer: When they meet the requirements for new units, are whole and sound, and have old mortar cleaned off

    Section 2103.1.1 says second-hand units shall not be reused unless they conform to the requirements of new units, are whole and sound, free from cracks and defects that interfere with laying, and have old mortar cleaned from them. There is no age or waiver provision.

    Reference: 2018 International Building Code, Section 2103.1.1

  6. Under IBC 2304.2, computations to determine the required size of wood structural members are based on which dimensions?

    Answer: Net (actual) dimensions

    Section 2304.2 says computations to determine the required sizes of members are based on net dimensions (actual sizes) and not nominal sizes. A nominal 2x4 is really 1 1/2 by 3 1/2 inches, so strength and fit are checked with the actual size.

    Reference: 2018 International Building Code, Section 2304.2

  7. In which case is a roof recover (new roof over old) NOT permitted under IBC 1511.3.1.1?

    Answer: When the existing roof already has two or more applications of roof covering

    Section 1511.3.1.1 prohibits a recover where the existing covering is water soaked or deteriorated, where it is slate, clay, cement or asbestos-cement tile, or where the roof already has two or more applications of any type of covering. A second layer over a single layer is generally allowed.

    Reference: 2018 International Building Code, Section 1511.3.1.1

  8. For a commercial egress stair, what do the maximum riser height and minimum rectangular tread depth in IBC 1011.5.2 allow?

    Answer: 7 inches maximum riser and 11 inches minimum tread

    Section 1011.5.2 sets riser height at 7 inches maximum and 4 inches minimum, and rectangular tread depth at 11 inches minimum. The 7 3/4 and 10 inch limits apply only inside Group R-3 and dwelling units of R-2.

    Reference: 2018 International Building Code, Section 1011.5.2

  9. Under IBC 803.1.2, what flame spread index range defines a Class A interior wall and ceiling finish?

    Answer: 0 to 25

    Section 803.1.2 groups finishes tested to ASTM E84 or UL 723: Class A is flame spread index 0-25, Class B is 26-75 and Class C is 76-200, each with a smoke-developed index of 0-450. The 0-450 figure is the smoke-developed limit, not the flame spread range.

    Reference: 2018 International Building Code, Section 803.1.2

  10. Under 29 CFR 1926.502(b), what is the required height of the top rail of a guardrail system above the walking/working level?

    Answer: 42 inches, plus or minus 3 inches

    Section 1926.502(b)(1) sets the top edge height of top rails at 42 inches plus or minus 3 inches. The system must also withstand at least 200 pounds applied within 2 inches of the top edge (b)(3), and midrails are needed where there is no wall at least 21 inches high (b)(2).

    Reference: 29 CFR 1926, 29 CFR 1926.502(b)(1)