Requirements at a glance
| Agency | Oregon Building Codes Division (BCD); state-run paper exam |
|---|---|
| Experience | Apprenticeship, or 288 classroom hours plus 4,000 hours, or 8,000 hours |
| Exam | 28 questions, 2 hours, open book; 75% to pass |
| Books allowed | Open book: NEC with Oregon amendments, NEC Handbook, ORS 479, OAR Division 918 and the other references on BCD's list; silent non-programmable calculator |
| Fees | $100 application fee (no separate exam fee); 8 hours of continuing education |
Maintenance electricians applying to BCD for a limited maintenance electrician (LME) license to maintain, repair and replace electrical equipment on an industrial plant premises or systems under 600 V phase-to-phase in office, government or board-designated buildings. No new installations and no service work.
Official links
How to get licensed, step by step
Apply to BCD
Send the application, proof of qualifying training and experience, a high school diploma or GED, and the fee. Choose your proctor site on the application.
Oregon Building Codes Division: licensing (opens in a new tab)
Get your Letter of Authorization
BCD mails the letter when your application is approved. Call the proctor site on it to book; you must test within 60 days of the letter.
Take the exam
Bring the letter, photo ID, your approved books, pencils and a silent, non-programmable calculator. 75% is the passing score.
Results and retakes
BCD grades the exam and mails the result in about 2 weeks. After a failure, wait 30 days and send a license reapplication form.
How to prepare
- The 2026 Oregon Electrical Specialty Code (2026 NEC) took effect October 1, 2026. BCD does not say which edition its exams test, so our questions follow the currently adopted code. Check your Letter of Authorization and the BCD materials list before you buy books.
- BCD publishes no outline or topic weights, so our topic split is an estimate. The exam is open book: tab your NEC with Oregon amendments, ORS 479 and OAR Division 918 and practice finding answers fast.
- Allowed: tabs, highlighting, printed errata and short margin notes. Not allowed: practice tests, class notes, calculation examples or added pages.
- An LME maintains, repairs and replaces only: no new installations and no service work (OAR 918-282-0240). Drill motors, heating equipment, controls and troubleshooting.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
Official reference list (as published by the testing agency)
- NFPA 70 / National Electrical Code (NEC) with Oregon amendments and errata
- NEC Handbook and errata
- Oregon Revised Statutes (ORS) Chapter 479
- Oregon Administrative Rules (OAR) Division 918
- American Electrician's Handbook (Hartwell); Electrical Black Book (Rapp); Ugly's Electrical References; Ferm's Fast Finder Index; Tom Henry's Key Word Index; Briganti NEC and Oregon Electrical Code key-word indexes
- A silent, non-printing, non-programmable calculator
- Tabs, highlighting, printed errata and short margin notes are allowed. Practice tests, class notes, calculation examples and added pages are not. (BCD materials list, rev. September 2026)
What's on the exam
Estimated topic weighting. No official breakdown is published:
| Topic | Questions | |
|---|---|---|
| Oregon Laws and Maintenance Scope (OAR 918-282-0240) | 4 | |
| Motors, Generators and Heating Equipment | 6 | |
| Controls and Troubleshooting | 7 | |
| Power Distribution and Lighting | 5 | |
| Wiring Methods and Grounding Basics | 3 | |
| Theory, Meters and Drawings | 3 |
Exam day details
- Administered by the Oregon Building Codes Division (state-run paper exam at a proctor site).
- Fee: No separate exam fee: the license application fee covers it ($100 for this license). Application fees are nonrefundable.
- 28 questions, 2 hours, open book, 75% to pass (BCD license directory). BCD publishes no topic outline, so our topic split is an estimate derived from the license scope in OAR Division 918-282.
- BCD mails a Letter of Authorization when your application is approved. Call the proctor site named on it to book; you must test within 60 days of the letter. Bring the letter and photo ID.
- Proctor sites are in Bend, Eugene, Hermiston, Klamath Falls, Ontario, Pendleton, Portland, Roseburg, Salem and White City. BCD grades the paper exam and mails the result in about 2 weeks; results are not given by phone.
