Requirements at a glance
| Agency | Your Kansas city or county licenses you; the International Code Council (ICC) gives the exam through Pearson VUE. There is no statewide license |
|---|---|
| Experience | Set by your city or county. Johnson County (license types A, B, C, DR) sets no years-of-experience rule: the company's qualifying individual shows a passing ICC exam or the required education and takes 8 hours of continuing education per license class each year, and the company carries general liability and workers' compensation insurance |
| Exam | KGB: 80 questions, 4 hours, 75% |
| Books allowed | 2018 International Building Code, 2018 International Residential Code and the Concrete Manual (2021 IBC/ACI 318-19 or 2015 IBC/ACI 318-14 edition) |
| Fees | $115 per ICC exam (national T-series exams are $120), plus your city or county's certificate or license fees |
Building contractors who build structures up to three stories and need a Johnson County Type B (building) license, or a similar license from a Kansas city or county that accepts the ICC standard exam.
Official links
How to get licensed, step by step
Ask your city or county which exam it accepts
Kansas law lets each jurisdiction name the standard examinations it accepts as proof of competency. Confirm the exam and the experience rules before you pay.
Sedgwick County MABCD: master and journeyman trade certificates (opens in a new tab)Johnson County Contractor Licensing: exam information (opens in a new tab)Kansas statute K.S.A. 12-1525 (standard examinations) (opens in a new tab)
Register for the building contractor exam (KGB) with ICC and Pearson VUE
Create an ICC account, pick the Kansas standard exam from the Exam Catalog and schedule a Pearson VUE appointment. If you fail, wait 10 days to retake.
Schedule with Pearson VUE (ICC exams) (opens in a new tab)ICC: State of Kansas exam bulletin (PDF) (opens in a new tab)
Pass at 75% with your books
The exam is open book with four-option multiple choice and no penalty for guessing. Bring only the approved references.
ICC: State of Kansas exam bulletin (PDF) (opens in a new tab)
Apply to your city or county
Send your passing score and proof of experience to the jurisdiction, with its fee. It issues the certificate or license and sets renewal rules.
Sedgwick County MABCD: master and journeyman trade certificates (opens in a new tab)Johnson County Contractor Licensing: exam information (opens in a new tab)
How to prepare
- Study the edition the exam is built on: the 2017 NEC for electrical and the 2018 IPC, IMC and IFGC for plumbing and mechanical. Your city's adopted code can be newer.
- The exam is open book, but there is not time to look up every answer. Tab your books by chapter and table before exam day.
- The 2014 NEC / 2015 I-Code Kansas exams end December 1, 2026. If your jurisdiction wants a 2021-based exam, ask about the national ICC T-series instead.
- Structural systems (46%) leads: footings, foundations, slabs, concrete, floors, roof and wall framing in IBC Chapters 16 through 23 and IRC Chapters 4 through 8.
- Know which book answers the question: small residential work is the IRC, other building work is the IBC.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below, and most questions come from the 2018 IBC and the 2018 IRC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
2018 International Building Code (IBC)Essential
Allowed in the exam room. The core of the building and roofing exams: permits, occupancy, egress, structural chapters and Chapter 15 roofing.
ICC store (opens in a new tab)Read free (UpCodes) (opens in a new tab)
2018 International Residential Code (IRC)Essential
Allowed in the exam room. The code for one- and two-family dwellings: design criteria, foundations, framing, roofs and life safety.
ICC store (opens in a new tab)Read free (UpCodes) (opens in a new tab)
Concrete Manual (2021 IBC/ACI 318-19 or 2015 IBC/ACI 318-14 edition)
Allowed in the exam room. Either edition of the ICC Concrete Manual is on the reference list; bring the one you are comfortable with.
Official reference list (as published by the testing agency)
- 2018 International Building Code (IBC) (allowed in the exam room)
- 2018 International Residential Code (IRC) (allowed in the exam room)
- Concrete Manual (CM) based on the 2021 IBC and ACI 318-19, or the Concrete Manual based on the 2015 IBC and ACI 318-14 (allowed in the exam room)
What's on the exam
Official content outline from International Code Council (ICC), delivered by Pearson VUE, (number of questions per topic):
| Topic | Questions | |
|---|---|---|
| Permits and General Regulations | 18 | |
| Building Planning and Life Safety | 24 | |
| Structural Systems | 46 | |
| Building Envelope | 12 |
The outline totals 100; the other items on the 80-question exam are unscored or unassigned.
Exam day details
- Administered by International Code Council (ICC), delivered by Pearson VUE, for Kansas cities and counties.
- Fee: $115 to ICC through Pearson VUE per exam. Your city or county's license fees are separate.
- 80 multiple-choice questions in 4 hours; 75% to pass.
- Open book: bring the approved references. Questions are four-option multiple choice with no penalty for guessing; 75% to pass.
- Kansas has no statewide electrician, plumber or mechanical license. ICC only tests; the city or county where you want to work sponsors you and issues the license.
- If you fail, wait 10 days to retake.
- The 2014 NEC / 2015 I-Code exams stop being offered December 1, 2026. These Kansas standard exams are based on the 2017 NEC and 2018 I-Codes; the national T-series exams cover the 2020 NEC and 2021 I-Codes.
Frequently asked questions
What's on the Kansas building contractor exam?
80 questions by weight: permits and general regulations 18%, building planning and life safety 24%, structural systems 46% and building envelope 12%.
Which code books does it use?
The 2018 International Building Code and 2018 International Residential Code, plus the Concrete Manual (either the 2021 IBC/ACI 318-19 edition or the 2015 IBC/ACI 318-14 edition).
