Requirements at a glance
| Agency | Rhode Island Contractors' Registration and Licensing Board (CRB); exam by PSI |
|---|---|
| Exam | 40 questions, 100 minutes, open book, 70% to pass (28 correct) |
| Experience | None to sit the exam; the CRB has its own licensing requirements |
| Books allowed | 29 CFR 1926; ACPA Concrete Pipe and Box Culvert Installation (2007); DIPRA ductile iron guide (2021 version from 10/9/2024); Pipe and Excavation Contracting (Roberts); RI Plumbing Code 2019; RIGL 39-1.2 (dig law) |
| Fees | $180 to PSI per exam; CRB application and license fees are separate |
Contractors who install, repair or replace underground sewer, storm drain and water lines and services outside buildings, from the main to within 5 feet of the building wall. Gas and telecommunications work are excluded.
Official links
How to get licensed, step by step
Schedule with PSI and sit the exam
No application is needed first: register at test-takers.psiexams.com/ricon or call 855-746-8173, pay the $180 fee (valid for one year, not refundable or transferable), and bring two forms of signed ID, one with a photo. You see your result when you finish.
Schedule with PSI (Rhode Island CRB) (opens in a new tab)PSI: Rhode Island CRB Candidate Information Bulletin (opens in a new tab)
Apply to the CRB
After you pass, send your application to the CRB, which has its own requirements and fees. If you fail, you retake the exam (and pay again) before you can apply.
Rhode Island Contractors' Registration and Licensing Board (opens in a new tab)
How to prepare
- Excavating and grading (8) is the largest section; RI dig law, CFR safety and sewer pipes are 5 questions each.
- The 2012 DIPRA guide isn't allowed from 1/15/2025.
- The exam is open book with permanent tabs and highlighting only; no writing in your books, no sticky notes. 70% to pass, and 1 to 5 unscored experimental questions may be added.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
Official reference list (as published by the testing agency)
- 29 CFR Part 1926 (OSHA construction), latest amendments, or 29 CFR 1926 Selections by PSI
- Concrete Pipe and Box Culvert Installation, 2007 (American Concrete Pipe Association)
- DIPRA Installation Guide for Ductile Iron Pipe, 2007 (revised 2012); the 2021 version can be used from 10/9/2024 and the 2012 version isn't allowed from 1/15/2025
- Pipe and Excavation Contracting, Dave Roberts, 2011 (Craftsman Book Company)
- State of Rhode Island Plumbing Code, 2019 (ICC)
- Title 39, Chapter 39-1.2: Excavation Near Underground Utility Facilities (Rhode Island dig law)
What's on the exam
Official content outline from PSI Services (number of questions per topic):
| Topic | Questions | |
|---|---|---|
| Safety-Code of Federal Regulations | 5 | |
| General Knowledge | 6 | |
| Underground Utilities-Concrete Pipe Installation | 4 | |
| Underground Utilities-Ductile Pipe Installation | 4 | |
| Excavating and Grading | 8 | |
| Backflow | 3 | |
| RI Dig Laws | 5 | |
| Underground Sewer Pipes | 5 |
Exam day details
- Administered by PSI Services for the Rhode Island Contractors' Registration and Licensing Board (CRB).
- Fee: $180 to PSI per exam. Not refundable or transferable, and valid for one year from payment. CRB application and license fees are separate.
- 40 questions in 100 minutes; 28 correct (70%) to pass.
- Open book: bring your own copies of the listed references. You may highlight, underline and index them with permanent tabs, but not write in them; sticky notes and loose papers are removed.
- A small number (1 to 5) of unscored experimental questions may be added; their time doesn't count against your time.
- Bring two forms of ID with your signature, one with a photo, in the name on your registration, and arrive 30 minutes early.
- There are no prerequisites to sit the exam. You pass it first and then apply to the CRB. You see your result when you finish, and you pay again to retake.
- The PSI bulletin says code questions use only the edition listed; other references may use later editions.
Frequently asked questions
What's on the Rhode Island underground utilities exam?
40 questions: excavating and grading 8, general knowledge 6, safety (CFR) 5, RI dig laws 5, underground sewer pipes 5, concrete pipe installation 4, ductile pipe installation 4 and backflow 3.
Does the license cover gas lines?
No. The statutory definition excludes gas and telecommunications work.
Which ductile iron guide is allowed?
The bulletin allows the 2021 DIPRA guide from 10/9/2024 and drops the 2012 version after 1/15/2025. Check the current bulletin.
Free questions with answers
Show all 10 free questions and answers
A sewer trench is being dug beside an old landfill and is deeper than 4 feet. Below what oxygen concentration does OSHA treat the trench air as oxygen deficient, requiring testing before employees enter?
Answer: 19.5 percent
Section 1926.651(g)(1)(i) calls for atmospheric testing before entry in excavations deeper than 4 feet where oxygen deficiency (less than 19.5 percent oxygen) or another hazardous atmosphere could reasonably be expected, such as near landfills. 20.9 percent is the normal oxygen content of air, so it is not the trigger.
