Requirements at a glance
| Agency | Board of State Examiners of Plumbers and Gas Fitters (Division of Occupational Licensure); exams by PSI |
|---|---|
| License | Journeyman Plumber or Master Plumber (Part 2) |
| Format | Part 2: 40 questions, closed book, 70% to pass |
| Fees | $80 PSI exam fee; the license fee in eLIPSE is $52 (journeyman, gas fitter, LP gas installer), $78 (master plumber) or $97 (master gas fitter) |
Journeyman and master plumber applicants. The PSI bulletin lists a single Part 2 outline for both licenses.
Official links
How to get licensed, step by step
Apply to the Board
Apply online through eLIPSE with your apprenticeship hours and education. The Board approves you, then PSI contacts you to schedule.
Board of State Examiners of Plumbers and Gas Fitters (opens in a new tab)
Schedule the plumber Part 2 exam with PSI
Test at a PSI site in Auburn, Boston, Fall River, Lawrence or West Springfield. Cancel at least 2 days ahead or you forfeit the fee.
Schedule with PSI (Massachusetts plumbers and gas fitters) (opens in a new tab)
Pass both parts
Each part is scored separately at 70%. Retake within 12 months of approval; after six failed attempts you must petition the Board in writing.
Schedule with PSI (Massachusetts plumbers and gas fitters) (opens in a new tab)
Get licensed
Pay the license fee in eLIPSE after you pass both parts.
Board of State Examiners of Plumbers and Gas Fitters (opens in a new tab)
How to prepare
- Both parts are closed book. Nothing is allowed in the room, so learn the code rules and numbers rather than where to find them.
- The editions are 248 CMR 3.00, 4.00, 5.00 and 11.00 (2021), 10.00 (2023 plumbing code), NFPA 54 (2012) and NFPA 58 (2011).
- Part 2 is a written exam even though the bulletin calls it Practical. Isometric analysis is 20 of 40 questions: practice counting fittings, offsets and developed length.
- Journeyman and master plumber applicants take the same Part 2.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
What to study
This is a closed-book exam, so nothing comes into the exam room. Study from these:
248 CMR 3.00 to 11.00: Massachusetts plumbing and gas rulesEssential
Not allowed in the exam room (closed book). The core of both plumbing and gas exams: Uniform State Plumbing Code (10.00, 2023), Fuel Gas Code (4.00 and 5.00, 2021), 6.00, 7.00 and 11.00.
Massachusetts regulations (Cornell LII, free to read) (opens in a new tab)
MGL Chapter 142: Supervision of Plumbing
Not allowed in the exam room. Licensing, permits and the water heater rules.
Massachusetts General Laws (free to read) (opens in a new tab)
Official reference list (as published by the testing agency)
- 248 CMR 3.00 (2021), 4.00 (2021), 5.00 (2021), 6.00 (2014 amendments to NFPA 58), 7.00 (2014) and 11.00 (2021)
- 248 CMR 10.00 to 10.23: Massachusetts Uniform State Plumbing Code (2023)
- NFPA 54 National Fuel Gas Code (2012) and NFPA 58 Liquefied Petroleum Gas Code (2011)
- MGL Chapter 142: Supervision of Plumbing, and the general provisions governing plumbing and gas work
What's on the exam
Official content outline from PSI Services (number of questions per topic):
| Topic | Questions | |
|---|---|---|
| Isometric Analysis | 20 | |
| General Trade Calculations | 5 | |
| Gas Piping | 7 | |
| Gas Venting | 8 |
Exam day details
- Administered by PSI Services for the Massachusetts Board of State Examiners of Plumbers and Gas Fitters.
- Fee: $80 PSI exam fee (retakes pay again, non-refundable). Board application and the license fee ($52 for journeyman) are separate.
- 40 questions; 70% to pass. The PSI bulletin calls this the Practical part, but it is a written multiple-choice exam. The time shows as 160 minutes in the bulletin. Isometric questions in this bank are described in words (offsets, fittings, lengths) rather than drawn.
- Closed book and two parts. Each part is scored on its own and you must pass both. Nothing is allowed in the exam room, and a silent non-programmable calculator is the only aid.
- If you fail, retake within 12 months of your application approval date. After six failed attempts you must petition the Board in writing before more attempts.
- The references are 248 CMR 3.00, 4.00, 5.00 and 11.00 (2021), 6.00 (2014 NFPA 58 amendments), 7.00 (2014 large gas equipment), 10.00 (Uniform State Plumbing Code, 2023), NFPA 54 (2012), NFPA 58 (2011), and MGL c.142.
