Requirements at a glance
| Agency | South Carolina Department of Labor, Licensing and Regulation (LLR), Contractor's Licensing Board; exams by PSI |
|---|---|
| Experience | The primary qualifying party needs 2 of the last 5 years of full-time experience in the classification, in a management role (S.C. Code 40-11-230) |
| Exams | Packaged Equipment-Heat Pump: 80 questions, 4 hours, 70%, plus Business Management and Law (Commercial); 70% on each |
| Books allowed | IMC and IFGC 2021 or 2024 (SC), ACCA Manuals N, D and J, Modern Refrigeration and Air Conditioning |
| Fees | PSI exam fees ($64 to $78 per exam), plus the Board's application and license fees and a financial statement or bond |
Applicants for a South Carolina Contractor's Licensing Board mechanical license in the Packaged Equipment-Heat Pump classification.
Official links
How to get licensed, step by step
Check the work needs a license
South Carolina requires a Contractor's Licensing Board license for commercial work above $10,000 in job cost (S.C. Code 40-11-30). Commercial licenses also cover residential work.
SC Contractor's Licensing Board (LLR) (opens in a new tab)S.C. Code Title 40 Chapter 11 (contractors) (opens in a new tab)
Apply to the Board
Apply to the Contractor's Licensing Board for an eligibility letter before you register with PSI.
Schedule Business and Law and the packaged equipment-heat pump exam with PSI
Register for each exam separately. You may take each trade exam twice in 12 months, then once every six months. Commercial Business and Law has no such limit.
Schedule with PSI (commercial contractors) (opens in a new tab)
Apply for the license
After you pass, the business entity applies with its primary qualifying party, a financial statement or bond, and the license fee. The group (1 to 5) sets the dollar limit of work you may bid.
SC Contractor's Licensing Board (LLR) (opens in a new tab)S.C. Code Title 40 Chapter 11 (contractors) (opens in a new tab)
How to prepare
- Code editions are changing. From November 1, 2026 PSI accepts the 2021 or the 2024 South Carolina codes (ICC codes with state modifications) and the 2023 or the 2020 NEC. After July 1, 2027 only the 2024 codes and the 2023 NEC. Bring one edition you know well and expect questions that read the same in both.
- Tab your books before exam day: highlighting, underlining and permanent tabs are allowed, but sticky notes and writing during the exam are not.
- Load calculations (8), air conditioning systems (6) and heat pumps (5) are the largest topics: practice Manual J and N methods with the book open.
- Ducts add up to about 20 questions across duct systems, conversions, components, metal ducts and sheet metal devices.
- A handful of questions cover basic electrical knowledge, fire rated construction and plan reading.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below, and most questions come from the SC IMC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
International Mechanical Code (IMC), 2021 or 2024 edition with South Carolina modificationsEssential
On PSI's list. Ducts, ventilation, equipment, venting and piping for the air conditioning and residential HVAC exams.
ICC store (opens in a new tab)Read free (UpCodes) (opens in a new tab)
International Fuel Gas Code (IFGC), 2021 or 2024 edition with South Carolina modifications
On PSI's list. Gas piping sizing, venting, combustion air and appliance installation.
ICC store (opens in a new tab)Read free (UpCodes) (opens in a new tab)
Modern Refrigeration and Air Conditioning (Goodheart-Willcox)
On PSI's list (21st or 22nd Edition for air conditioning; 19th or 20th for residential HVAC). Refrigeration cycle, components, controls and piping.
