Hawaii licensing exam

Hawaii Maintenance Electrician Exam: Practice Test & Licensing Guide

The PSI exam for Hawaii's maintenance electrician license: 50 questions on the 2020 NEC with heavy weight on general electrical knowledge and safety. Open book with the NEC provided.

Questions
50
Time limit
2 hours
Passing score
70%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10General Electrical Knowledge

A 1,500-watt, 120-volt resistance heater is on the bench. What is the approximate resistance of its element?

Requirements at a glance

AgencyHawaii Board of Electricians and Plumbers (DCCA PVL); exams by PSI
ExperienceAge 18 or older, and either 1 year of electrical maintenance work plus at least 80 hours of electrical coursework accepted by a University of Hawaii community college, or 2 years of electrical schooling with at least 1,000 hours of hands-on lab work (HRS 448E-5(b))
ExamMaintenance electrician: 50 questions, 2 hours, 70%
Books allowedNone; the 2020 NEC is provided in the exam center
Fee$95 to PSI, plus the Board's application and license fees

Electrical workers applying for a Hawaii maintenance electrician license from the Board of Electricians and Plumbers, which covers maintaining existing electrical work.

How to get licensed, step by step

  1. Apply to the Board

    Send the Board of Electricians and Plumbers your application with proof of your experience. You can't register with PSI until it approves you.

    Board of Electricians and Plumbers (opens in a new tab)Hawaii Revised Statutes chapter 448E (electricians and plumbers) (opens in a new tab)Hawaii Administrative Rules 16-80 (electricians and plumbers) (opens in a new tab)

  2. Schedule the maintenance electrician exam with PSI

    Register online or call PSI at 833-333-4754. Your approval is good for 2 years and you can test as often as you like in that time.

    Schedule with PSI (Hawaii trade exams) (opens in a new tab)

  3. Get licensed

    PSI reports your result to the Board; follow the Board's instructions for the license fee and any remaining requirements.

    Board of Electricians and Plumbers (opens in a new tab)

How to prepare

  • Hawaii's trade exams are PSI exams on specific editions: the 2020 NEC, the 2018 UPC, IMC, IFGC and IBC. Hawaii's state electrical code is older than the 2020 NEC, so study to the editions on PSI's bulletin, and check the bulletin again before test day.
  • Contractor exams are closed book except C-13, where PSI provides the NEC. Electrician exams provide the NEC too. Plumber and other contractor exams allow no reference books.
  • General electrical knowledge (14) and safety information (10) are 24 of the 50 questions; service, feeders and branch circuits is only 2.
  • Grounding and bonding and conductors and cables are 6 each: know Articles 250 and 310.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the 2020 NEC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

  • 2020 National Electrical Code (NEC), NFPA 70Essential

    Provided in the exam center, so you can't bring your own. Practice finding answers fast.

    NFPA store (opens in a new tab)

Official reference list (as published by the testing agency)
  • NFPA 70: National Electrical Code, 2020 edition (provided in the exam center)

What's on the exam

Official content outline from PSI Services (number of questions per topic):

TopicQuestions
General Electrical Knowledge14
Service, Feeders, and Branch Circuits2
Grounding and Bonding6
Conductors and Cables6
Raceways and Boxes4
Special Occupancies, Conditions, and Equipment4
Electrical Power, Motors, and Equipment for General Use4
Safety Information10

Exam day details

  • Administered by PSI Services for the Hawaii Board of Electricians and Plumbers.
  • Fee: $95 to PSI. Board application and license fees are separate.
  • 50 scored questions in 2 hours; 35 correct (70%) to pass.
  • The Board must approve your application before you can register with PSI. Your eligibility lasts 2 years, and you can test as often as you like within it.
  • PSI may add up to 10 unscored pretest questions; they do not count against your time.
  • PSI provides an online calculator, or you can bring a silent, non-programmable one.

Frequently asked questions

What's on the Hawaii maintenance electrician exam?

50 scored questions: general electrical knowledge 14, safety information 10, grounding and bonding 6, conductors and cables 6, raceways and boxes 4, special occupancies 4, electrical power, motors and equipment for general use 4 and service, feeders and branch circuits 2.

Which NEC edition is used?

The 2020 NEC, provided in the exam center.

What does a maintenance electrician license cover?

The statute defines it as a license to maintain electrical work.

Free questions with answers

Show all 10 free questions and answers
  1. A 1,500-watt, 120-volt resistance heater is on the bench. What is the approximate resistance of its element?

