Requirements at a glance
| Agency | Georgia State Licensing Board for Residential and General Contractors; exams by PSI |
|---|---|
| Exam | Business and Law, 50 questions, 120 minutes, open book, 70% (35) to pass |
| Books allowed | Georgia-NASCLA Contractors Guide to Business, Law and Project Management, 3rd Edition |
| Fees | $72 (Residential-Basic or Residential-Light Commercial), $106 (General Contractor) or $60 (Business and Law) to PSI per the PSI bulletin, plus the Board's application and license fees |
Everyone applying for a Georgia Residential-Basic, Residential-Light Commercial or General Contractor license from the State Licensing Board for Residential and General Contractors. Pass it once and it covers every other residential and general license.
Official links
How to get licensed, step by step
Apply to the Board
Get approved by the Residential and General Contractors board first, then register with PSI. You need both the Business and Law exam and the trade exam.
Georgia State Licensing Board for Residential and General Contractors (opens in a new tab)
Register with PSI
Book and pay PSI online or at 855-744-0314.
Schedule with PSI (Georgia residential and general contractors) (opens in a new tab)PSI bulletin: Georgia residential and general contractors (opens in a new tab)
Mind the attempt limits
You get 2 attempts per exam approval within the 1-year eligibility period. After two failures of the same exam you must wait at least 1 year (O.C.G.A. 43-41-6(g)).
PSI bulletin: Georgia residential and general contractors (opens in a new tab)
How to prepare
- Estimating and bidding (7), business organization and financial management (7), project management and lien law (6) and contracts (6) are half the exam.
- Pass it once and it satisfies the business and law requirement for all Georgia residential and general contractor licenses.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below, and most questions come from the Georgia-NASCLA guide. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
Georgia-NASCLA Contractors Guide to Business, Law and Project Management (Residential and General Contractors), 3rd EditionEssential
The only reference allowed on the Business and Law exam.
Official reference list (as published by the testing agency)
- Georgia-NASCLA Contractors Guide to Business, Law and Project Management, Georgia State Licensing Board for Residential and General Contractors, 3rd Edition
What's on the exam
Official content outline from PSI Services (number of questions per topic):
| Topic | Questions | |
|---|---|---|
| Licensing Requirements | 5 | |
| Estimating and Bidding | 7 | |
| Business Organization and Financial Management | 7 | |
| Tax Laws | 5 | |
| Labor Laws | 5 | |
| Project Management and Lien Law | 6 | |
| Contracts | 6 | |
| Risk Management | 4 | |
| Environmental and Safety | 5 |
Exam day details
- Administered by PSI Services for the Georgia State Licensing Board for Residential and General Contractors.
- Fee: $60 to PSI per the PSI bulletin. The Board's application and license fees are separate.
- 50 scored questions in 120 minutes; 35 correct (70%) to pass.
- Open book: the Georgia-NASCLA guide is the only reference. You may highlight, underline and index it with permanent tabs but not write in it.
- Passing the Georgia Business and Law exam meets the business and law requirement for all residential and general contractor licenses.
- Under the PSI bulletin you get 2 attempts per exam approval within the 1-year eligibility period; after two failures of the same exam you must wait at least 1 year (O.C.G.A. 43-41-6(g)).
Frequently asked questions
What's on the Georgia Business and Law exam?
50 questions: estimating and bidding 7, business organization and financial management 7, project management and lien law 6, contracts 6, licensing requirements 5, tax laws 5, labor laws 5, environmental and safety 5 and risk management 4.
Do electricians and plumbers take it?
No. Electrical, plumbing, conditioned air and low voltage contractors are licensed by the Construction Industry Licensing Board, whose exams include their own law and administration sections. This exam is for residential and general contractors.
What book is allowed?
The Georgia-NASCLA Contractors Guide to Business, Law and Project Management, 3rd Edition, for the Residential and General Contractors board.
Free questions with answers
Show all 10 free questions and answers
A candidate receives a first exam approval and fails the Business and Law exam on the first try. Within the same 1-year eligibility period, how many total attempts does the bulletin give on that first approval for each exam?
Answer: 2 attempts to pass each exam within the eligibility year
On a first exam approval the candidate has 2 attempts to pass both the Business and Law and the Trade exams within the 1-year eligibility period. One failure leaves one attempt; it does not end the approval.
Reference: PSI Candidate Information Bulletin, Georgia Residential and General Contractors, Examination Scheduling Procedures, Eligibility
A contractor's direct cost for a remodel is $240,000. The contractor wants a 20% gross margin, meaning profit is 20% of the contract price. What contract price is required?
