Oregon licensing exam

Oregon Limited Renewable Energy Technician Exam: Practice Test & Licensing Guide

The Oregon Building Codes Division Limited Renewable Energy Technician (LRT) exam: 28 open-book questions in 2 hours on photovoltaic and renewable energy systems under the NEC with Oregon amendments. 75% to pass.

Questions
28
Time limit
2 hours
Passing score
75%
Books
Open book

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10Oregon Laws and PV/Renewable Scope (OAR 918-282-0205, 0400; 50 kW AC)

Under OAR 918-282-0205(1), an Oregon limited renewable energy technician (LRT) must be employed by which type of business?

Requirements at a glance

AgencyOregon Building Codes Division (BCD); state-run paper exam
ExperienceOregon apprenticeship only (4,000 on-the-job hours and 288 classroom hours)
Exam28 questions, 2 hours, open book; 75% to pass
Books allowedOpen book: NEC with Oregon amendments, NEC Handbook, ORS 479, OAR Division 918 and the other references on BCD's list; silent non-programmable calculator
Fees$50 application fee (no separate exam fee); 4 hours of continuing education

Installers applying to BCD for a limited renewable energy technician (LRT) license to install renewable energy systems up to 50 kW AC and 600 V nominal, employed by a limited renewable energy contractor or electrical contractor. The path is an Oregon apprenticeship only.

How to get licensed, step by step

  1. Apply to BCD

    Send the application, proof of qualifying training and experience, a high school diploma or GED, and the fee. Choose your proctor site on the application.

    Oregon Building Codes Division: licensing (opens in a new tab)

  2. Get your Letter of Authorization

    BCD mails the letter when your application is approved. Call the proctor site on it to book; you must test within 60 days of the letter.

    BCD: license exams and locations (opens in a new tab)

  3. Take the exam

    Bring the letter, photo ID, your approved books, pencils and a silent, non-programmable calculator. 75% is the passing score.

    BCD: license exams and locations (opens in a new tab)

  4. Results and retakes

    BCD grades the exam and mails the result in about 2 weeks. After a failure, wait 30 days and send a license reapplication form.

    BCD: license exams and locations (opens in a new tab)

How to prepare

  • The 2026 Oregon Electrical Specialty Code (2026 NEC) took effect October 1, 2026. BCD does not say which edition its exams test, so our questions follow the currently adopted code. Check your Letter of Authorization and the BCD materials list before you buy books.
  • BCD publishes no outline or topic weights, so our topic split is an estimate. The exam is open book: tab your NEC with Oregon amendments, ORS 479 and OAR Division 918 and practice finding answers fast.
  • Allowed: tabs, highlighting, printed errata and short margin notes. Not allowed: practice tests, class notes, calculation examples or added pages.
  • The LRT scope is renewable systems up to 50 kW AC (sum of inverter ratings) and 600 V nominal. Drill NEC 690 and 705, string voltage and conductor sizing, and rapid shutdown.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

    Official reference list (as published by the testing agency)
    • NFPA 70 / National Electrical Code (NEC) with Oregon amendments and errata
    • NEC Handbook and errata
    • Oregon Revised Statutes (ORS) Chapter 479
    • Oregon Administrative Rules (OAR) Division 918
    • American Electrician's Handbook (Hartwell); Electrical Black Book (Rapp); Ugly's Electrical References; Ferm's Fast Finder Index; Tom Henry's Key Word Index; Briganti NEC and Oregon Electrical Code key-word indexes
    • A silent, non-printing, non-programmable calculator
    • Tabs, highlighting, printed errata and short margin notes are allowed. Practice tests, class notes, calculation examples and added pages are not. (BCD materials list, rev. September 2026)

    What's on the exam

    Estimated topic weighting. No official breakdown is published:

    TopicQuestions
    Oregon Laws and PV/Renewable Scope (OAR 918-282-0205, 0400; 50 kW AC)4
    PV Systems (NEC 690)9
    Interconnection and Energy Storage (NEC 705, 706, 710)4
    Wiring Methods and Grounding4
    Calculations (string voltage, conductor and OCPD sizing)4
    Safety, Rapid Shutdown and Blueprint Reading3

