Requirements at a glance
| Agency | Oregon Building Codes Division (BCD); state-run paper exam |
|---|---|
| Experience | Apprenticeship, or 576 classroom hours plus 8,000 commercial or industrial hours, or 16,000 hours |
| Exam | 52 questions, 3 hours, open book; 75% to pass |
| Books allowed | Open book: NEC with Oregon amendments, NEC Handbook, ORS 479, OAR Division 918 and the other references on BCD's list; silent non-programmable calculator |
| Fees | $100 application fee (no separate exam fee); 16 hours of continuing education |
Electricians applying to BCD for a limited journeyman manufacturing plant (PJ) license to install, maintain, replace and repair wiring in an existing operable manufacturing or industrial plant owned or used by their employer.
Official links
How to get licensed, step by step
Apply to BCD
Send the application, proof of qualifying training and experience, a high school diploma or GED, and the fee. Choose your proctor site on the application.
Oregon Building Codes Division: licensing (opens in a new tab)
Get your Letter of Authorization
BCD mails the letter when your application is approved. Call the proctor site on it to book; you must test within 60 days of the letter.
Take the exam
Bring the letter, photo ID, your approved books, pencils and a silent, non-programmable calculator. 75% is the passing score.
Results and retakes
BCD grades the exam and mails the result in about 2 weeks. After a failure, wait 30 days and send a license reapplication form.
How to prepare
- The 2026 Oregon Electrical Specialty Code (2026 NEC) took effect October 1, 2026. BCD does not say which edition its exams test, so our questions follow the currently adopted code. Check your Letter of Authorization and the BCD materials list before you buy books.
- BCD publishes no outline or topic weights, so our topic split is an estimate. The exam is open book: tab your NEC with Oregon amendments, ORS 479 and OAR Division 918 and practice finding answers fast.
- Allowed: tabs, highlighting, printed errata and short margin notes. Not allowed: practice tests, class notes, calculation examples or added pages.
- A PJ works in an existing operable manufacturing or industrial plant owned or used by the employer. Drill motors and NEC 430, controls, troubleshooting, distribution equipment and hazardous locations.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
Official reference list (as published by the testing agency)
- NFPA 70 / National Electrical Code (NEC) with Oregon amendments and errata
- NEC Handbook and errata
- Oregon Revised Statutes (ORS) Chapter 479
- Oregon Administrative Rules (OAR) Division 918
- American Electrician's Handbook (Hartwell); Electrical Black Book (Rapp); Ugly's Electrical References; Ferm's Fast Finder Index; Tom Henry's Key Word Index; Briganti NEC and Oregon Electrical Code key-word indexes
- A silent, non-printing, non-programmable calculator
- Tabs, highlighting, printed errata and short margin notes are allowed. Practice tests, class notes, calculation examples and added pages are not. (BCD materials list, rev. September 2026)
What's on the exam
Estimated topic weighting. No official breakdown is published:
| Topic | Questions | |
|---|---|---|
| Oregon Laws and Plant Licence Scope (OAR 918-282-0190) | 6 | |
| General Requirements, Grounding and Bonding | 7 | |
| Wiring Methods and Distribution (switchgear, transformers, panels) | 10 | |
| Motors, Generators, Controllers (NEC 430) | 11 | |
| Equipment, Hazardous Locations and Special Equipment | 7 | |
| Troubleshooting, Controls and Theory/Calculations | 7 | |
| Safety (NFPA 70E basics) | 4 |
Exam day details
- Administered by the Oregon Building Codes Division (state-run paper exam at a proctor site).
- Fee: No separate exam fee: the license application fee covers it ($100 for this license). Application fees are nonrefundable.
- 52 questions, 3 hours, open book, 75% to pass (BCD license directory). BCD publishes no topic outline, so our topic split is an estimate derived from the license scope in OAR Division 918-282.