Answer: $300,000
Margin is a share of price, so price = cost / (1 - 0.20) = 240,000 / 0.80 = $300,000. Check: 20% of 300,000 is 60,000 and 300,000 - 60,000 = 240,000. The $288,000 answer is a 20% markup on cost (240,000 x 1.20), which yields only a 16.7% margin.
Reference: General estimating practice, Markup versus gross margin
A contract includes a $2,500 lighting-fixture allowance. The owner selects fixtures that cost $3,100 installed. How is the difference normally handled?
Answer: The owner pays the $600 overage by an adjustment to the contract price
An allowance is a placeholder for items not yet selected. If the selection costs more than the allowance, the contract sum is increased by the difference (3,100 - 2,500 = $600); if it costs less, the owner receives a credit.
Reference: General estimating practice, Allowances
A sole proprietor's business is sued over unpaid supplier invoices and cannot pay. What is the owner's exposure?
Answer: The owner's personal assets can be reached because the owner and the business are legally the same
A sole proprietorship is not a separate legal entity, so the owner has unlimited personal liability for its debts. Registering a trade name does not create liability protection; forming an LLC or corporation is what limits it.
Reference: General business practice, Business structures: sole proprietorship
What are the employer's and employee's Social Security and Medicare tax rates on regular wages, per IRS Publication 15?
Answer: Each pays 6.2% Social Security and 1.45% Medicare, so 7.65% apiece
Social Security is 6.2% and Medicare is 1.45% for the employee and an equal amount for the employer, 7.65% each and 15.3% combined, on wages below the Social Security wage base. Medicare has no wage cap.
Reference: IRS Publication 15 (Circular E), Employer's Tax Guide, Section 9 (Social Security and Medicare Taxes)
A nonexempt laborer earns $24.00 per hour and works 46 hours in one fixed workweek. What is gross pay for the week under the FLSA?
Answer: $1,176
Regular pay: 40 x 24 = $960. Overtime rate: 24 x 1.5 = $36 per hour; 6 overtime hours x 36 = $216. Total = 960 + 216 = $1,176. $1,104 pays all 46 hours at the regular rate (46 x 24), and $1,656 pays all 46 hours at the overtime rate.
Reference: 29 U.S.C. 207(a)(1) (Fair Labor Standards Act), Section 7(a): overtime calculation
A subcontractor is asked to sign a lien waiver and release before the progress check has been received. Which type of waiver best protects the subcontractor if the payment never arrives?
Answer: A conditional waiver, effective only when payment is actually received
A conditional waiver releases lien rights only upon receipt of the stated payment. An unconditional waiver is effective on signing, so if the check never arrives or bounces, the lien right may already be lost. Where a state statute prescribes waiver forms, those forms and their effective-upon-payment wording control.
Reference: General business practice, Lien waivers
A contract provision is ambiguous, and each side proposes a different reasonable reading. Under the general rule of contract interpretation, how is the ambiguity usually resolved?
Answer: It is construed against the party that drafted the contract
Courts generally interpret an unclear term against the drafter (contra proferentem), since that party could have written it clearly. Ambiguity does not by itself void a contract.
Reference: General business practice, Contracts: interpretation of ambiguity
Which insurance covers the structure under construction against fire, wind and vandalism before the owner accepts it?
Answer: Builder's risk insurance
Builder's risk is a property policy on the building, materials and often equipment on site during construction. Auto, professional and workers' compensation policies insure vehicles, design or advice errors, and employee injuries.
Reference: General business practice, Insurance: builder's risk
A contractor will replace windows in a house built in 1965, and the work will disturb painted surfaces. Under EPA's Renovation, Repair and Painting rule, what is required?
Answer: The firm must be certified and must use certified renovators with lead-safe work practices
EPA's RRP rule applies to paid renovation, repair and painting work that disturbs lead-based paint in housing built before 1978. The firm must be certified and use certified renovators who follow lead-safe work practices (in states with an EPA-authorized program, the state issues the certifications under equivalent rules). Window replacement is never treated as exempt minor repair, regardless of the square footage disturbed.
Reference: 40 CFR Part 745, Subpart E, 745.81, 745.85 and 745.89 (RRP: firm certification and work practices)
Sources
- PSI: Georgia Residential and General Contractors Candidate Information Bulletin (opens in a new tab)
- Georgia State Licensing Board for Residential and General Contractors (opens in a new tab)
Questions last verified November 14, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.