The state-run exam for Alaska's electrician journeyman certificate of fitness, based on the 2020 NEC. Open book, 70% to pass, 4-hour limit.

Questions
Not published by Alaska
Time limit
4 hours
Passing score
70%
Books
Open book

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10General NEC 2020: Definitions and Requirements

Which description matches the Article 100 definition of "readily accessible"?

Requirements at a glance

AgencyAlaska Department of Labor and Workforce Development, Mechanical Inspection (state-run exam, not PSI)
Experience8,000 hours as an Alaska trainee in commercial or industrial electrical work (at most 2,000 hours residential, 1,000 classroom hours) (8 AAC 90.160)
ExamOpen book, 70% to pass, 4-hour maximum; the number of questions and topic weights are not published
Books allowed2020 NEC (open book)
Fees$50 non-refundable application fee, then a $200 certificate fee when issued

Electrician trainees in Alaska who have 8,000 hours of commercial or industrial electrical experience (up to 2,000 hours residential) and apply to Mechanical Inspection for a journeyman certificate of fitness.

How to get licensed, step by step

  1. Hold a trainee certificate

    Alaska counts experience only while you hold a trainee certificate of fitness in the trade, and only in a registered program.

    Alaska DOLWD Mechanical Inspection (opens in a new tab)

  2. Apply to Mechanical Inspection

    Send the application packet, fees and experience verification forms. Processing takes 7 to 10 business days before you can schedule.

    Alaska DOLWD Mechanical Inspection (opens in a new tab)

  3. Take the journeyman electrician exam

    The Department tests in Anchorage, Juneau and Fairbanks on the first and third Wednesday of each month; job centers, union halls and approved proctors cover other places. Bring a government photo ID.

    Mechanical Inspection: testing information and study guides (opens in a new tab)

  4. Retest if needed

    If you fail, wait 30 days from the date of your last exam. Results are emailed to you.

    Mechanical Inspection: testing information and study guides (opens in a new tab)

How to prepare

  • The state publishes no blueprint. Our questions are a balanced mix of the code book on the Department's study guide list, so use them to learn where things are in the book.
  • The exam is open book, so practice finding answers quickly in a tabbed copy of the code. Confirm the books and format with Mechanical Inspection at 907-269-4925.
  • Certificates last 2 years and need 16 hours of continuing education.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

    Official reference list (as published by the testing agency)
    • National Electrical Code (NFPA 70), 2020 edition (open book, per the Mechanical Inspection study guide list)

    What's on the exam

    Estimated topic weighting. No official breakdown is published:

    TopicQuestions
    General NEC 2020: Definitions and Requirements6
    General NEC 2020: Services, Feeders and Branch Circuits12
    General NEC 2020: Grounding and Bonding8
    General NEC 2020: Wiring Methods and Conductors12
    General NEC 2020: Equipment, Motors and Transformers10
    General NEC 2020: Special Occupancies and Equipment8
    General NEC 2020: Load Calculations4

    Exam day details

    • Administered by State of Alaska Department of Labor and Workforce Development, Mechanical Inspection (not PSI).
    • Fee: No separate exam fee is listed. Mechanical Inspection charges a $50 non-refundable application fee and a $200 certificate fee when issued.
    • Journeyman certificate (8 AAC 90.160): 8,000 hours as a trainee (at most 2,000 hours residential, 1,000 classroom hours), exam, $50 application fee and $200 certificate fee. The certificate lasts 2 years and requires 16 hours of continuing education.
    • If you fail, wait 30 days from the date of your last exam before retesting.
    • State-run, open book, 70% to pass, 4-hour maximum. The Department publishes no question count or topic weights.
    • Mechanical Inspection tests in Anchorage, Juneau and Fairbanks on the first and third Wednesday of each month; job centers, union halls and approved proctors cover other places. Approval of your application packet takes 7 to 10 business days before you can schedule.

    Note: The Alaska Department of Labor does not publish the number of questions or topic weights for certificate of fitness exams. Our topic split and 60-question practice length are estimates, and a TODO(verify) remains on the exact books and scope. Check with Mechanical Inspection at 907-269-4925.

    Frequently asked questions

    How many questions are on the Alaska journeyman electrician exam?

    The Department of Labor does not publish a question count or topic weights. It does set a 4-hour maximum and a 70% pass score.

    Is the Alaska journeyman exam open book?

    Yes. The Department lists the 2020 NEC as the open-book study reference.

    Where do I take it?

    Mechanical Inspection tests in Anchorage, Juneau and Fairbanks on the first and third Wednesday of each month. Job centers, union halls and approved proctors cover other places.

    Free questions with answers

    Show all 10 free questions and answers
    1. Which description matches the Article 100 definition of "readily accessible"?

      Answer: Capable of being reached quickly for operation or inspection without climbing over or removing obstacles or using portable ladders

      Readily accessible means reaching the equipment quickly without obstacles or a portable ladder. Equipment behind a fixed panel is only "accessible" and a locked room fails the quick-reach test. This definition drives rules such as the location of service disconnects and overcurrent devices.

      Reference: 2020 National Electrical Code (NFPA 70), Article 100, Definitions: Readily Accessible

    2. A 20-ampere, 120-volt branch circuit supplies several general-purpose receptacle outlets in a shop. The electrician also wants to connect a fixed exhaust fan to the same circuit. What is the maximum rating of fixed utilization equipment, other than luminaires, permitted on that circuit?

