Question 1 of 10Piping Systems

A hot-water heating loop has a maximum system design pressure of 50 psi. What is the minimum hydrostatic test pressure and duration required by the IMC?

Requirements at a glance

AgencySouth Carolina Department of Labor, Licensing and Regulation (LLR), Contractor's Licensing Board; exams by PSI
ExperienceThe primary qualifying party needs 2 of the last 5 years of full-time experience in the classification, in a management role (S.C. Code 40-11-230)
ExamsAir Conditioning: 80 questions, 4 hours, 70%, plus Business Management and Law (Commercial); 70% on each
Books allowedIMC and IFGC 2021 or 2024 (SC), ACCA Manuals J, D and N, Modern Refrigeration and Air Conditioning and 29 CFR 1926
FeesPSI exam fees ($64 to $78 per exam), plus the Board's application and license fees and a financial statement or bond

Applicants for a South Carolina Contractor's Licensing Board mechanical license in the Air Conditioning classification.

How to get licensed, step by step

  1. Check the work needs a license

    South Carolina requires a Contractor's Licensing Board license for commercial work above $10,000 in job cost (S.C. Code 40-11-30). Commercial licenses also cover residential work.

    SC Contractor's Licensing Board (LLR) (opens in a new tab)S.C. Code Title 40 Chapter 11 (contractors) (opens in a new tab)

  2. Apply to the Board

    Apply to the Contractor's Licensing Board for an eligibility letter before you register with PSI.

    SC Contractor's Licensing Board (LLR) (opens in a new tab)

  3. Schedule Business and Law and the air conditioning exam with PSI

    Register for each exam separately. You may take each trade exam twice in 12 months, then once every six months. Commercial Business and Law has no such limit.

    Schedule with PSI (commercial contractors) (opens in a new tab)

  4. Apply for the license

    After you pass, the business entity applies with its primary qualifying party, a financial statement or bond, and the license fee. The group (1 to 5) sets the dollar limit of work you may bid.

    SC Contractor's Licensing Board (LLR) (opens in a new tab)S.C. Code Title 40 Chapter 11 (contractors) (opens in a new tab)

How to prepare

  • Code editions are changing. From November 1, 2026 PSI accepts the 2021 or the 2024 South Carolina codes (ICC codes with state modifications) and the 2023 or the 2020 NEC. After July 1, 2027 only the 2024 codes and the 2023 NEC. Bring one edition you know well and expect questions that read the same in both.
  • Tab your books before exam day: highlighting, underlining and permanent tabs are allowed, but sticky notes and writing during the exam are not.
  • Load calculations (7) are the biggest single topic: practice Manual J methods with the book open.
  • Ducts add up to about 20 questions across duct systems, conversions, components, metal ducts and sheet metal devices: tab IMC Chapter 6 and the duct tables.
  • Heat pumps (4), furnaces (2), chimneys and vents (3), combustion air (2) and fuel gas (5) come from the IMC and IFGC.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the SC IMC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

Official reference list (as published by the testing agency)
  • International Mechanical Code (IMC), 2021 or 2024 edition with South Carolina modifications
  • International Fuel Gas Code (IFGC), 2021 or 2024 edition with South Carolina modifications
  • ACCA Manual N, 5th Edition; Manual D, 3rd Edition; Manual J, 8th Edition; a duct calculator
  • Modern Refrigeration and Air Conditioning, 21st or 22nd Edition; 29 CFR Part 1926 (all on PSI's list)

What's on the exam

Official content outline from PSI Services (number of questions per topic):

