Requirements at a glance
| Agency | Minnesota Department of Labor and Industry (DLI) |
|---|---|
| Experience | No operating experience required (16 and 17 year olds need an approved course) |
| Exam | 50 questions, 2.5 hours, 70% to pass |
| Books allowed | DLI does not state whether the exam is open or closed book; ask DLI when you schedule |
| Fees | $50 exam fee (nonrefundable, good for one year), plus the two-year license fee (DLI chart, September 2023: special $20, first and second class $40) |
Operators of boilers up to 50 horsepower (or shift engineers in a plant up to 100 horsepower) and apprentices. No operating experience is required.
Official links
How to get licensed, step by step
Apply to DLI
Send DLI your special boiler engineer application and the $50 exam fee. A special engineer may operate boilers up to 50 horsepower, or take shift duty in a plant up to 100 horsepower.
Minnesota Department of Labor and Industry (DLI) (opens in a new tab)DLI: boiler engineer licenses (opens in a new tab)
Schedule your exam
After DLI approves your application, you schedule the exam in DLI's iMS system. DLI gives exams at its St. Paul office (Tuesday to Thursday) and at outstate sites including Duluth, Mankato, Rochester and St. Cloud.
Take the exam
You have 2.5 hours and need 70%. DLI's chief boiler inspector prepares the exam; DLI does not state whether it is open or closed book, so ask DLI before exam day.
DLI: boiler engineer licenses (opens in a new tab)Minnesota Rules chapter 5225 (boilers) (opens in a new tab)Minnesota Statutes 326B.95 to 326B.998 (boilers) (opens in a new tab)
Results and retakes
DLI mails results in about 2 weeks. If you fail, wait 30 days after receiving results before reapplying.
How to prepare
- Know low-pressure boiler limits (steam 15 psig or less; water 160 psig and 250 F or less), safety valves, water gauges, blowdown and daily operating checks.
- Every DLI exam is open book, but with DLI-supplied references only: a code book without tabs, the DLI laws-and-rules booklet and a desk calculator. You cannot bring your own books, so practice finding answers fast rather than relying on tabs.
- DLI publishes no topic weights, so our topic split is an estimate. Several versions of each exam are in use, and some questions ask for more than one answer or the choice that does not apply.
- DLI publishes no blueprint, sample questions or book policy for boiler exams, so our topic split is an estimate. Questions rest on Minnesota Statutes 326B.95 to 326B.998, Rules 5225 and textbook-standard boiler practice.
- DLI's listed study books are Low Pressure Boilers (Steingress), High Pressure Boilers (Steingress and Frost) and Stationary Engineering. Grade A exams are longer and include the grade B content, so this bank covers grades C and B.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
What to study
This is a closed-book exam, so nothing comes into the exam room. Study from these:
Minnesota Rules chapter 5225 and Statutes 326B.95 to 326B.998 (boilers and pressure vessels)Essential
The licensing, operation, attendance and safety rules DLI's chief boiler inspector tests. DLI does not state whether the exam is open book.
Official reference list (as published by the testing agency)
- Minnesota Statutes 326B.95 to 326B.998 and Minnesota Rules chapter 5225 (DLI's Second Class - Chief Statutes and Rules study document)
- DLI's listed study books: Low Pressure Boilers (Steingress), High Pressure Boilers (Steingress and Frost) and Stationary Engineering (Steingress, Frost and Walker); the special exam also lists Safe Boiler Operation Fundamentals (ATP)
- ASME Boiler and Pressure Vessel Code (Sections I, IV, VI and VII, per Rules 5225.0050) and the National Board Inspection Code
What's on the exam
Estimated topic weighting. No official breakdown is published:
| Topic | Questions | |
|---|---|---|
| Boiler Types, Parts and Fittings | 12 | |
| Safety Valves, Water Gauges and Controls | 10 | |
| Operation, Firing and Combustion | 10 | |
| Feedwater, Water Treatment and Blowdown | 6 | |
| Inspection, Registration and Boiler Safety (Minnesota Statutes 326B.95 to 326B.998) | 6 | |
| Licensing and Attendance Rules (Minnesota Rules 5225) | 6 |
Exam day details
- Administered by the Minnesota Department of Labor and Industry (DLI), which gives its own exams.
- Fee: $50 exam fee (nonrefundable, good for one year); the two-year license fee is separate (DLI chart, September 2023: special $20, second and first class $40).
- DLI's chief boiler inspector prepares the written exams (Rules 5225.0500). The time limit is 2.5 hours and the passing score is 70%.
- DLI does not state on any page we found whether the exam is open or closed book, and it publishes no blueprint, topic weights or sample questions. Our topic split is an estimate.
- Grades are nested: C covers low-pressure boilers (steam 15 psig or less; water 160 psig and 250 F or less), B covers all boilers, and A adds steam engines and turbines. DLI's A-grade exams are longer and include the B content. This practice bank covers the B-grade content.
- A failed exam can be retaken after 30 days (DLI license chart). All but the special license also need a notarized affidavit of operating experience.
Note: DLI publishes no blueprint, weights, sample questions or book policy for boiler exams, so our topic split is an estimate. Questions rest on Minnesota Statutes 326B.95 to 326B.998, Rules 5225 and textbook-standard boiler practice; we did not have the ASME or National Board codes or the Steingress texts on file.
Frequently asked questions
How many questions are on the Minnesota special boiler engineer exam?
50 questions in 2.5 hours; you need 70% to pass (DLI License Classifications chart).
What can a special engineer operate?