      Answer: 10 amperes, which is 50 percent of the branch-circuit rating

      Where a branch circuit also serves lighting units or cord-and-plug equipment not fastened in place, fixed utilization equipment may not exceed 50 percent of the circuit rating. On a 20-A circuit that is 10 A. The 80 percent figure applies to continuous loads and does not govern here.

      Reference: 2020 National Electrical Code (NFPA 70), 210.23(A)(2)

    3. A 400-ampere feeder has a field-installed 10-ft tap that leaves the feeder enclosure and terminates in a single 30-ampere circuit breaker serving a 30-ampere calculated load. The tap meets all other 240.21(B)(1) conditions. What is the minimum ampacity of the tap conductors?

      Answer: 40 amperes, which is one-tenth of the 400-A feeder overcurrent device

      A 10-ft tap conductor must have ampacity not less than the calculated load and, for field taps leaving the enclosure, not less than 10 percent of the feeder overcurrent device rating: 400 x 0.10 = 40 A. The 25% and 33% figures are traps from the 25-ft tap rule, which has different limits.

      Reference: 2020 National Electrical Code (NFPA 70), 240.21(B)(1)

    4. Which AC system supplying premises wiring is required to be grounded?

      Answer: A 3-phase, 4-wire, 208Y/120-volt system whose neutral serves 120-volt loads

      Systems of 50 to 1000 V must be grounded where they can be grounded so the maximum voltage to ground is 150 V or less, where they are 3-phase 4-wire wye with the neutral used as a circuit conductor, or 4-wire delta with a midpoint used as a circuit conductor. Three-wire delta motor systems may remain ungrounded under 250.21.

      Reference: 2020 National Electrical Code (NFPA 70), 250.20(B)

    5. Rigid metal conduit is buried under a lawn at a commercial building (no street, driveway or parking area, no concrete cover). What minimum cover does Table 300.5 require?

      Answer: 6 in. of cover, the general-location value for rigid metal conduit

      Rigid metal and intermediate metal conduit need 6 in. of cover in the general (all locations not specified) row. Direct-buried cables need 24 in. and listed nonmetallic raceways need 18 in. in the same row.

      Reference: 2020 National Electrical Code (NFPA 70), Table 300.5

    6. Type UF cable on a 120/240-volt, 30-ampere circuit is direct buried under a lawn at a commercial site. What minimum cover is required?

      Answer: 24 in.

      Direct-burial cable in the general row of Table 300.5 needs 24 in. of cover. The 12 in. depth is limited to residential 120-V, 20-A circuits with GFCI protection, and this circuit is 30 A and 240 V.

      Reference: 2020 National Electrical Code (NFPA 70), Table 300.5

    7. A 7 1/2-hp, 230-volt, 3-phase squirrel-cage motor has a Table 430.250 full-load current of 22 A. What is the maximum rating of an inverse-time circuit breaker for branch-circuit short-circuit and ground-fault protection, using Table 430.52 and the standard-size exception?

      Answer: 60 amperes, because 22 A x 250% = 55 A and the next standard size is permitted

      Table 430.52 allows an inverse-time breaker at 250 percent of the full-load current: 22 x 2.50 = 55 A. Since 55 A is not a standard rating in 240.6(A), the next higher standard size, 60 A, is permitted. A 70 A device would use the wrong percentage.

      Reference: 2020 National Electrical Code (NFPA 70), 430.52(C)(1), Table 430.52; 240.6(A)

    8. Which value is used to size the branch-circuit conductors for a typical continuous-duty 3-phase motor?

      Answer: The full-load current from Table 430.250, not the nameplate current

      For conductor ampacity, short-circuit protection and disconnect ratings, the Code uses the Table 430.250 full-load current for the motor's horsepower and voltage. Only motor overload protection is based on the nameplate current.

      Reference: 2020 National Electrical Code (NFPA 70), 430.6(A)(1)

    9. A grain-handling building has combustible dust from flour and starch in the air. Which hazardous (classified) location group applies?

      Answer: Class II, Group G, which covers flour, starch and grain dusts

      Class II locations involve combustible dust. Group E is metal dust, Group F is carbonaceous dust such as coal or coke, and Group G covers flour, starch, grain, wood and plastic dusts. Class III is for ignitable fibers and flyings, which have no groups.

      Reference: 2020 National Electrical Code (NFPA 70), 500.5(C); 500.6(B)

    10. A 40,000-sq-ft hotel with no ballrooms or dining rooms has a general lighting unit load of 1.7 VA per sq ft from Table 220.12. Using the hotel and motel demand factors in Table 220.42, what is the general lighting demand load?

      Answer: 36,000 VA, which is 20,000 x 60% plus 48,000 x 50%

      Connected load = 40,000 x 1.7 = 68,000 VA. For hotels and motels, Table 220.42 applies 60 percent to the first 20,000 VA (12,000 VA) and 50 percent to the portion from 20,001 to 100,000 VA: 48,000 x 0.50 = 24,000 VA. Demand = 12,000 + 24,000 = 36,000 VA. The 29,200 VA figure uses the older 50/40 percent factors that the 2020 edition replaced. The demand factors do not apply to areas such as ballrooms where all lighting is used at once.

      Reference: 2020 National Electrical Code (NFPA 70), Table 220.12; Table 220.42