- BCD mails a Letter of Authorization when your application is approved. Call the proctor site named on it to book; you must test within 60 days of the letter. Bring the letter and photo ID.
- Proctor sites are in Bend, Eugene, Hermiston, Klamath Falls, Ontario, Pendleton, Portland, Roseburg, Salem and White City. BCD grades the paper exam and mails the result in about 2 weeks; results are not given by phone.
- The passing score for all BCD licensing exams is 75%. After a failed exam you wait 30 days and send a license reapplication form; the result includes a strength and weakness report.
- Bring your own pencils and, if you use one, a silent, non-printing, non-programmable calculator. Scratch paper is provided.
- Qualification (BCD license directory): Apprenticeship, or 576 classroom hours plus 8,000 commercial or industrial hours, or 16,000 hours; high school diploma or GED.
- The 2026 Oregon Electrical Specialty Code (2026 NEC) took effect October 1, 2026, replacing the 2023 code. BCD does not say which edition its exams test, so our questions follow the currently adopted 2026 code; where a section number changed, the explanation also gives the 2023 number.
Note: BCD publishes no content outline, topic weights or question-count breakdown for the electrical exams, so our topic split is an estimate. The question count and time come from the BCD license directory. Our 2026 section numbers and rules were checked against NFPA's published 2026 revision records and Oregon's amendment table rather than the printed code, and BCD does not state which code edition the exams test.
Frequently asked questions
Who can take the Oregon limited manufacturing plant journeyman exam?
Candidates who meet BCD's qualification for this license: Apprenticeship, or 576 classroom hours plus 8,000 commercial or industrial hours, or 16,000 hours; high school diploma or GED. BCD mails a Letter of Authorization once your application is approved.
What's on the exam?
BCD publishes no outline or weights. Our topics follow the legal scope of the license in OAR Division 918-282 and the NEC with Oregon amendments, and our split is an estimate.
Is the exam open book?
Yes. You may bring the references on BCD's materials list, with tabs, highlighting and short margin notes. Practice tests, class notes and added pages are not allowed.
What if I fail?
Wait 30 days, then send BCD a license reapplication form to test again. Results come by mail in about 2 weeks.
Free questions with answers
Show all 10 free questions and answers
Under OAR 918-282-0190, where is a limited journeyman manufacturing plant (PJ) electrician licensed to install, maintain, replace and repair electrical wiring?
Answer: On or in an existing, operable manufacturing or industrial plant owned or used by the licensee's employer
OAR 918-282-0190(1)(a) limits the PJ license to an existing and operable manufacturing or industrial plant that the licensee's employer owns or uses. It is not a general journeyman license, so work for outside customers or on new plants under construction falls outside it.
Reference: Oregon Administrative Rules, Chapter 918, Division 282, 918-282-0190(1)(a)
A new 480Y/277-volt panelboard has exposed live parts on the front and a grounded concrete wall opposite the work area (Condition 2). What is the minimum clear depth of working space in front of it?
Answer: 3 ft 6 in.
Table 110.26(A)(1), 151 to 600 volts to ground, gives 3 ft for Condition 1, 3 ft 6 in. for Condition 2 and 4 ft for Condition 3. Concrete, brick and tile walls count as grounded parts, so the wall makes this Condition 2.
Reference: NFPA 70, National Electrical Code, 2026, Table 110.26(A)(1)
In a new installation two 480Y/277-volt motor control center lineups face each other across an aisle, with exposed live parts on both sides of the working space. What minimum working-space depth applies under Table 110.26(A)(1)?
Answer: 4 ft
Exposed live parts on both sides of the working space is Condition 3. For 151 to 600 volts to ground that is 4 ft. The reduced Condition 2 clearance in 110.26(A)(1)(b) is only for replacement in existing buildings under written procedures.