    Answer: 9.6 ohms

    R = E squared / P = 120 x 120 / 1,500 = 14,400 / 1,500 = 9.6 ohms. 12.5 is the current (P / E) mistaken for resistance, 19.2 doubles the answer, and 0.1 is P / E squared inverted.

    Reference: General practice, Power and resistance formulas

  2. Three resistive loads of 10, 15 and 25 ohms are connected in series across a 120-volt source. What is the circuit current?

    Answer: 2.4 amperes

    Series resistances add: 10 + 15 + 25 = 50 ohms. I = 120 / 50 = 2.4 A. 24.8 A is the answer if the loads were wrongly treated as parallel (1/R = 0.2067, R = 4.84 ohm); 12 A uses only the 10-ohm load and 4.8 A uses only the 25-ohm load.

    Reference: General practice, Series circuits

  3. Which panelboard directory entry best meets 408.4(A), which requires every circuit to be identified with a clear, specific purpose?

    Answer: Room 204, east-wall receptacles

    408.4(A) requires every circuit and circuit modification to carry a legible, permanent description that is clear, evident and specific to the circuit's purpose or use, with spare positions described accordingly. Vague entries like 'misc.' or 'various' do not let a maintenance electrician identify the circuit.

    Reference: 2020 National Electrical Code (NFPA 70), 408.4(A)

  4. Which type of connection is specifically not permitted for connecting equipment grounding conductors, grounding electrode conductors and bonding jumpers?

    Answer: A connection device or fitting that depends solely on solder

    250.8(B) states that connection devices or fittings that depend solely on solder shall not be used for connecting grounding and bonding equipment. Listed pressure connectors, exothermic welds and properly engaged machine screws are on the permitted list in 250.8(A).

    Reference: 2020 National Electrical Code (NFPA 70), 250.8(B)

  5. Seven 10 AWG copper THHN current-carrying conductors (90 C column ampacity 40 A) share one conduit. Using Table 310.15(C)(1), what is the adjusted ampacity of each?

    Answer: 28 amperes

    Table 310.15(C)(1) applies a 70 percent factor for 7-9 current-carrying conductors. Start with the 90 C value: 40 x 0.70 = 28 A. 32 A uses the 80 percent factor for 4-6 conductors, 35 A is the 75 C unadjusted value, and 20 A uses the 50 percent factor for 10-20 conductors.

    Reference: 2020 National Electrical Code (NFPA 70), Table 310.15(C)(1); Table 310.16

  6. Under 344.30(B), what is the general maximum spacing between supports for a horizontal run of rigid metal conduit?

    Answer: 10 feet

    344.30(B)(1) requires RMC to be supported at intervals not exceeding 10 ft. Table 344.30(B) allows greater spacing for straight runs made up with threaded couplings, and 4-1/2 ft is the spacing for flexible metal conduit.

    Reference: 2020 National Electrical Code (NFPA 70), 344.30(B)

  7. Which Class I group classification is assigned to acetylene under the Code's hazardous location rules?

    Answer: Group A

    500.6(A)(1) classifies acetylene as Class I, Group A. Group B includes hydrogen, Group C ethylene, and Group D includes propane and gasoline vapors.

    Reference: 2020 National Electrical Code (NFPA 70), 500.6(A)(1)

  8. Which value is used to size motor overload protection for a motor under 430.6(A)(2)?

    Answer: The current rating marked on the motor nameplate

    430.6(A)(1) uses the Table 430.248/430.250 full-load current for conductor ampacity and branch-circuit device sizing, but 430.6(A)(2) requires the actual nameplate current to be used when sizing separate motor overload protection.

    Reference: 2020 National Electrical Code (NFPA 70), 430.6(A)(1), (A)(2)

  9. An employee must work near exposed energized parts on a portable ladder. What type of side rails must the ladder have under 1910.333(c)(7)?

    Answer: Nonconductive side rails

    29 CFR 1910.333(c)(7) states portable ladders must have nonconductive side rails if they are used where the employee or the ladder could contact exposed energized parts. The same requirement appears in 1926.1053(b)(12) for construction.

    Reference: 29 CFR 1910.333 (OSHA), 1910.333(c)(7)

  10. Why must an electrician working near exposed energized parts remove a metal watch band and finger rings?

    Answer: Conductive jewelry may contact live parts and cause burns or shock

    29 CFR 1910.333(c)(8) prohibits conductive articles of jewelry and clothing, such as watch bands, bracelets, rings and key chains, if they might contact exposed energized parts, unless they are rendered nonconductive by covering, wrapping or other insulating means.

    Reference: 29 CFR 1910.333 (OSHA), 1910.333(c)(8)