    Exam day details

    • Administered by the Oregon Building Codes Division (state-run paper exam at a proctor site).
    • Fee: No separate exam fee: the license application fee covers it ($50 for this license). Application fees are nonrefundable.
    • 28 questions, 2 hours, open book, 75% to pass (BCD license directory). BCD publishes no topic outline, so our topic split is an estimate derived from the license scope in OAR Division 918-282.
    • BCD mails a Letter of Authorization when your application is approved. Call the proctor site named on it to book; you must test within 60 days of the letter. Bring the letter and photo ID.
    • Proctor sites are in Bend, Eugene, Hermiston, Klamath Falls, Ontario, Pendleton, Portland, Roseburg, Salem and White City. BCD grades the paper exam and mails the result in about 2 weeks; results are not given by phone.
    • The passing score for all BCD licensing exams is 75%. After a failed exam you wait 30 days and send a license reapplication form; the result includes a strength and weakness report.
    • Bring your own pencils and, if you use one, a silent, non-printing, non-programmable calculator. Scratch paper is provided.
    • Qualification (BCD license directory): Oregon apprenticeship only (4,000 on-the-job hours and 288 classroom hours, OAR 918-282-0205); high school diploma or GED.
    • The 2026 Oregon Electrical Specialty Code (2026 NEC) took effect October 1, 2026, replacing the 2023 code. BCD does not say which edition its exams test, so our questions follow the currently adopted 2026 code; where a section number changed, the explanation also gives the 2023 number.

    Note: BCD publishes no content outline, topic weights or question-count breakdown for the electrical exams, so our topic split is an estimate. The question count and time come from the BCD license directory. Our 2026 section numbers and rules were checked against NFPA's published 2026 revision records and Oregon's amendment table rather than the printed code, and BCD does not state which code edition the exams test.

    Frequently asked questions

    Who can take the Oregon limited renewable energy technician exam?

    Candidates who meet BCD's qualification for this license: Oregon apprenticeship only (4,000 on-the-job hours and 288 classroom hours, OAR 918-282-0205); high school diploma or GED. BCD mails a Letter of Authorization once your application is approved.

    What's on the exam?

    BCD publishes no outline or weights. Our topics follow the legal scope of the license in OAR Division 918-282 and the NEC with Oregon amendments, and our split is an estimate.

    Is the exam open book?

    Yes. You may bring the references on BCD's materials list, with tabs, highlighting and short margin notes. Practice tests, class notes and added pages are not allowed.

    What if I fail?

    Wait 30 days, then send BCD a license reapplication form to test again. Results come by mail in about 2 weeks.

    Free questions with answers

    Show all 10 free questions and answers
    1. Under OAR 918-282-0205(1), an Oregon limited renewable energy technician (LRT) must be employed by which type of business?

      Answer: A limited renewable energy contractor or an electrical contractor

      OAR 918-282-0205(1) requires an LRT to be employed by a limited renewable energy contractor or an electrical contractor, which mirrors ORS 479.630(16). The LRT license does not allow independent work for a general contractor or for other limited contractor classes.

      Reference: Oregon Administrative Rules (OAR) Chapter 918, OAR 918-282-0205(1)

    2. The on-the-job training in OAR 918-282-0205(2)(a)(A) calls for 1,500 hours in renewable energy system work. What is the minimum number of those hours that must be in photovoltaics?

      Answer: 1,000 hours, with at least 500 hours in other renewable electrical energy systems

      Rule 0205(2)(a)(A) sets 1,500 hours total with a minimum of 1,000 in photovoltaics and a minimum of 500 in other renewable electrical energy system installations such as wind, micro-hydro, fuel cells and engine generators for off-grid systems. The split is not even and the block is not all PV.

      Reference: Oregon Administrative Rules (OAR) Chapter 918, OAR 918-282-0205(2)(a)(A)

    3. For rapid shutdown purposes, how far from the PV array in all directions does NEC 690.12(B) define the array boundary?

      Answer: 1 ft (305 mm)

      690.12(B) defines the array boundary as 305 mm (1 ft) from the array in all directions. The 3 ft (1 m) figure is a different measurement: how far inside a building controlled conductors may run before they must meet the 30-volt limit.

      Reference: NFPA 70, National Electrical Code, 2026, 690.12(B)

    4. What is the maximum voltage permitted for PV system dc circuits on or in a one- or two-family dwelling under NEC 690.7?

