Kansas licensing exam

Kansas General Building Contractor Exam (ICC KGA): Practice Test & Licensing Guide

The ICC Kansas Standard General Building Contractor A exam (KGA): 90 open-book questions on the 2018 International Building Code and the Concrete Manual. 75% to pass.

Questions
90
Time limit
4 hours
Passing score
75%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10Permits and General Regulations

A homeowner wants to put up a one-story detached storage shed in the back yard without a building permit. Under the 2018 IBC work-exemption list, what is the largest floor area such a shed can have and still be exempt?

Requirements at a glance

AgencyYour Kansas city or county licenses you; the International Code Council (ICC) gives the exam through Pearson VUE. There is no statewide license
ExperienceSet by your city or county. Johnson County (license types A, B, C, DR) sets no years-of-experience rule: the company's qualifying individual shows a passing ICC exam or the required education and takes 8 hours of continuing education per license class each year, and the company carries general liability and workers' compensation insurance
ExamKGA: 90 questions, 4 hours, 75%
Books allowed2018 International Building Code and the Concrete Manual (2021 IBC/ACI 318-19 or 2015 IBC/ACI 318-14 edition)
Fees$115 per ICC exam (national T-series exams are $120), plus your city or county's certificate or license fees

General contractors who build structures of any height and need a Johnson County Type A (general building) license, or a similar license from a Kansas city or county that accepts the ICC standard exam.

How to get licensed, step by step

  1. Ask your city or county which exam it accepts

    Kansas law lets each jurisdiction name the standard examinations it accepts as proof of competency. Confirm the exam and the experience rules before you pay.

    Sedgwick County MABCD: master and journeyman trade certificates (opens in a new tab)Johnson County Contractor Licensing: exam information (opens in a new tab)Kansas statute K.S.A. 12-1525 (standard examinations) (opens in a new tab)

  2. Register for the general building contractor exam (KGA) with ICC and Pearson VUE

    Create an ICC account, pick the Kansas standard exam from the Exam Catalog and schedule a Pearson VUE appointment. If you fail, wait 10 days to retake.

    Schedule with Pearson VUE (ICC exams) (opens in a new tab)ICC: State of Kansas exam bulletin (PDF) (opens in a new tab)

  3. Pass at 75% with your books

    The exam is open book with four-option multiple choice and no penalty for guessing. Bring only the approved references.

    ICC: State of Kansas exam bulletin (PDF) (opens in a new tab)

  4. Apply to your city or county

    Send your passing score and proof of experience to the jurisdiction, with its fee. It issues the certificate or license and sets renewal rules.

    Sedgwick County MABCD: master and journeyman trade certificates (opens in a new tab)Johnson County Contractor Licensing: exam information (opens in a new tab)

How to prepare

  • Study the edition the exam is built on: the 2017 NEC for electrical and the 2018 IPC, IMC and IFGC for plumbing and mechanical. Your city's adopted code can be newer.
  • The exam is open book, but there is not time to look up every answer. Tab your books by chapter and table before exam day.
  • The 2014 NEC / 2015 I-Code Kansas exams end December 1, 2026. If your jurisdiction wants a 2021-based exam, ask about the national ICC T-series instead.
  • Structural systems (42%) and planning and life safety (31%) are almost three quarters of the exam: tab IBC Chapters 3 through 10 and 16 through 23.
  • Use and occupancy and types of construction (Chapters 3 and 6), means of egress (Chapter 10) and concrete (Chapter 19) reward careful tabbing.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the 2018 IBC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

Official reference list (as published by the testing agency)
  • 2018 International Building Code (IBC) (allowed in the exam room)
  • Concrete Manual (CM) based on the 2021 IBC and ACI 318-19, or the Concrete Manual based on the 2015 IBC and ACI 318-14 (allowed in the exam room)

What's on the exam

Official content outline from International Code Council (ICC), delivered by Pearson VUE, (number of questions per topic):

TopicQuestions
Permits and General Regulations19
Building Planning and Life Safety31
Structural Systems42
Building Envelope8

The outline totals 100; the other items on the 90-question exam are unscored or unassigned.