Official reference list (as published by the testing agency)
- International Mechanical Code (IMC), 2021 or 2024 edition with South Carolina modifications
- International Fuel Gas Code (IFGC), 2021 or 2024 edition with South Carolina modifications
- ACCA Manual N, 5th Edition; Manual D, 3rd Edition; Manual J, 8th Edition; Trane and ACCA ductulators
- Modern Refrigeration and Air Conditioning, 21st or 22nd Edition; Pipefitter's Handbook, 3rd Edition; Whitman, Refrigeration and Air Conditioning Technology, 6th Edition; Trane Air Conditioning Manual; ASHRAE Handbook of Fundamentals 1997; 29 CFR Part 1926 (all on PSI's list)
What's on the exam
Official content outline from PSI Services (number of questions per topic):
| Topic | Questions | |
|---|---|---|
| General Piping | 1 | |
| General Tubing | 1 | |
| Pipe Assembly | 1 | |
| Piping Systems | 2 | |
| Drain Piping | 1 | |
| Valves | 1 | |
| Piping Insulation | 1 | |
| Hangers and Supports | 1 | |
| Mechanical Sound, Vibration, and Seismic Control | 1 | |
| Heating and Cooling Principles | 2 | |
| Refrigerants | 1 | |
| Load Calculations | 8 | |
| Heating and Cooling Equipment | 1 | |
| Testing, Adjusting, and Balancing | 2 | |
| HVACR Control Fundamentals | 1 | |
| Control Schematics and Wiring Diagrams | 1 | |
| HVACR Control Systems | 1 | |
| Machine Room | 1 | |
| Air Conditioning Systems | 6 | |
| Heat Pumps | 5 | |
| Furnaces | 2 | |
| Chimneys, Flues, Vents, and Vent Connectors | 3 | |
| Combustion Air | 2 | |
| General Fuel Knowledge | 1 | |
| Natural Gas | 1 | |
| General Duct Systems Knowledge and Principles | 4 | |
| Duct Conversion/Equivalencies | 4 | |
| Mechanical Sheet Metal Devices/Systems | 2 | |
| Duct System Components | 5 | |
| Metal Ducts | 3 | |
| Fiberglass Ducts | 1 | |
| Filtering Systems | 1 | |
| Ventilation Equipment and Devices | 2 | |
| Exhaust Systems | 2 | |
| General Electrical Knowledge | 2 | |
| Requirements for Electrical Installations | 1 | |
| Electrical/Electronic Fundamentals | 1 | |
| Safety | 2 | |
| Fire Rated Construction | 1 | |
| General Plan Reading | 1 |
Exam day details
- Administered by PSI Services for the South Carolina Department of Labor, Licensing and Regulation (Contractor's Licensing Board).
- Fee: $64 to PSI. Board application and license fees are separate.
- 80 scored questions plus 1 to 10 unscored experimental items (they count against your time) in 240 minutes; 56 correct (70%).
- Code editions: from November 1, 2026 PSI accepts the 2021 or 2024 South Carolina codes (NEC 2023 or 2020); after July 1, 2027 only the 2024 codes and the 2023 NEC. Our questions are written to be correct under both.
- Open book: bring the references on PSI's list. You may highlight, underline and add permanent tabs (tabs that would tear the page if removed); sticky notes and removable tabs are not allowed.
- Apply to the Contractor's Licensing Board first. After approval you get an eligibility letter and register with PSI (855-340-3701) for each exam; the registration confirmation is valid 1 year or until a classification has been failed twice.
- You may take each trade exam twice in 12 months, then once every six months.
- Every Contractor's Licensing Board license needs the Business Management and Law exam and the technical exam for the classification, 70% on each (S.C. Code 40-11-230).
Frequently asked questions
What's on the South Carolina packaged equipment-heat pump exam?
80 scored questions, led by load calculations 8, air conditioning systems 6, heat pumps 5, duct system components 5, general duct systems knowledge and principles 4, duct conversions/equivalencies 4 and 30 smaller topics.
Does it include electrical questions?
A few: general electrical knowledge 2, requirements for electrical installations 1 and electrical/electronic fundamentals 1.
How does it differ from the air conditioning exam?
It has more weight on packaged air conditioning systems and heat pumps and drops pumps, water treatment and air compressors.
Free questions with answers
Show all 10 free questions and answers
A hot-water pipe in a hydronic heating loop has an exterior surface temperature above 250 degrees F. What minimum clearance to combustible materials does the IMC require?
Answer: 1 inch
IMC Section 1206.5 requires hydronic pipe whose exterior temperature exceeds 250 degrees F to have at least 1 inch of clearance to combustible materials. It is a fixed code number; 6 inches is a vent-connector style clearance and does not apply to hydronic pipe.
Reference: International Mechanical Code (SC 2021 and 2024 editions), Section 1206.5
A zone has a design sensible cooling load of 36,000 Btu/h. The supply air is 20 degrees F cooler than the room. Using the 1.08 sensible heat factor, what supply airflow is required?
Answer: About 1,667 cfm
Rearranging Q = 1.08 x cfm x TD gives cfm = Q / (1.08 x TD) = 36,000 / (1.08 x 20) = 36,000 / 21.6 = 1,667 cfm. Using 1.2 instead of 1.08 gives 1,500, dividing by TD only gives 1,800, and dividing by 1.08 alone gives 33,333.
Reference: HVAC fundamentals (concept: standard-air sensible heat equation), cfm = Q / (1.08 x TD)
Without any work input, in which direction does heat naturally flow between two substances?
Answer: From a warmer substance toward a cooler one
Heat flows naturally from higher temperature to lower temperature. A refrigeration cycle moves heat the other way only by using compressor work, which is why a heat pump needs power input to lift heat from cold outdoor air to a warm building.