      Answer: 600 volts

      690.7 limits PV system dc circuits on or in one- and two-family dwellings to 600 volts. The 1000-volt limit applies to arrays on or attached to other buildings and to dc circuits inside buildings. Use the maximum voltage, not the nominal voltage, when checking these limits.

      Reference: NFPA 70, National Electrical Code, 2026, 690.7

    5. A designer is laying out a rooftop array on a warehouse. What highest dc circuit voltage may originate from an array attached to a building that is not a one- or two-family dwelling?

      Answer: 1000 volts

      690.7 allows up to 1000 volts for PV system dc circuits within or originating from arrays on or attached to buildings and for dc circuits inside buildings, with a 600-volt limit on or in one- and two-family dwellings. Circuits above 1000 volts must meet 690.31(G), which keeps them off dwellings and out of buildings containing habitable rooms.

      Reference: NFPA 70, National Electrical Code, 2026, 690.7

    6. A string has 12 series-connected crystalline silicon modules, each with a rated open-circuit voltage of 41.0 V. The lowest expected ambient temperature is -12 C. Using Table 690.7(A), what is the maximum PV source circuit voltage?

      Answer: 571 V

      Table 690.7(A) gives a correction factor of 1.16 for -11 to -15 C. Maximum voltage = 12 x 41.0 V x 1.16 = 570.7, about 571 V. 492 V (12 x 41.0) skips the temperature correction, 561 V uses 1.14 from the -6 to -10 C row, and 615 V uses 1.25, the factor for -36 to -40 C.

      Reference: NFPA 70, National Electrical Code, 2026, 690.7(A)(2), Table 690.7(A)

    7. A 200-ampere busbar panelboard is protected by a 150-ampere main breaker. Using 705.12(B)(2) (PV breaker at the opposite end of the bus from the main), what is the maximum inverter output circuit current allowed?

      Answer: 72 A

      705.12(B)(2): 125 percent of the source output current plus the main OCPD rating must not exceed 120 percent of the busbar rating. 120 percent of 200 A = 240 A, minus the 150 A main = 90 A, divided by 1.25 = 72 A. 90 A forgets the 125 percent factor, 50 A uses 100 percent of the bus with no 125 percent, and 40 A is the result of the stricter 705.12(B)(1) rule.

      Reference: NFPA 70, National Electrical Code, 2026, 705.12(B)(2)

    8. A feeder tap sized under 240.21(B)(2) connects to a feeder protected by a 100-ampere overcurrent device, and a 40-ampere power source overcurrent device is also connected to it. Under 705.12(A)(3), what is the minimum tap conductor ampacity?

      Answer: 46.7 A

      705.12(A)(3) requires tap conductors sized under 240.21(B)(2) or (B)(4) to have ampacity of at least one-third of the sum of the feeder overcurrent device rating plus the ratings of any power source overcurrent devices connected to the feeder: (100 + 40) / 3 = 46.7 A. 33.3 A uses only the feeder device, 35.0 A takes one quarter of the sum, and 140 A is the sum with no one-third factor. The Oregon amendment to 705.12(A) in OAR 918-305-0105 Table 1-E carries the same one-third rule as item (3).

      Reference: NFPA 70, National Electrical Code, 2026, 705.12(A)(3); OAR 918-305-0105 Table 1-E

    9. Under NEC 690.43, when must exposed non-current-carrying metal parts of PV module frames and equipment be connected to an equipment grounding conductor?

      Answer: Regardless of the system voltage

      690.43 requires exposed non-current-carrying metal parts of PV module frames, electrical equipment and conductor enclosures to be connected to an equipment grounding conductor per 250.134 or 250.136, regardless of voltage. Low voltage does not remove the bonding requirement.

      Reference: NFPA 70, National Electrical Code, 2026, 690.43

    10. A rail clamp is used to attach modules and also to bond the module frames to the rail. What does 690.43(A) require of that clamp?

      Answer: It must be listed, labeled and identified for bonding PV modules

      690.43(A) says devices and systems used for mounting PV modules that are also used for bonding the module frames must be listed, labeled and identified for bonding PV modules (see UL 2703). A clamp listed for mechanical retention only cannot be relied on for bonding.

      Reference: NFPA 70, National Electrical Code, 2026, 690.43(A)

    Sources

    Questions last verified November 10, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.