Exam day details

  • Administered by International Code Council (ICC), delivered by Pearson VUE, for Kansas cities and counties.
  • Fee: $115 to ICC through Pearson VUE per exam. Your city or county's license fees are separate.
  • 90 multiple-choice questions in 4 hours; 75% to pass.
  • Open book: bring the approved references. Questions are four-option multiple choice with no penalty for guessing; 75% to pass.
  • Kansas has no statewide electrician, plumber or mechanical license. ICC only tests; the city or county where you want to work sponsors you and issues the license.
  • If you fail, wait 10 days to retake.
  • The 2014 NEC / 2015 I-Code exams stop being offered December 1, 2026. These Kansas standard exams are based on the 2017 NEC and 2018 I-Codes; the national T-series exams cover the 2020 NEC and 2021 I-Codes.

Frequently asked questions

What's on the Kansas general building contractor exam?

90 questions by weight: permits and general regulations 19%, building planning and life safety 31%, structural systems 42% and building envelope 8%.

Which code books does it use?

The 2018 International Building Code, plus the Concrete Manual (either the 2021 IBC/ACI 318-19 edition or the 2015 IBC/ACI 318-14 edition).

Which jurisdictions accept it?

Johnson County recognizes the KGA exam for its A (general building) license. Other cities and counties set their own rules, so confirm where you will work.

Free questions with answers

Show all 10 free questions and answers
  1. A homeowner wants to put up a one-story detached storage shed in the back yard without a building permit. Under the 2018 IBC work-exemption list, what is the largest floor area such a shed can have and still be exempt?

    Answer: 120 square feet

    Section 105.2 lists one-story detached accessory structures used as tool and storage sheds, playhouses and similar uses as exempt only when the floor area is not greater than 120 square feet. 200 square feet is a common local figure but is not in the model code. Exempt work must still comply with the code's technical requirements.

    Reference: 2018 International Building Code, Section 105.2

  2. A contractor plans a freestanding fence along a commercial site. Under 2018 IBC Section 105.2, a building permit is NOT required for a fence up to what height?

    Answer: Not over 7 feet

    Section 105.2 exempts fences not over 7 feet (2134 mm) high. A 6-foot figure is common for residential zoning but is not the IBC limit. Fences taller than 7 feet need a permit, and the exemption never authorizes work that violates other code provisions.

    Reference: 2018 International Building Code, Section 105.2

  3. A contractor filed a permit application in January but never answered the plan reviewer's comments, and no permit was issued. Under the 2018 IBC, after how long is the application deemed abandoned unless it is pursued in good faith, and how long can each extension be?

    Answer: 180 days; extensions of up to 90 days each

    Section 105.3.2 deems an application abandoned 180 days after filing unless it has been pursued in good faith or a permit issued. The building official may grant one or more extensions not exceeding 90 days each, requested in writing with justifiable cause. Do not confuse this with Section 105.5, where permit extensions can be up to 180 days.

    Reference: 2018 International Building Code, Section 105.3.2

  4. A one-story building on the level of exit discharge contains a theater lobby and auditorium that form a single 9,000-square-foot Group A-1 fire area with a posted occupant load of 340. It is not a multitheater complex. Under 2018 IBC Section 903.2.1.1, does the A-1 fire area require sprinklers?

    Answer: Yes, because the fire area has an occupant load of 300 or more

    Section 903.2.1.1 requires sprinklers for Group A-1 where any one condition exists: fire area over 12,000 square feet, occupant load of 300 or more, fire area not on a level of exit discharge, or a multitheater complex. The 340 occupant load triggers it even though the area is under 12,000 square feet and on the exit-discharge level.

    Reference: 2018 International Building Code, Section 903.2.1.1

  5. A developer is designing a small four-unit apartment building (Group R-2) of 4,800 square feet total. Under 2018 IBC Section 903.2.8, what is the sprinkler requirement?