- Apply to the Board through the eLIPSE portal. After you pass both parts, pay the license fee in eLIPSE. Exams are at PSI sites in Auburn, Boston, Fall River, Lawrence and West Springfield.
Frequently asked questions
What is on plumber Part 2?
40 questions: isometric analysis 20, gas venting 8, gas piping 7 and general trade calculations 5.
Is Part 2 really a practical exam?
The bulletin calls it Practical, but it is a written, computer-based multiple-choice exam.
Do journeyman and master plumbers take the same Part 2?
Yes, the bulletin lists one Part 2 outline.
Free questions with answers
Show all 10 free questions and answers
A commercial restroom has a horizontal branch serving two valve-operated (flush valve) toilets, two wall-lip urinals and four lavatories with 1-1/4 inch outlets. What is the load in drainage fixture units and the smallest horizontal branch size under 248 CMR 10.15?
Answer: 24 fixture units; 3-inch branch
Table 1: valve-operated toilet 6, wall-lip urinal 4, lavatory 1. So 2(6) + 2(4) + 4(1) = 12 + 8 + 4 = 24 DFU. Table 2 allows only 6 DFU on a 2-inch branch but 34 DFU on 3 inches (with no more than four water closets), so 3 inches is the minimum. The 20 DFU figure comes from counting the toilets as tank type (4 each).
Reference: 248 CMR 10.00 (2023), 248 CMR 10.15(7) Tables 1 and 2
A building drain will carry 190 fixture units from the building and is installed at 1/4 inch per foot. Using 248 CMR 10.15 Table 2, what is the smallest building drain size?
Answer: 4 inches
In Table 2 a 4-inch building drain carries 180 DFU at 1/8 inch per foot, 216 DFU at 1/4 inch per foot and 250 DFU at 1/2 inch per foot. At 1/4 inch per foot, 216 is greater than 190, so 4 inches is enough. The 5-inch answer comes from wrongly reading the 1/8 inch column (180 is too small). A 3-inch building drain tops out at 40 DFU.
Reference: 248 CMR 10.00 (2023), 248 CMR 10.15(7) Table 2
A 3-inch toilet drain runs at 1/4 inch per foot from the trap weir to its vent fitting, with a developed length of 9 feet. Under 248 CMR 10.16(10) Table 1, what is the result?
Answer: It exceeds the 8 foot maximum, so the vent must be moved closer or the fixture re-vented
Table 1 (Distance of Fixture Trap from Vent) allows a maximum developed length of 8 feet for a 3-inch pipe (6 ft for 2-inch, 10 ft for 4-inch), at a slope not over 1/4 inch per foot. A 9 foot run is 1 foot too long. Ten feet is the 4-inch limit, not the 3-inch limit.
Reference: 248 CMR 10.00 (2023), 248 CMR 10.16(10) Table 1
A one-family house has three tank-type toilets, three lavatories, two bathtubs, one single-head shower valve, one residential kitchen sink, one domestic dishwasher (hot water only), one laundry valve and two wall hydrants (cold only). Using 248 CMR 10.14(4) Tables 1, 2 and 3, and counting hot and cold factor values separately as in the 10.14 worked example, what is the smallest cold-water main size?
Answer: 1-1/4 inch
Following the 10.14 example, fixtures with hot and cold supplies count their Table 1 factor on each side. Cold: toilets 3 x 1 = 3, lavatories 3, tubs 2 x 2 = 4, shower 2, kitchen sink 2, laundry valve 2, hydrants 2 x 2 = 4, total 20. Hot: lavatories 3, tubs 4, shower 2, kitchen sink 2, dishwasher 2, laundry valve 2, total 15. Grand total 35. Table 2 demand factor for a one or two family dwelling is 0.50: 35 x 0.50 = 17.5. Table 3 puts 16.6 to 28 at 1-1/4 inch. Counting each fixture only once (22 x 0.50 = 11) wrongly gives 1 inch; skipping the demand factor (35) gives 1-1/2 inch.
Reference: 248 CMR 10.00 (2023), 248 CMR 10.14(4) Tables 1, 2 and 3
A restaurant has two flush-valve toilets, one flushometer urinal, four lavatories, two commercial pot sinks, one commercial dishwasher (hot water only), one service sink and two hose connections (cold only). Using 248 CMR 10.14(4) Tables 1, 2 and 3 (restaurant demand factor), and counting hot and cold factor values separately as in the 10.14 worked example, what is the smallest cold-water main size?