Reference: HVAC fundamentals (concept: second law, heat flow direction), Heat flow direction
A technician measures a suction line temperature of 52 degrees F at the evaporator outlet of a packaged unit. The suction gauge pressure converts to a saturation temperature of 40 degrees F. What is the system superheat?
Answer: 12 degrees F
Superheat is the actual suction line temperature minus the saturation temperature at suction pressure: 52 - 40 = 12 degrees F. The 40-degree figure is the saturation temperature itself, and adding the two gives 92, which has no meaning in a charge check.
Reference: Refrigeration fundamentals (concept: superheat measurement), Superheat = line temperature - saturation temperature
A heat pump delivers 36,000 Btu/h of heating while using 3.0 kW of electricity. Using 3,412 Btu/h per kW, what is the coefficient of performance (COP)?
Answer: 3.5
COP is useful heat out divided by energy in, both in the same units. Input is 3.0 kW x 3,412 = 10,236 Btu/h, so COP = 36,000 / 10,236 = 3.5. A COP of 12 is the EER-style Btu/h per watt value (36,000 / 3,000 W), and 1.0 is the COP of resistance heat.
Reference: Heat pump fundamentals (concept: COP calculation, 1 kW = 3,412 Btu/h), COP = Btu/h output / (kW x 3,412)
Air moves through a duct at 1,600 feet per minute. Using V = 4,005 x square root of VP, what is the velocity pressure?
Answer: About 0.16 inch w.c.
Rearranging, VP = (V / 4,005)^2 = (1,600 / 4,005)^2 = 0.3995^2 = 0.16 inch w.c. The 0.40 answer is V / 4,005 without squaring, and 0.64 results from doubling the velocity ratio before squaring. Velocity pressure rises with the square of velocity, so doubling velocity quadruples it.
Reference: Duct design fundamentals (concept: velocity pressure equation), VP = (V / 4,005)^2
A 14-inch round duct carries air at 800 feet per minute. The duct area is 1.069 square feet. What is the airflow?
Answer: About 855 cfm
Airflow Q = A x V = 1.069 ft2 x 800 fpm = 855 cfm. The area of a 14-inch circle is pi x (14/12)^2 / 4 = 1.069 ft2. The 640 answer results from using 0.8 ft2, 1,070 from using 1,000 fpm, and 1,720 from using 1,600 fpm.
Reference: Duct design fundamentals (concept: continuity equation Q = A x V), Q = A x V
An approved duct is run underground beneath a slab on grade for 80 feet. What total slope is the minimum drop to a drainage point, as required by the IMC?
Answer: 10 inches
IMC Section 603.8.1 requires underground ducts to slope at least 1/8 inch per foot toward a point of drainage that has access. Over 80 feet, 80 x 1/8 = 10 inches. 1/16 inch per foot gives 5 inches and 1/4 inch per foot gives 20. Section 603.8 also requires ducts without a protective coating to be encased in 2 inches of concrete.
Reference: International Mechanical Code (SC 2021 and 2024 editions), Section 603.8.1 Slope
Using the IMC single-dwelling-unit table, what minimum thickness of galvanized steel is required for a 16-inch round duct at 1-inch water gauge static pressure?
Answer: 0.019 inch
IMC Table 603.4 (ducts within single dwelling units) lists round diameters 15 to 17 inches at 1-inch w.g. as 0.019 inch galvanized (0.027 aluminum). At 1/2-inch w.g. the same size is 0.016 inch, which is the usual wrong pick. Ducts over 20 inches or above 1-inch w.g. fall under SMACNA instead.
Reference: International Mechanical Code (SC 2021 and 2024 editions), Table 603.4
A single-wall metal vent connector serves a draft-hood appliance. The vent it connects to is 18 feet tall. What is the maximum horizontal length of the connector under the IFGC?
Answer: 13.5 feet
IFGC Section 503.10.9 limits the horizontal length of a single-wall connector to 75 percent of the height of the vent or chimney: 0.75 x 18 = 13.5 feet. A Type B double-wall connector may be 100 percent (18 feet). Using 50 percent gives 9, which is a common half-rule slip.
Reference: International Fuel Gas Code (SC 2021 and 2024 editions), Section 503.10.9 Length of Vent Connector
Sources
- PSI: South Carolina Contractor's Licensing Board Candidate Information Bulletin (updated 9/15/2026) (opens in a new tab)
- South Carolina Contractor's Licensing Board (LLR) (opens in a new tab)
- South Carolina Code of Laws Title 40 Chapter 11 (contractors) (opens in a new tab)
Questions last verified November 16, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.