Reference: NFPA 70, National Electrical Code, 2026, Table 110.26(A)(1), Condition 3
A 75-kVA, three-phase transformer has a 480-volt primary. Only primary overcurrent protection will be used (no secondary protection). Using Table 450.5(B), what is the largest standard fuse or breaker rating permitted?
Answer: 125 A
Primary current = 75,000 / (1.732 x 480) = 90.2 A. Table 450.5(B) allows 125 percent for primary-only protection of currents of 9 A or more: 90.2 x 1.25 = 112.8 A. That is not a standard size, so Note 1 allows the next higher standard rating, 125 A (240.6). 90 A ignores the 125 percent, 150 A exceeds the next standard size above 112.8 A, and 225 A uses the 250 percent primary value that applies only when secondary protection is also provided.
Reference: NFPA 70, National Electrical Code, 2026, Table 450.5(B) and Note 1
A 240/120-volt, three-phase, four-wire delta system has the midpoint of one phase winding grounded. How must the conductor with the higher voltage to ground be identified, and what is that voltage?
Answer: Orange, or other effective means; 208 volts to ground
Section 110.15 requires the high-leg conductor of a four-wire delta with a grounded midpoint to be marked orange or by other effective means. Its voltage to ground is 0.866 x 240 = 208 volts. 120 V is the lighting leg and 277 V belongs to a 480Y system.
Reference: NFPA 70, National Electrical Code, 2026, 110.15
A single 25-hp, 460-volt, three-phase squirrel-cage motor (Table 430.250 FLC = 34 A) is on its own branch circuit. What is the minimum ampacity of the branch-circuit conductors?
Answer: 42.5 A
Section 430.22 requires conductors with an ampacity of at least 125 percent of the table full-load current: 34 x 1.25 = 42.5 A. 34 A uses 100 percent, 39.1 A uses 115 percent (the overload factor), and 59.5 A is the 175 percent dual-element fuse value.
Reference: NFPA 70, National Electrical Code, 2026, 430.22; Table 430.250
Under 500.6(A), which Class I group is acetylene?
Answer: Group A
Section 500.6(A) lists Group A as acetylene, Group B as materials such as hydrogen, Group C as materials such as ethylene, and Group D as materials such as propane.
Reference: NFPA 70, National Electrical Code, 2026, 500.6(A)
Under 505.5(B), which describes a Zone 0 location?
Answer: Ignitible concentrations of flammable gases or vapors are present continuously or for long periods of time
Zone 0 is for gases or vapors present continuously or for long periods. Zone 1 is where they are likely to exist under normal operating conditions, and Zone 2 is where they are not likely in normal operation and exist only briefly if they occur. Dust is outside the zone system for gases.
Reference: NFPA 70, National Electrical Code, 2026, 505.5(B)
A 25-hp motor (1 hp = 746 W) delivers full-load output while drawing 21,000 W of input power. What is its efficiency?
Answer: 88.8 percent
Output = 25 x 746 = 18,650 W. Efficiency = output / input = 18,650 / 21,000 = 0.888, or 88.8 percent. 112.6 percent comes from dividing input by output, which would be over 100 percent and is impossible.
Reference: Standard electrical theory and trade practice (not a code section), Efficiency = output / input; 1 hp = 746 W
How does NFPA 70E define the arc flash boundary?
Answer: The distance from an arc source at which incident energy equals 1.2 cal/cm2
The arc flash boundary is the distance at which the incident energy is 1.2 cal/cm2 (5 J/cm2), the level at which a second-degree burn can occur on unprotected skin. A person inside this boundary needs arc-rated protective equipment appropriate to the hazard.
Reference: NFPA 70E, Standard for Electrical Safety in the Workplace, NFPA 70E Article 100, Definitions (arc flash boundary)
Sources
- Oregon BCD: license exams and locations (opens in a new tab)
- Oregon Building Codes Division (licensing) (opens in a new tab)
- Oregon BCD: Electrical Specialty Code adoption (opens in a new tab)
Questions last verified November 10, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.