- The passing score for all BCD licensing exams is 75%. After a failed exam you wait 30 days and send a license reapplication form; the result includes a strength and weakness report.
- Bring your own pencils and, if you use one, a silent, non-printing, non-programmable calculator. Scratch paper is provided.
- Qualification (BCD license directory): Apprenticeship, or 288 classroom hours plus 4,000 hours, or 8,000 hours; high school diploma or GED.
- The 2026 Oregon Electrical Specialty Code (2026 NEC) took effect October 1, 2026, replacing the 2023 code. BCD does not say which edition its exams test, so our questions follow the currently adopted 2026 code; where a section number changed, the explanation also gives the 2023 number.
Note: BCD publishes no content outline, topic weights or question-count breakdown for the electrical exams, so our topic split is an estimate. The question count and time come from the BCD license directory. Our 2026 section numbers and rules were checked against NFPA's published 2026 revision records and Oregon's amendment table rather than the printed code, and BCD does not state which code edition the exams test.
Frequently asked questions
Who can take the Oregon limited maintenance electrician exam?
Candidates who meet BCD's qualification for this license: Apprenticeship, or 288 classroom hours plus 4,000 hours, or 8,000 hours; high school diploma or GED. BCD mails a Letter of Authorization once your application is approved.
What's on the exam?
BCD publishes no outline or weights. Our topics follow the legal scope of the license in OAR Division 918-282 and the NEC with Oregon amendments, and our split is an estimate.
Is the exam open book?
Yes. You may bring the references on BCD's materials list, with tabs, highlighting and short margin notes. Practice tests, class notes and added pages are not allowed.
What if I fail?
Wait 30 days, then send BCD a license reapplication form to test again. Results come by mail in about 2 weeks.
Free questions with answers
Show all 10 free questions and answers
An LME is employed by a commercial office building owner. On what systems does OAR 918-282-0240 allow the LME to maintain, repair and replace electrical installations in that building?
Answer: Systems that are less than 600 volts phase to phase
OAR 918-282-0240(1)(b) uses less than 600 volts phase to phase for commercial office buildings, buildings occupied by the state or a local government, and facilities designated by the board. The 300 volts to ground figure belongs to the limited building maintenance electrician license (OAR 918-282-0260), a different and narrower license.
Reference: Oregon Administrative Rules (OAR) Chapter 918, OAR 918-282-0240(1)(b)
A plant employs several individuals who install electrical wiring. Under OAR 918-282-0150(1), whom must the plant employ on regular payroll to supervise this work?
Answer: A registered professional electrical engineer, a general supervising electrician or a limited supervising electrician
OAR 918-282-0150(1) names three acceptable people: a registered professional electrical engineer, a general supervising electrician or a limited supervising electrician. An LME is a maintenance worker and is not a supervising license, and a journeyman license alone does not satisfy the rule.
Reference: Oregon Administrative Rules (OAR) Chapter 918, OAR 918-282-0150(1)
A 30-hp, 230-volt, three-phase squirrel-cage motor with a continuous duty rating is on its own branch circuit. Using Table 430.250, what is the minimum ampacity of the branch-circuit conductors?
Answer: 100 A, from 80 A (table FLC) x 1.25
Section 430.6(A)(1) sends you to the Table 430.250 full-load current for conductor sizing: 80 A for a 30-hp, 230-volt motor. Section 430.22 requires 125 percent of that value: 80 x 1.25 = 100 A. The 1.15 multiplier is for the disconnect rating, and 2.5 is for an inverse-time breaker, not for conductors.
Reference: NFPA 70, National Electrical Code, 2026, 430.6(A)(1), 430.22 and Table 430.250
Using Table 430.250, what is the full-load current of a 15-hp, 208-volt, three-phase induction motor?
