Georgia licensing exam

Georgia General Contractor Exam (NASCLA Commercial General Building): Practice Test & Licensing Guide

The NASCLA-accredited Commercial General Building Contractor exam that Georgia uses for General Contractor and General Contractor Limited Tier licenses: 115 questions from general requirements to procurement and contracting. Open book, 70% to pass.

Questions
115
Time limit
5.5 hours
Passing score
70%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10General Requirements

A tenant fit-out creates a 12,000 sq ft open office suite (Group B business use, no unusual features). Using IBC Table 1004.5, what occupant load does the code assign to the suite?

Requirements at a glance

AgencyGeorgia State Licensing Board for Residential and General Contractors; exams by PSI
ExamNASCLA-accredited Commercial General Building exam (115 questions, 330 minutes, open book, 70% (81) to pass) plus the Business and Law exam; also used for General Contractor Limited Tier
Books allowed2021 or 2024 IBC, ACI 318, ICC A117.1, Principles and Practices of Commercial Construction, Construction Project Management, the NASCLA guide, 29 CFR 1926 and the other references on the PSI list
Fees$72 (Residential-Basic or Residential-Light Commercial), $106 (General Contractor) or $60 (Business and Law) to PSI per the PSI bulletin, plus the Board's application and license fees

Individuals and qualifying agents applying for a Georgia General Contractor or General Contractor Limited Tier license from the State Licensing Board for Residential and General Contractors, in addition to the Business and Law exam.

How to get licensed, step by step

  1. Apply to the Board

    Get approved by the Residential and General Contractors board first, then register with PSI. You need both the Business and Law exam and the trade exam.

    Georgia State Licensing Board for Residential and General Contractors (opens in a new tab)

  2. Mind the attempt limits

    You get 2 attempts per exam approval within the 1-year eligibility period. After two failures of the same exam you must wait at least 1 year (O.C.G.A. 43-41-6(g)).

    PSI bulletin: Georgia residential and general contractors (opens in a new tab)

How to prepare

  • Procurement and contracting requirements (31) and general requirements (25) are 56 of the 115 questions: know contracts, bidding, scheduling, safety and project administration as well as the building code.
  • You may use the 2021 or the 2024 IBC; where the two differ, learn the edition you bring.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the IBC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

  • International Building Code (IBC): 2018 edition for Residential-Light Commercial; 2021 or 2024 edition for General ContractorEssential

    Allowed in the exam room. Georgia's 2024 IBC with Georgia amendments is the current state code, but the Residential-Light Commercial list pins the 2018 edition.

    ICC store (opens in a new tab)

  • 29 CFR 1926 (OSHA Construction Standards), sections on your reference list

    Trenching, scaffolds, fall protection and ladders. Print just the listed sections.

    Read free (eCFR) (opens in a new tab)

  • Contractors Guide to Business, Law, and Project Management: Georgia Construction Industry Licensing Board, 5th Edition (NASCLA)

    On the Board's reference lists for the electrical, conditioned air and plumbing exams.

    NASCLA store (opens in a new tab)

Official reference list (as published by the testing agency)
  • International Building Code, 2021 or 2024 (ICC)
  • ACI 318, 2014 or 2019 (Building Code Requirements for Structural Concrete)
  • ICC A117.1-2017 (Accessible and Usable Buildings and Facilities)
  • Principles and Practices of Commercial Construction, 11th Edition (2024)
  • Construction Project Management, 4th or 5th Edition (Gould and Joyce)
  • NASCLA Contractors Guide to Basic Business, Law and Project Management, 14th Edition
  • 29 CFR Part 1926 (OSHA) or the PSI OSHA excerpts
  • The other references on the PSI list (masonry, roofing, steel deck, gypsum, post-tensioning, green building and stormwater guides)

What's on the exam

Official content outline from PSI Services (number of questions per topic):

TopicQuestions
General Requirements25
Site Construction15
Concrete6
Masonry4
Metals6
Wood5
Thermal and Moisture Protection5
Doors, Windows, and Glazing4
Finishes5
Mechanical and Plumbing Systems6
Electrical Systems3
Procurement and Contracting Requirements31

Exam day details

  • Administered by PSI Services for the Georgia State Licensing Board for Residential and General Contractors.
  • Fee: $106 to PSI per the PSI bulletin. The Board's application and license fees are separate.
  • 115 scored questions in 330 minutes; 81 correct (70%) to pass.
  • Open book. Code questions use the IBC edition on the PSI list (2021 or 2024). References may be highlighted, underlined and indexed with permanent tabs, but not written in.
  • This NASCLA-accredited exam also serves General Contractor Limited Tier applicants. Passing it lets you send your transcript through NASCLA's National Examination Database to other participating states.
  • General Contractor licensing also requires the Georgia Business and Law exam.
  • Under the PSI bulletin you get 2 attempts per exam approval within the 1-year eligibility period; after two failures of the same exam you must wait at least 1 year (O.C.G.A. 43-41-6(g)).

Frequently asked questions

What's on the Georgia General Contractor exam?

115 questions: procurement and contracting requirements 31, general requirements 25, site construction 15, concrete 6, metals 6, mechanical and plumbing systems 6, wood 5, thermal and moisture protection 5, finishes 5, masonry 4, doors, windows and glazing 4 and electrical systems 3.

Is the same exam used for General Contractor Limited Tier?

Yes. The PSI bulletin lists the NASCLA-accredited exam for both General Contractor and General Contractor Limited Tier, for individuals and qualifying agents.

Which exams do I need for a General Contractor license?

The NASCLA-accredited General Contractor exam and the Georgia Business and Law exam.