Boilers up to 50 horsepower, or shift duty in a plant up to 100 horsepower, and work as an apprentice. 10 square feet of heating surface equals 1 boiler horsepower (Rules 5225.1000).
Do I need experience?
No operating experience is required for the special license; 16 and 17 year olds need an approved course (Rules 5225.0550).
Free questions with answers
Show all 10 free questions and answers
In a firetube boiler, where do the hot combustion gases travel as they heat the water?
Answer: Inside the boiler tubes, with the water surrounding the outside of the tubes
In a firetube boiler the combustion gases pass inside the tubes and heat is transferred to the water between the tubes and the outer shell. The reverse arrangement (water inside the tubes, gases outside) describes a watertube boiler.
Reference: Improving Steam System Performance: A Sourcebook for Industry, 2nd ed. (U.S. DOE), Section 1, Generation: Boilers (Firetube boilers)
Scotch marine firetube boilers are, in general, NOT used where the required steam pressure is above about what value?
Answer: 300 psig
Scotch marine boilers generate steam on the large shell side, which limits the pressure they can safely produce; the DOE sourcebook says they are generally not used above 300 psig. Pressures near 3,000 psig are the realm of watertube boilers.
Reference: Improving Steam System Performance: A Sourcebook for Industry, 2nd ed. (U.S. DOE), Section 1, Generation: Boilers (Firetube boilers)
A high-pressure boiler has 550 square feet of water heating surface. What is the minimum number of safety valves under Minnesota Rules 5225.4100?
Answer: Two
Rule 5225.4100 requires every boiler to have at least one safety valve and requires two or more on a high-pressure boiler with more than 500 square feet of water heating surface. At 550 square feet this high-pressure boiler needs at least two.
Reference: Minnesota Rules, chapter 5225, 5225.4100 Safety Valves, first paragraph
A safety valve on a Minnesota boiler must be set no higher than:
Answer: The maximum allowable working pressure shown on the inspector's certificate for that boiler
Rule 5225.4100 says every safety valve must be stamped under the ASME Code and set no higher than the maximum allowable working pressure on the inspector's certificate. A valve set above that value could let the boiler exceed its safe limit.
Reference: Minnesota Rules, chapter 5225, 5225.4100 Safety Valves, first paragraph
According to Minnesota Rules 5225.1110, what must the boiler room logbook document?
Answer: When the boiler checks were made, who made them, and what specific equipment checks were done
Rule 5225.1110, subpart 1 requires a logbook kept in the boiler room by the chief engineer or an engineer the chief designates. It documents when the boiler checks were made, who made them, and which specific checks of equipment were made, and it must be available to the boiler inspector.
Reference: Minnesota Rules, chapter 5225, 5225.1110, subp. 1 (logbook)
Which of the following is NOT a factor listed in Rule 5225.1110 for deciding whether a boiler is operated, maintained and attended in a prudent and attentive manner?
Answer: The purchase price of the boiler
The listed factors include size or capacity of the plant, condition of the boilers and appurtenances, frequency of checks and maintenance history, extent of public occupancy, operating service conditions including weather, compliance with other statutes and rules, and any other factor that adversely affects safety. The purchase price is not among them.
Reference: Minnesota Rules, chapter 5225, 5225.1110, subp. 1, items A to G
Under Rule 5225.5000, how must the boiler feed pipe be equipped?
Answer: A check valve near the boiler, and a valve or cock between the check valve and the boiler
Rule 5225.5000 requires the feed pipe to have a check valve near the boiler and a valve or cock between the check valve and the boiler. Where two or more boilers share a feed source, each branch also needs a globe or regulating valve between the check valve and the supply, with the inlet under the disk. A check valve only at the pump, or a safety valve in the feed line, does not meet the rule.
Reference: Minnesota Rules, chapter 5225, 5225.5000 Feed Piping and Check Valve, first paragraph
A feed line has a combination stop-and-check valve with one seat and disk and a stem that closes the valve when screwed down. How does Rule 5225.5000 treat it?
Answer: It is considered only a stop valve, so a separate check valve must still be installed near the boiler
The rule says a combination stop-and-check valve with only one seat and disk and a stem that can close it must be considered only a stop valve. A separate check valve must therefore still be installed as the first paragraph requires.
Reference: Minnesota Rules, chapter 5225, 5225.5000 Feed Piping and Check Valve, second paragraph
Who is responsible for ensuring that a newly installed boiler is inspected by the department before it is placed in operation, and for the inspection fees for that initial inspection?
Answer: The person who installs the boiler is responsible for the inspection and its fees
Subdivision 1(b) says anyone who installs a boiler must ensure it is inspected by the department after installation is complete and before it is placed in operation, and the fees for that initial inspection are the installer's responsibility. Later annual inspection fees belong to the owner.
Reference: Minnesota Statutes, chapter 326B, 326B.958, subd. 1(b), (e)
Under Minnesota Statutes 326B.978, into which classes are boiler engineers divided?
Answer: Chief engineers, first class engineers, second class engineers and special engineers
Subdivision 1 divides engineers into four classes: chief, first class and second class (each with Grade A, B and C) and special engineers. The special license is the entry level.
Reference: Minnesota Statutes, chapter 326B, 326B.978, subd. 1
Sources
- Minnesota DLI: boiler engineer licenses (opens in a new tab)
- Minnesota Statutes 326B.95 to 326B.998 (boilers and pressure vessels) (opens in a new tab)
- Minnesota Rules chapter 5225 (boilers, pressure vessels and licensing) (opens in a new tab)
- Minnesota DLI: license exam schedule (opens in a new tab)
Questions last verified November 9, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.