CSLB's trade exam for the C-33 Painting and Decorating license: planning and estimating, substrate repair and surface preparation, application of paint, wallcoverings and finishes, and safety. Closed book.

Questions
Not published by California
Time limit
3.5 hours
Passing score
Not published by California
Books
Closed book
What to study ↓

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10Planning and Estimating

A painter must estimate the paint needed for a triangular gable end that is 20 ft wide at the base and 8 ft high at the peak. How many square feet of surface is that?

Requirements at a glance

AgencyCalifornia Contractors State License Board (CSLB); exams by PSI
Experience4 years of journey-level experience in the trade within the last 10 years
ExamsC-33 Painting and Decorating trade exam, plus the Law and Business exam
FormatClosed book, 4-choice, 3.5 hours per exam; question count and pass score not published
Study referencesPCA Industry Standards and Craftsman Manual; The Painter's Handbook; EPA lead-safe renovation guidance
Fees$450 application (one classification); $200 (sole owner) or $350 initial license fee after you pass; $25,000 contractor bond; fingerprints

Qualifiers for a California C-33 Painting and Decorating contractor license. Taken together with the Law and Business exam.

How to get licensed, step by step

  1. Pick your classification

    Find the CSLB classification for your work. The qualifier named on the license needs 4 years of journey-level experience in it within the past 10 years.

    CSLB: Get Licensed to Build (PDF) (opens in a new tab)

  2. Apply to CSLB

    Submit the $450 application with your experience verification. CSLB reviews it and refers you to test.

    California Contractors State License Board (CSLB) (opens in a new tab)CSLB: List of all fees (opens in a new tab)

  3. Schedule Law and Business and the C-33 exam with PSI

    Book both exams with PSI. Pass both within 18 months of acceptance; each exam sitting costs $51.43 paid to PSI. Passing results stay good for 5 years.

    PSI: schedule your CSLB exam (877-392-6422) (opens in a new tab)

  4. Bond, fees and fingerprints

    After you pass, CSLB sends a Bond and Fee letter: file the $25,000 contractor bond, pay the initial license fee and complete fingerprints to receive your license.

How to prepare

  • The CSLB exams are closed book and CSLB doesn't publish question counts or the passing score, so aim for steady scores well above 80% on our practice tests rather than a bare minimum.
  • Use CSLB's free study guide for your classification: it lists the sections, approximate weights and the references the questions come from.
  • Every license needs two exams (Law and Business plus the trade exam). Pass both within 18 months of CSLB accepting your application.
  • Substrate repair and surface preparation is the biggest section at about 30%: practice surface prep for each substrate and coating failure causes.
  • Planning and estimating (about 28%) includes coverage rates, labor and material takeoffs.
  • Know lead-safe work practices for pre-1978 buildings and the Cal/OSHA lead rules.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

What to study

This is a closed-book exam, so nothing comes into the exam room. Study from these:

Official reference list (as published by the testing agency)
  • CSLB C-33 Painting and Decorating study guide (applies to exams on or after April 27, 2022)
  • PCA Industry Standards and PCA Craftsman Manual; The Painter's Handbook (Gottsegen)
  • EPA, Steps to Lead Safe Renovation
  • Cal/OSHA Title 8 safety orders (2025)

What's on the exam

Official content outline from PSI Services (number of questions per topic):

TopicQuestions
Planning and Estimating28
Substrate Repair and Surface Preparation30
Application of Paint, Wallcoverings, and Finishes21
Safety21

Exam day details

  • Administered by PSI Services for the California Contractors State License Board (CSLB).
  • Fee: $450 CSLB application fee (one classification), paid to CSLB. Separately, each exam sitting costs $51.43, paid directly to PSI (a retake costs it again, after a 21-day wait). Cancel or reschedule at least 2 days ahead to keep your fee. The $200 or $350 initial license fee and the $25,000 bond come after you pass.
  • Closed book: no code books, notes or calculators from home. PSI provides a calculator, and every question has four choices with no penalty for guessing.
  • You get 3.5 hours per exam and see your result on screen. A failing report breaks your performance down by section.
  • Every license needs two exams: Law and Business plus the trade exam for the classification (C-61 has no trade exam). You must pass both within 18 months of CSLB accepting your application, and passing results stay good for 5 years.
  • The qualifier needs 4 years of journey-level experience within the last 10 years. Each exam sitting costs $51.43 paid to PSI, and you must cancel or reschedule at least 2 days before the appointment to keep the fee.
  • Work worth $500 or more (labor and materials) requires a California contractor license.

Note: CSLB does not publish the number of questions or the passing score for its exams. The 100-question practice length is ours, and the pass line shown in our practice tests is only a study target. Check CSLB's study guide and the PSI bulletin for current details.

Frequently asked questions

What's on the California C-33 exam?

CSLB lists approximate weights: substrate repair and surface preparation 30%, planning and estimating 28%, application of paint, wallcoverings and finishes 21% and safety 21%.

Does the C-33 exam cover lead-safe work?

The study guide names EPA's Steps to Lead Safe Renovation and the Cal/OSHA lead rules, so expect safety and surface-preparation questions on lead-based paint.

How many questions are on the exam and what score do I need?

CSLB doesn't publish either number, so we don't state them. Each exam is closed book with 4-choice questions and 3.5 hours to finish. Your result appears on screen, and a failing report shows how you did by section.

Free questions with answers

Show all 10 free questions and answers
  1. A painter must estimate the paint needed for a triangular gable end that is 20 ft wide at the base and 8 ft high at the peak. How many square feet of surface is that?