    Answer: An automatic sprinkler system is required throughout the building

    Section 903.2.8 requires an automatic sprinkler system installed in accordance with Section 903.3 throughout all buildings with a Group R fire area. There is no area or story threshold for Group R in the 2018 IBC; Sections 903.2.8.1 through 903.2.8.4 only permit lighter system types (NFPA 13R/13D per 903.3.1.2/903.3.1.3) for certain R occupancies, not omission of sprinklers.

    Reference: 2018 International Building Code, Section 903.2.8

  6. A Group R-2 apartment building two stories tall contains 18 dwelling units. Under 2018 IBC Section 907.2.9.1, which condition requires a manual fire alarm system in this building, absent an exception?

    Answer: More than 16 dwelling units or sleeping units

    Section 907.2.9.1 requires a manual fire alarm system in Group R-2 where any dwelling unit is three or more stories above the lowest level of exit discharge, any unit is more than one story below the highest level of exit discharge, or the building contains more than 16 dwelling or sleeping units. With 18 units the third condition applies. The section's exceptions (for example, two-story buildings with 1-hour separations and exits directly to the exterior, or sprinklered buildings with waterflow-activated notification) can remove the system or the manual boxes, which is why the stem says absent an exception.

    Reference: 2018 International Building Code, Section 907.2.9.1

  7. An interior steel column delivers a total service load of 54,000 pounds to a square spread footing bearing on clay (CL), using the presumptive values of 2018 IBC Table 1806.2. What is the minimum side dimension of the square footing?

    Answer: 6.0 feet

    Table 1806.2 gives 1,500 psf vertical foundation pressure for clay, sandy clay, silty clay, clayey silt, silt and sandy silt. Required area = 54,000 / 1,500 = 36 sq ft, so the side is the square root of 36 = 6.0 feet. 5.2 feet comes from using the sand value of 2,000 psf (27 sq ft), 4.2 feet from gravel at 3,000 psf (18 sq ft), and 7.3 feet from dividing by 1,000 psf (54 sq ft).

    Reference: 2018 International Building Code, Table 1806.2

  8. A spread footing on silty sand (SM) carries a dead load of 40,000 pounds. Using the presumptive lateral sliding resistance in 2018 IBC Table 1806.2, what is the sliding resistance from friction at the base?

    Answer: 10,000 pounds

    For sand, silty sand, clayey sand, silty gravel and clayey gravel, Table 1806.2 gives a coefficient of friction of 0.25, multiplied by the dead load: 0.25 x 40,000 = 10,000 pounds. 14,000 uses 0.35 (gravel), 28,000 uses 0.70 (crystalline bedrock), and 6,000 wrongly uses the lateral bearing value of 150.

    Reference: 2018 International Building Code, Table 1806.2

  9. An unsprinklered Group M store has an interior exit stairway. Using 2018 IBC Table 803.13, what interior wall and ceiling finish class is required in that stairway?

    Answer: Class A

    Table 803.13 for Groups B, E, M and R-1 in nonsprinklered buildings requires Class A in interior exit stairways, ramps and exit passageways, Class B in corridors, and Class C in rooms and enclosed spaces. Sprinklered buildings may use Class B in the stairway.

    Reference: 2018 International Building Code, Table 803.13

  10. Which individual window pane is a hazardous location requiring safety glazing under the general provisions of 2018 IBC Section 2406.4.3, assuming no exception applies and a walking surface is adjacent to the glass?

    Answer: Pane area 12 sq ft, bottom edge 10 inches above floor, top edge 70 inches

    Section 2406.4.3 requires all four conditions: exposed area greater than 9 sq ft, bottom edge less than 18 inches above the floor, top edge greater than 36 inches above the floor, and a walking surface within 36 inches of the glass. Only the 12 sq ft pane with a 10-inch bottom edge and 70-inch top edge meets all of them.

    Reference: 2018 International Building Code, Section 2406.4.3

Sources