Free questions with answers

Show all 10 free questions and answers
  1. A tenant fit-out creates a 12,000 sq ft open office suite (Group B business use, no unusual features). Using IBC Table 1004.5, what occupant load does the code assign to the suite?

    Answer: 80 occupants

    Table 1004.5 gives business areas one occupant per 150 sq ft of gross floor area: 12,000 / 150 = 80. Dividing by 100 gives 120, dividing by 200 gives 60, and dividing by 15 (the assembly table-and-chair factor) gives 800; none of those is the business factor.

    Reference: 2024 International Building Code (Georgia Building Code, 2024 edition), Table 1004.5

  2. A trench is 5 feet deep and a competent person suspects a hazardous atmosphere could build up in it. Under 29 CFR 1926.651(g)(1), what is required?

    Answer: Test the atmosphere before employees enter, since the excavation is deeper than 4 feet

    Section 1926.651(g)(1) requires atmospheric testing in excavations deeper than 4 feet where oxygen deficiency or a hazardous atmosphere exists or could reasonably be expected, before employees enter. Waiting for symptoms is not acceptable.

    Reference: 29 CFR 1926 Subpart P (Excavations), 29 CFR 1926.651(g)(1)

  3. A contractor will pour a 36 ft by 20 ft slab-on-ground 6 inches thick and wants to order 5 percent extra for waste. How many cubic yards should be ordered?

    Answer: 14.0 cubic yards

    Thickness = 6 in / 12 = 0.5 ft. Volume = 36 x 20 x 0.5 = 360 cu ft; 360 / 27 = 13.33 cu yd. Add 5 percent: 13.33 x 1.05 = 14.0 cu yd. 13.3 ignores waste, 16.8 treats 6 inches as 0.6 ft, and 28.0 treats the thickness as 1 foot.

    Reference: General concrete estimating practice, Volume and unit conversion

  4. Of the ASTM C270 mortar types M, S, N and O, which has the highest compressive strength and is often specified for foundation walls and retaining walls in contact with soil?

    Answer: Type M

    Mortar types in descending order of strength are M, S, N and O. Type M is used where high strength and durability are needed, such as masonry below grade. IBC 2103.2.1 requires masonry mortar to conform to TMS 602.

    Reference: ASTM C270 mortar types (general masonry practice); 2024 IBC, ASTM C270 property requirements; IBC Section 2103.2.1

  5. A W14x22 steel beam is 36 feet long. In the designation, 14 is the nominal depth in inches and 22 is the weight in pounds per linear foot. About how much does the beam weigh, for selecting slings and the crane?

    Answer: 792 pounds

    Weight = 22 lb/ft x 36 ft = 792 lb. Multiplying depth by length (14 x 36) gives 504, using half the length gives 396, and doubling the length gives 1,584.

    Reference: Structural steel shape designations (AISC), W-shape designation and weight

  6. A plumber needs to notch a 2x6 stud (actual depth 5 1/2 inches) in an exterior bearing wall in conventional light-frame construction. Under 2024 IBC Section 2308.6.2 (2308.5.9 in the 2021 IBC), what is the maximum notch depth?

    Answer: 1 3/8 inches

    Exterior wall and bearing partition studs may not be cut or notched more than 25 percent of their depth: 5.5 x 0.25 = 1.375 in (1 3/8 in). The 40 percent limit (2.2 in) is for nonbearing partitions, one-third gives 1.83 in, and one-sixth gives 0.92 in.

    Reference: 2024 International Building Code (Georgia Building Code, 2024 edition), Section 2308.6.2

  7. A low-slope asphalt shingle roof is planned at a slope of 3:12. Under IBC Section 1507.2.2, asphalt shingles may be used on slopes of 2:12 or greater, and what extra requirement applies at 3:12?

    Answer: Double underlayment application

    Section 1507.2.2 permits asphalt shingles only on slopes of 2 units vertical in 12 horizontal or more, and for slopes from 2:12 up to 4:12 requires double underlayment application under 1507.1.1. Ice barriers are a separate requirement for areas with a history of ice damming.

    Reference: 2024 International Building Code (Georgia Building Code, 2024 edition), Section 1507.2.2

  8. A Group B office building has no sprinkler system. Using IBC Table 803.13, what is the minimum interior finish class for an interior exit stairway?

    Answer: Class A

    In the Table 803.13 row for Groups B, E, M and R-1, interior exit stairways in nonsprinklered buildings require Class A. With sprinklers the requirement drops to Class B. Class C appears for rooms and enclosed spaces.

    Reference: 2024 International Building Code (Georgia Building Code, 2024 edition), Table 803.13

  9. Under IPC Section 903.1.1, an open plumbing vent pipe extending through an ordinary roof must terminate at least how far above the roof?

    Answer: 6 inches

    Section 903.1.1 requires open vent pipes that extend through a roof to terminate not less than 6 inches above it (Georgia text effective 1/1/2026). Seven feet applies where the roof is used as a promenade, sunbathing deck or similar space (903.1.2).

    Reference: 2024 International Plumbing Code (Georgia Plumbing Code, 2024 edition), Section 903.1.1

  10. Under the Miller Act, 40 U.S.C. 3131(b), what must a contractor furnish before being awarded a federal construction contract above the Act's threshold ($100,000 in the statute text; the FAR adjusts it for inflation)?

    Answer: Performance and payment bonds

    Section 3131(b) requires a performance bond (protecting the Government against default) and a payment bond (protecting persons supplying labor and material) before a federal construction contract above $100,000 is awarded. Insurance policies and letters of credit do not satisfy that requirement.

    Reference: Miller Act, 40 U.S.C. 3131, 40 U.S.C. 3131(b)

Sources

Questions last verified November 15, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.