Answer: 46.2 A
Table 430.250 lists 46.2 A for 15 hp at 208 volts. The 42 A value is the 230-volt column, 21 A is the 460-volt column, and 59.4 A is the 208-volt value for a 20-hp motor, one row down.
Reference: NFPA 70, National Electrical Code, 2026, Table 430.250
In a standard three-wire start/stop motor control circuit, what keeps the starter coil energized after the START button is released?
Answer: A normally open auxiliary contact wired in parallel with the START button
The holding (seal-in) contact is a normally open auxiliary contact on the starter that closes with the coil and bridges across the START button, so the coil stays energized when the button is released. The STOP button and overload contact are normally closed and sit in series with the coil, where they break the circuit when opened.
Reference: Oregon Administrative Rules (OAR) Chapter 918, OAR 918-282-0240(2)(b) (controls subject area; general control-circuit practice)
A conveyor starter is controlled by a maintained-contact selector switch (two-wire control). After a power outage ends and voltage returns with the switch still on, what happens?
Answer: The motor restarts automatically
Two-wire control has no holding contact, so the maintained switch re-energizes the coil as soon as voltage returns and the motor restarts on its own (low-voltage release). Three-wire start/stop control drops out on power loss and requires a new START command (low-voltage protection), which is why three-wire control is used wherever an unexpected restart could injure someone.
Reference: Oregon Administrative Rules (OAR) Chapter 918, OAR 918-282-0240(2)(b) (controls subject area; general control-circuit practice)
A motor control center operates at 480Y/277 volts. Exposed live parts are on the front side of the working space, and a grounded concrete wall is on the opposite side. What is the minimum clear working space depth required by Table 110.26(A)(1)?
Answer: 3 ft 6 in.
The 277 volts to ground falls in the 151 to 600 volt row of Table 110.26(A)(1). Exposed live parts on one side and a grounded surface opposite is Condition 2, which requires 1.0 m (3 ft 6 in.). Concrete, brick and tile walls count as grounded. Condition 1 would be 3 ft and Condition 3 would be 4 ft.
Reference: NFPA 70, National Electrical Code, 2026, 110.26(A)(1) and Table 110.26(A)(1)
A 400-A feeder overcurrent device protects the feeder conductors. Field-installed tap conductors, under 10 ft long, leave the enclosure where the tap is made and are enclosed in a raceway to a panelboard. Under 240.21(B)(1), what is the minimum ampacity of the tap conductors based on the one-tenth rule?
Answer: 40 A, which is one-tenth of 400 A
For the 10-ft tap rule, field-installed tap conductors that leave the enclosure where the tap is made must have an ampacity not less than one-tenth of the rating of the overcurrent device protecting the feeder: 400 / 10 = 40 A. The tap must also carry the calculated load it supplies and not be less than the rating of the device at its termination. One-third is the 25-ft tap rule.
Reference: NFPA 70, National Electrical Code, 2026, 240.21(B)(1)
Service-entrance conductors are 3/0 AWG copper. Using Table 250.66, what is the minimum copper grounding electrode conductor size (where no special electrode rule applies)?
Answer: 4 AWG
Table 250.66 gives 4 AWG copper for the largest ungrounded conductor sizes 2/0 or 3/0 AWG copper. The 6 AWG size is for 1 or 1/0 AWG, and 2 AWG is for sizes over 3/0 through 350 kcmil.
Reference: NFPA 70, National Electrical Code, 2026, 250.66 and Table 250.66
A 240-volt heating element draws 15 A. What is its resistance?
Answer: 16 ohms
Ohm's law gives R = E / I = 240 / 15 = 16 ohms. The 3,600 answer multiplies E x I (which is watts), 0.0625 inverts the formula, and 32 ohms doubles the answer.
Reference: Ohm's law and power formulas (standard electrical theory), Ohm's law: R = E / I
Sources
- Oregon BCD: license exams and locations (opens in a new tab)
- Oregon Building Codes Division (licensing) (opens in a new tab)
- Oregon BCD: Electrical Specialty Code adoption (opens in a new tab)
Questions last verified November 10, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.