TopicQuestions
General Piping1
General Tubing1
Pipe Assembly1
Piping Systems4
Drain Piping1
Valves1
Piping Specialties1
Pumps2
Piping Insulation1
Hangers and Supports1
Mechanical Sound, Vibration, and Seismic Control1
Water Treatment for Mechanical Systems1
Heating and Cooling Principles2
Refrigerants1
Load Calculations7
Heating and Cooling Equipment1
Air Compressors1
Testing, Adjusting, and Balancing2
HVACR Control Fundamentals1
Control Schematics and Wiring Diagrams1
HVACR Control Systems1
Machine Room1
Air Conditioning Systems3
Heat Pumps4
Furnaces2
Specialized Heaters2
Chimneys, Flues, Vents, and Vent Connectors3
Combustion Air2
General Fuel Knowledge1
Natural Gas2
LP Gas2
General Duct Systems Knowledge and Principles4
Duct Conversions/Equivalencies4
Mechanical Sheet Metal Devices/Systems2
Duct System Components5
Metal Ducts3
Fiberglass Ducts1
Filtering Systems1
Ventilation Equipment and Devices1
Exhaust Systems2
Safety2

Exam day details

  • Administered by PSI Services for the South Carolina Department of Labor, Licensing and Regulation (Contractor's Licensing Board).
  • Fee: $64 to PSI. Board application and license fees are separate.
  • 80 scored questions plus 1 to 10 unscored experimental items (they count against your time) in 240 minutes; 56 correct (70%) to pass.
  • Code editions: from November 1, 2026 PSI accepts the 2021 or 2024 South Carolina codes (NEC 2023 or 2020); after July 1, 2027 only the 2024 codes and the 2023 NEC. Our questions are written to be correct under both.
  • Open book: bring the references on PSI's list. You may highlight, underline and add permanent tabs (tabs that would tear the page if removed); sticky notes and removable tabs are not allowed.
  • Apply to the Contractor's Licensing Board first. After approval you get an eligibility letter and register with PSI (855-340-3701) for each exam; the registration confirmation is valid 1 year or until a classification has been failed twice.
  • You may take each trade exam twice in 12 months, then once every six months.
  • Every Contractor's Licensing Board license needs the Business Management and Law exam and the technical exam for the classification, 70% on each (S.C. Code 40-11-230).

Frequently asked questions

What's on the South Carolina air conditioning exam?

80 scored questions, led by Load Calculations 7, duct system components 5, piping systems 4, heat pumps 4, general duct systems knowledge and principles 4, duct conversions/equivalencies 4, air conditioning systems 3, chimneys, flues, vents, and vent connectors 3 and 33 smaller topics.

What are the biggest sections of the South Carolina air conditioning exam?

Load calculations 7, duct system components 5, heat pumps 4, piping systems 4, general duct knowledge 4 and duct conversions 4.

Does the air conditioning exam cover heating?

It includes furnaces, specialized heaters, chimneys and vents, combustion air and fuel gas. Heating is also a separate South Carolina classification.

Free questions with answers

Show all 10 free questions and answers
  1. A hot-water heating loop has a maximum system design pressure of 50 psi. What is the minimum hydrostatic test pressure and duration required by the IMC?

    Answer: 100 psi for at least 15 minutes

    IMC 1208.1 requires a hydrostatic test at 1.5 times the maximum design pressure but never less than 100 psi, held at least 15 minutes. 1.5 x 50 = 75 psi, which is below the 100 psi floor, so 100 psi governs. The 75 psi choices ignore the minimum.

    Reference: 2021 International Mechanical Code (SC edition), Section 1208.1

  2. A closed-loop pump gauge shows a differential pressure of 30 psi across the pump. What is that differential in feet of water head? (Use 2.31 feet of water per psi.)

    Answer: 69.3 feet

    One psi equals 2.31 feet of water, so 30 psi x 2.31 = 69.3 feet. Multiplying by 0.433 (the psi-per-foot value) gives 13.0 feet, which is converting in the wrong direction. Doubling the result gives 138.6 feet.

    Reference: Hydronic pump head conversion (general practice), 1 psi = 2.31 ft of water

  3. An exterior wall is 8 ft high and 50 ft long and contains 60 ft2 of windows. The wall assembly (excluding windows) has an overall R-value of 17 (including air films). Outdoor design temperature is 95 degrees F and indoor is 75 degrees F. What is the conductive heat gain through the opaque wall using Q = A x dT / R?