Which jurisdictions accept it?
Johnson County recognizes the KGB exam for its B (building) license. Other cities and counties set their own rules, so confirm where you will work.
Free questions with answers
Show all 10 free questions and answers
A property owner wants a contractor to build a detached one-story tool shed in the back yard of a commercial property (IBC governs). Which shed can be built without a building permit under IBC Section 105.2?
Answer: A one-story shed with a 110-square-foot floor area
IBC 105.2 exempts one-story detached accessory structures used as tool and storage sheds, playhouses and similar uses only when the floor area is not greater than 120 square feet. The 110 sq ft shed qualifies. The 130 and 150 sq ft sheds exceed the limit, and the two-story shed is not a one-story structure. The exemption never excuses violations of other code provisions.
Reference: 2018 International Building Code, Section 105.2 (Building)
A homeowner plans a detached one-story storage building behind a single-family house regulated by the 2018 IRC. Which size of building may be built without a permit under Section R105.2?
Answer: A 190-square-foot detached one-story storage building
IRC R105.2 exempts one-story detached accessory structures when the floor area does not exceed 200 square feet. That is a larger limit than the IBC limit of 120 square feet for sheds. The 190 sq ft one-story building qualifies; 210 and 240 sq ft exceed the limit and the two-story building is not a one-story structure.
Reference: 2018 International Residential Code, Section R105.2 (Building)
Where must the building permit (or a copy) be kept while a commercial building is under construction, according to IBC Section 105.7?
Answer: On the site of the work until the project is complete
IBC 105.7 states the building permit or a copy must be kept on the site of the work until completion of the project. Inspectors expect to find it there when they arrive. The other locations are not what the section requires.
Reference: 2018 International Building Code, Section 105.7
A new office floor (Group B business area) has 6,000 square feet of gross floor area. Using IBC Table 1004.5, what is the design occupant load of the floor?
Answer: 40 occupants
Table 1004.5 gives business areas a load factor of 150 square feet per occupant (gross). 6,000 sq ft / 150 = 40 occupants. Using 100 (industrial factor) gives 60, using 200 (residential factor) gives 30, and using 50 gives 120.
Reference: 2018 International Building Code, Table 1004.5
A school classroom measures 900 square feet of net floor area. Using IBC Table 1004.5, what occupant load is used for egress design?
Answer: 45 occupants
Educational classroom areas are figured at 20 square feet per occupant on a net basis. 900 / 20 = 45. A factor of 50 (shops and vocational rooms) gives 18, 15 (unconcentrated assembly) gives 60, and 150 (business) gives 6.
Reference: 2018 International Building Code, Table 1004.5
A story in a non-sprinklered Group B building has an occupant load of 240 served by an enclosed exit stairway. Using the general capacity factor of IBC Section 1005.3.1, what is the minimum required stair capacity?
Answer: 72 inches
Stairway capacity is the occupant load times 0.3 inch per occupant: 240 x 0.3 = 72 inches. The reduced 0.2 factor applies only where the building has both a qualifying sprinkler system and an emergency voice/alarm system. 240 x 0.2 = 48 in is the other-components factor, and 0.15 gives 36 in. Remember the 44-inch minimum width of Section 1011.2 also applies.
Reference: 2018 International Building Code, Section 1005.3.1
A second-floor retail sales area in a two-story store is being designed. What minimum uniform live load applies under IBC Table 1607.1 for retail stores on upper floors?
Answer: 75 psf
Table 1607.1 lists retail stores at 100 psf on the first floor and 75 psf on upper floors; wholesale stores are 125 psf on all floors. The first-floor value of 100 psf is the common mistake for an upper-floor sales area.
Reference: 2018 International Building Code, Table 1607.1
Under IRC Section R506.2.1, what is the maximum depth of compacted fill beneath a slab-on-ground when the fill is earth, unless approved otherwise?
Answer: 8 inches
IRC R506.2.1 limits fill depth under a slab to 24 inches for clean sand or gravel and 8 inches for earth, unless otherwise approved. Fill must be free of vegetation and foreign material and compacted to give uniform support.
Reference: 2018 International Residential Code, Section R506.2.1
A roofer is installing asphalt shingles on a 3:12 roof slope. What additional underlayment requirement applies under IBC Section 1507.2.2?
Answer: Double underlayment application is required
IBC 1507.2.2 requires double underlayment application, per Section 1507.1.1, for asphalt shingle roofs with slopes from 2:12 up to 4:12. A 3:12 slope falls in that range. Slopes of 4:12 and steeper use the normal single layer.
Reference: 2018 International Building Code, Section 1507.2.2
What range of least dimension must attic ventilation openings have, or be screened to, under IRC Section R806.1?
Answer: 1/16 inch minimum and 1/4 inch maximum
IRC R806.1 requires ventilation openings with a least dimension of 1/16 inch minimum and 1/4 inch maximum. Larger openings must be covered with corrosion-resistant wire cloth, hardware cloth or similar material whose openings are within that same range, and they must be protected against rain, snow, birds and rodents.
Reference: 2018 International Residential Code, Section R806.1
Sources
- ICC: State of Kansas Contractor/Trades Examination Information Bulletin (10/12/2026) (opens in a new tab)
- Pearson VUE: ICC exams (opens in a new tab)
- Sedgwick County MABCD: master and journeyman trade certificates (opens in a new tab)
- Johnson County Contractor Licensing: exam information (opens in a new tab)
Questions last verified November 5, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.