Reference: 29 CFR Part 1926 Subpart P, 1926.651(g)(1)(i)
A backhoe ruptures a natural gas line and gas is escaping. In addition to notifying the utility, what must the responsible party do under Rhode Island's dig law?
Answer: Call 9-1-1 promptly and keep people away until emergency crews arrive
Section 39-1.2-11 requires the responsible party to call 9-1-1 promptly after a serious electrical short or release of regulated gas or hazardous liquid, and to evacuate the area where there is immediate danger to life or health. Backfilling is prohibited.
Reference: RIGL Chapter 39-1.2 (Excavation Near Underground Utility Facilities), 39-1.2-11
What is the height of a barometric loop used for backflow protection under the IPC, and how may it be used?
Answer: 35 feet high, only as an atmospheric or pressure-type vacuum breaker
IPC Section 608.14.4 says barometric loops precede the point of connection, extend vertically to a height of 35 feet, and may be used only as an atmospheric-type or pressure-type vacuum breaker. The loop protects against backsiphonage, not backpressure.
Reference: 2021 International Plumbing Code (Rhode Island RISBC-3), 608.14.4
In DIPRA Type 4 laying conditions, how deep must the sand, gravel or crushed-stone bedding be under the pipe?
Answer: 1/8 of the pipe diameter, but not less than 4 inches
Section 3.1 describes Type 4 as pipe bedded in sand, gravel or crushed stone to a depth of 1/8 pipe diameter (4 inches minimum), with backfill compacted to the top of the pipe at about 80 percent Standard Proctor (AASHTO T-99).
Reference: DIPRA Installation Guide for Ductile Iron Pipe (Revised 04-24), Section 3.1, Type 4
In which direction should the bell end of bell-and-spigot concrete pipe point when the pipe is laid in a sewer line?
Answer: Upstream, with the spigot pointing downstream
ACPA's Jointing section says placement starts at the outlet end of the line, with the bell end pointing upstream and the spigot or tongue pointing downstream. This helps keep bedding material from being forced into the bell during jointing and makes coupling easier.
Reference: Concrete Pipe and Box Culvert Installation (American Concrete Pipe Association), Installation, Jointing
A sewer will run 250 feet at a uniform 1.0 percent slope downhill. The upstream invert is 98.00 feet. What is the downstream invert elevation?
Answer: 95.50 feet
A 1.0 percent slope drops 1 foot per 100 feet. Over 250 feet the drop is 250 x 0.01 = 2.50 feet, so 98.00 - 2.50 = 95.50 feet. 97.75 uses 0.1 percent (a 0.25 ft drop), 93.00 uses 2 percent (a 5.00 ft drop), and 98.00 ignores the slope.
Reference: Standard grade calculation (slope x length = drop), 1.0 percent = 1 foot per 100 feet
A 4-inch building sewer must be laid at the code minimum slope. Using the IPC table for horizontal drainage pipe, how much total drop is needed over a 60-foot run?
Answer: 7.5 inches
IPC Table 704.1 requires at least 1/8 inch per foot for pipe sizes of 3 to 6 inches. Over 60 feet the minimum drop is 60 x 1/8 = 7.5 inches. Using 1/4 inch per foot (the slope for 2 1/2 inch and smaller) would give 15 inches.
Reference: 2021 International Plumbing Code (Rhode Island RISBC-3), Table 704.1
Under the content outline for the Rhode Island underground utilities exam, underground utility work runs between the main or lateral and a point how far from the outer wall of a building?
Answer: Within 5 feet
The bulletin's definition covers installing, repairing, altering or replacing underground utilities, sewer, storm drain and water lines, services and laterals, between the main, lateral, related services or appurtenances and within five feet of the outer wall of a building or structure. Work inside that 5-foot zone belongs to the plumbing trade.
Reference: PSI Candidate Information Bulletin, Rhode Island Contractors' Registration and Licensing Board, Underground Utilities License Examination, definitions
Which work is specifically excluded from the Rhode Island 'underground utility' definition used for this license?
Answer: Gas and telecommunications work
The bulletin's definition specifically excludes gas and telecommunications work and any work defined in RIGL 28-27-28. Water lines, services, laterals, sewer lines and storm drainage lines are all inside the definition.
Reference: PSI Candidate Information Bulletin, Rhode Island Contractors' Registration and Licensing Board, Underground Utilities License Examination, definitions
Under the Rhode Island IPC amendment, what separation is required between a water service pipe and a building drain or sewer?
Answer: 10 feet of undisturbed or compacted earth, unless an exception applies
The RISBC-3 version of IPC 603.2 requires water service pipe and building drain or sewer to be separated by 10 feet of undisturbed or compacted earth. Exceptions allow a 12-inch vertical separation, a shared trench with approved sewer materials, or sleeving at crossings.
Reference: 2021 International Plumbing Code (Rhode Island RISBC-3), 603.2 (RISBC-3 amendment)
Sources
- PSI: Rhode Island CRB Candidate Information Bulletin (Last Revised 6/21/2022, reference updates through 2026) (opens in a new tab)
- Rhode Island Contractors' Registration and Licensing Board (opens in a new tab)
Questions last verified November 17, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.