    Answer: 400 BTU/h

    Net opaque area = 8 x 50 = 400 ft2 minus 60 ft2 of windows = 340 ft2. Temperature difference = 95 - 75 = 20 degrees F. Q = 340 x 20 / 17 = 400 BTU/h. Using the gross 400 ft2 gives 471, using 95 degrees F as the difference gives 1,900, and leaving out R gives 6,800.

    Reference: Standard HVAC load calculation practice, Conduction: Q = A x dT / R

  4. Air moves through a duct at 2,000 feet per minute. What is the velocity pressure? (VP = (V/4005)^2)

    Answer: 0.25 inch w.g.

    V/4005 = 2,000 / 4,005 = 0.499. Squaring gives 0.249, or about 0.25 inch w.g. Forgetting to square leaves 0.50, which is the most common slip. The 0.12 and 1.00 choices are halves and doubles that do not come from the formula.

    Reference: Duct design fundamentals (general practice), Velocity pressure: VP = (V/4005)^2

  5. What does the equivalent round diameter of a rectangular duct represent?

    Answer: A round duct that has the same friction loss at the same airflow

    The equal-friction equivalent diameter is based on matching friction loss for the same airflow, which is why it is used with ductulator charts. A round duct with the same area would carry the same air at the same velocity, but because its perimeter is smaller it would have lower friction than the rectangular duct.

    Reference: Duct design fundamentals (general practice), Equivalent diameter (equal friction)

  6. What does the IMC say about the length of a flexible air connector?

    Answer: It is limited to 14 feet

    IMC 603.6.2.1 limits flexible air connectors to 14 feet. Flexible air ducts, by contrast, are not limited in length under 603.6.1.1 in the 2021 and 2024 editions. Both must be listed and labeled as Class 0 or Class 1 (UL 181).

    Reference: 2021 International Mechanical Code (SC edition), Section 603.6.2.1

  7. In a single dwelling unit, what is the minimum thickness of a 16-inch round galvanized steel duct operating at a static pressure of 1 inch w.g. under the IMC's simplified table?

    Answer: 0.019 inch

    IMC Table 603.4 lists round galvanized ducts of 15 to 17 inches at 0.016 inch for 1/2-inch w.g. and 0.019 inch for 1-inch w.g. The 0.016 inch value is the 1/2-inch w.g. column, and 0.024 inch applies to 18-inch and larger sizes at 1 inch w.g.

    Reference: 2021 International Mechanical Code (SC edition), Table 603.4

  8. A single-wall vent connector serves a draft-hood furnace. The vent it connects to is 20 feet tall. What is the maximum horizontal length of the connector?

    Answer: 15 feet

    IFGC 503.10.9 limits a single-wall connector to 75 percent of the vent or chimney height: 0.75 x 20 = 15 feet. A Type B double-wall connector may be 100 percent of the height, which would give 20 feet. Engineered systems are excepted.

    Reference: 2021 International Fuel Gas Code (SC edition), Section 503.10.9

  9. On a system with a condensing saturation temperature of 112 degrees F, the liquid line temperature at the condenser outlet is 100 degrees F. What is the subcooling?

    Answer: 12 degrees F

    Subcooling equals saturation temperature at condensing pressure minus the actual liquid line temperature: 112 - 100 = 12 degrees F. Liquid that is cooler than saturation is subcooled. The 24 and 88 values are arithmetic errors.

    Reference: Standard HVAC/refrigeration practice, Subcooling = saturation temperature - liquid line temperature

  10. A heat pump delivers 36,000 BTU/h of heating while drawing 3.0 kW. What is the coefficient of performance (COP)? (1 kW = 3,412 BTU/h)

    Answer: 3.5

    Electrical input = 3.0 x 3,412 = 10,236 BTU/h. COP = 36,000 / 10,236 = 3.5. The 12.0 value is the Btu/h-per-watt efficiency ratio (EER-style) and 10.6 comes from dividing by 3,412 without converting kW.

    Reference: Standard HVAC/refrigeration practice, COP = output Btu/h / (3,412 x input kW)