    Answer: 80 sq ft

    A gable is a triangle, so area = 1/2 x base x height = 0.5 x 20 x 8 = 80 sq ft. 160 sq ft is the full rectangle (20 x 8) that forgets the one-half factor; 40 sq ft halves the answer twice.

    Reference: General trade practice, Concept: area takeoff for triangles

  2. A room is 14 ft by 12 ft with 8 ft ceilings. The walls get two coats; the ceiling is not painted. Openings total 45 sq ft (one door and two windows). The paint covers 350 sq ft per gallon per coat. How many whole gallons should be ordered?

    Answer: 3 gallons

    Perimeter = 2 x (14 + 12) = 52 ft. Wall area = 52 x 8 = 416 sq ft. Less openings: 416 - 45 = 371 sq ft. Two coats = 742 sq ft. 742 / 350 = 2.12 gallons, so order 3 whole gallons. Two gallons is rounding down and would run short; 4 or more comes from skipping the opening deduction and adding waste twice.

    Reference: General trade practice, Concept: coverage and gallons math

  3. An exterior of a house measures 40 ft by 30 ft and the walls are 9 ft high. Openings (doors, windows, garage door) total 180 sq ft. Two coats of a paint rated at 400 sq ft per gallon are specified. How many whole gallons are needed?

    Answer: 6 gallons

    Perimeter = 2 x (40 + 30) = 140 ft. Gross wall area = 140 x 9 = 1,260 sq ft. Net = 1,260 - 180 = 1,080 sq ft. Two coats = 2,160 sq ft. 2,160 / 400 = 5.4 gallons, rounded up to 6. Three gallons covers only one coat; 5 rounds down; 7 results from forgetting to subtract the openings (2,520 / 400 = 6.3).

    Reference: General trade practice, Concept: coverage and gallons math

  4. A painter finds regular gypsum wallboard in a bathroom ceiling that is soaked and soft where a shower leak has been running for months. Under the California Building Code, why is plain gypsum wallboard a poor choice for this location?

    Answer: It is not to be used with direct water exposure or continuous high humidity

    CBC 2508.2 says gypsum wallboard shall not be used where there will be direct exposure to water or continuous high humidity. The damaged board should be removed and replaced after the leak is fixed, then primed and painted. Painting over wet, soft board only hides the failure.

    Reference: 2025 California Building Code (CBC), Section 2508.2

  5. An uncarpeted floor in an RRP work area measures 120 sq ft. For cleaning verification it must be wiped in roughly equal sections, each smaller than 40 sq ft, with a new wet cloth per section. What is the fewest number of sections?

    Answer: 4 sections

    40 CFR 745.85(b)(1)(ii)(B) says a surface greater than 40 sq ft must be divided into roughly equal sections each less than 40 sq ft. 120 / 40 = 3 sections of exactly 40 sq ft, which is not less than 40, so at least 4 sections (30 sq ft each) are needed. Each cloth is compared to the cleaning verification card.

    Reference: 40 CFR Part 745 (EPA Renovation, Repair and Painting Rule), 745.85(b)(1)(ii)(B)

  6. A painter's lead exposure, measured without regard to a respirator, averages 2 micrograms per cubic meter over 8 hours. What does that number represent in the lead standard?

    Answer: The action level

    The action level in 8 CCR 1532.1(b) is 2 micrograms per cubic meter as an 8-hour TWA; at or above it the employer must follow monitoring and other requirements. The PEL is 10, the level 3 presumption is 500 (50 times the PEL) and the blasting exception is 25.

    Reference: Cal/OSHA Title 8 (Construction Safety Orders), 8 CCR 1532.1(b)

  7. A painter will roll a semi-gloss (nonflat) interior enamel in a building in the South Coast AQMD. Under Rule 1113, what is the maximum VOC content for a nonflat coating?

    Answer: 50 grams per liter

    Rule 1113 Table of Standards 1 sets the nonflat coating limit at 50 g/L (less water and exempt compounds, excluding colorant added to tint bases), the same as flats. 100 g/L applies to primers, sealers and undercoaters, 250 g/L to interior stains and 275 g/L to varnish and lacquer.

    Reference: South Coast AQMD Rule 1113 (Architectural Coatings), (c)(1) and Table of Standards 1

  8. What is the correct order for painting a room that has the walls, ceiling and trim all being coated?

    Answer: Ceiling, then walls, then trim

    Working from the top down lets drips and spatter land on surfaces not yet finished. The ceiling is coated first, then the walls, with trim last (or trim first when the scheme calls for cutting in to it). Painting the ceiling last spatters the finished walls.

    Reference: General trade practice, Concept: sequence of work

  9. Overlap lines (lap marks) show in a dry latex wall finish after a roller job. What is the most common cause?

    Answer: Letting the edge dry before rolling into it

    Lap marks come from rolling fresh paint against an edge that has already begun to dry, so the coating builds up twice. Keeping a wet edge by working in manageable sections and rolling from wet into dry prevents them.

    Reference: General trade practice, Concept: maintaining a wet edge

  10. Under 8 CCR 1532.3 (respirable crystalline silica in construction), which pair of values is correct for the PEL and action level, each as an 8-hour TWA?

    Answer: PEL 50 and action level 25 micrograms per cubic meter

    California's silica standard sets the PEL at 50 micrograms per cubic meter and the action level at 25, each as an 8-hour TWA. The 10 and 2 pair belongs to lead, and the reversed pair confuses which limit is the higher number.

    Reference: Cal/OSHA Title 8 (Construction Safety Orders), 8 CCR 1532.3(b) and (d)(1)