Answer: 1-1/2 inches
Cold: flush-valve toilets 2 x 12 = 24, urinal 6, lavatories 4 x 1 = 4, pot sinks 2 x 6 = 12, service sink 2, hose connections 2 x 2 = 4, total 52. Hot: lavatories 4, pot sinks 12, dishwasher 6, service sink 2, total 24. Grand total 76. Table 2: Restaurant, Cafe = 0.70, so 76 x 0.70 = 53.2. Table 3: 28.1 to 55 is 1-1/2 inch. Skipping the demand factor (76) points to 2 inches, and using the multi-residential factor 0.35 (26.6) points to 1-1/4 inches.
Reference: 248 CMR 10.00 (2023), 248 CMR 10.14(4) Tables 1, 2 and 3
Using the multi-family diversity table in 248 CMR 5.05(3) (NFPA 54 5.4.2.3), what is the design demand for 20 domestic ranges, each rated 63,000 Btu/hr?
Answer: 353 cubic feet per hour
The table gives 28 percent for 20 ranges and a demand of 353 cfh. Check: 20 x 63 cfh = 1,260 cfh connected load, and 1,260 x 0.28 = 352.8, about 353 cfh. 1,260 ignores diversity, 756 is the 60 percent of the four-range row, and 408 is the 24-and-over row.
Reference: 248 CMR 5.00 (2021), Amendments to NFPA 54, 248 CMR 5.05(3), Table 5.4.2.3
A CSST manifold will be concealed in a wall at a residence. Which requirement is stated in 248 CMR 5.05(8)(g)?
Answer: It must be a manifold supplied and listed by the CSST manufacturer, installed where accessible
5.05(8)(g) says only manifolds for CSST systems supplied and listed by the CSST manufacturer may be concealed, and assembled manifolds (close nipples and malleable tees) must be in an accessible location. Field-built manifolds therefore cannot be concealed.
Reference: 248 CMR 5.00 (2021), Amendments to NFPA 54, 248 CMR 5.05(8)(g)
A main gas pressure regulator needs a steel vent line run to the outdoors, 75 feet long. Using the table in 248 CMR 5.09(5) (Table 9.1.19.1), what is the minimum Schedule 40 pipe size?
Answer: 1 inch
Table 9.1.19.1 lists the minimum steel pipe size for a main gas pressure regulator vent as 3/4 inch for 0 to 40 feet, 1 inch for 0 to 100 feet, and 1-1/4 inch for 0 to 200 feet. At 75 feet the 100 foot column applies, so 1 inch. Three-quarter inch is only good to 40 feet.
Reference: 248 CMR 5.00 (2021), Amendments to NFPA 54, 248 CMR 5.09(5), Table 9.1.19.1
High and low gas pressure switches are manifolded to one steel vent line that is 150 feet long to the outdoors. Using Table 9.1.19.1 in 248 CMR 5.09(5), what is the minimum pipe size?
Answer: 1-1/2 inch
For manifolded high and low gas pressure switches, Table 9.1.19.1 gives 3/4 inch steel for 0 to 40 feet, 1 inch for 0 to 100 feet, and 1-1/2 inch for 0 to 200 feet. A 150 foot run falls in the 200 foot column. The 1-1/4 inch size is the regulator column, not the switch column.
Reference: 248 CMR 5.00 (2021), Amendments to NFPA 54, 248 CMR 5.09(5), Table 9.1.19.1
A steel regulator vent line passes through a pitched roof. What does 248 CMR 5.09(5)(d) require at the penetration?
Answer: A sealed metal sleeve, vent 18 inches above the roof
5.09(5)(d): vent lines that penetrate roofs or sidewalls run through metallic sleeves sealed against weather and insects, and extend no less than 18 inches above a roof surface (or terminate through the sidewall at a safe location). CSST vent lines may not go through roofs or sidewalls at all (5.09(5)(e)).
Reference: 248 CMR 5.00 (2021), Amendments to NFPA 54, 248 CMR 5.09(5)(d)
Sources
- PSI: Massachusetts Plumbers and Gas Fitters Candidate Information Bulletin (10/3/2025) (opens in a new tab)
- Massachusetts Board of State Examiners of Plumbers and Gas Fitters (opens in a new tab)
- 248 CMR (Plumbers and Gas Fitters), Cornell LII (opens in a new tab)
Questions last verified November 15, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.