Michigan licensing exam

Michigan Master Electrician Exam: Practice Test & Licensing Guide

The PSI exam for Michigan's master electrician license: 76 questions on the same NEC topics as the journeyman exam plus planning and supervising electrical installations. Open book, 75% to pass.

Questions
76
Time limit
3 hours
Passing score
75%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10Grounding and Bonding

A service has 4/0 AWG copper ungrounded conductors. The grounding electrode conductor runs to a metal underground water pipe and to the building steel. What is the minimum size copper grounding electrode conductor?

Requirements at a glance

AgencyMichigan LARA, Bureau of Construction Codes; exam by PSI
Exam76 questions, 3 hours, 75% to pass
Books allowedNEC (items based on 2023; factory markings and tabs only, no NEC Handbook), Michigan Electrical Code Rules Part 8, 2016 PA 407 and 1972 PA 230
Fees$100 to PSI per attempt, plus LARA application and license fees
ExperienceAge 22 or older, at least 12,000 hours of electrical work over at least 6 years under a master electrician, and a journeyman license held for at least 2 years (MCL 339.5713)
Attempts2 attempts within 1 year, then reapply with the State; 2 failures within 2 years also require a 1-year wait and an approved code course (MCL 339.5713)
Electrical contractorThere is no separate contractor exam: an electrical contractor license goes to someone who holds a master license or employs a master electrician (MCL 339.5711)

Journeyman electricians applying to LARA for a Michigan master electrician license, which lets you supervise electrical work and qualify an electrical contractor license.

How to get licensed, step by step

  1. Apply to LARA

    Submit your master electrician application with your experience documentation. LARA approves you before you can pay for the exam.

    Michigan LARA: Bureau of Construction Codes (opens in a new tab)Michigan Legislature: Skilled Trades Regulation Act, 2016 PA 407 (opens in a new tab)

  2. Schedule with PSI

    Follow your approval letter to pay and book. You get 2 attempts within 1 year at $100 each.

    Schedule with PSI (Michigan electrical) (opens in a new tab)PSI: Michigan electrical candidate bulletin (opens in a new tab)

  3. Prepare your books

    Bring a bound NEC with factory markings and tabs only, plus bound copies of Part 8, PA 407 and PA 230. Printed BCC documents need 3 staples and no tabs.

    PSI: Michigan electrical candidate bulletin (opens in a new tab)

How to prepare

  • Michigan adopts the 2023 NEC with Michigan Part 8 amendments (effective 3/12/2024). Exam items are based on the 2023 edition, so tab your book for 2023 articles.
  • Practice finding Table 310.16, Chapter 9 conduit fill tables and Article 430 motor tables quickly; most questions are look-ups plus a calculation.
  • The master exam adds planning and supervising installations on top of the journeyman content, so expect more service, feeder and load calculation work.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the 2023 NEC and Michigan Part 8. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

Official reference list (as published by the testing agency)
  • National Electrical Code (NEC): exam items are based on the 2023 edition; other editions may be used. Factory markings, highlights and factory tabs only. The NEC Handbook is not allowed.
  • Michigan Electrical Code Rules, Part 8 (2023 Part 8 rules adopt the 2023 NEC with Michigan amendments)
  • Skilled Trades Regulation Act, 2016 PA 407
  • State Construction Code Act, 1972 PA 230

What's on the exam

Estimated topic weighting. No official breakdown is published:

TopicQuestions
Grounding and Bonding7
Overcurrent Protection6
Wiring Methods and Installations8
Boxes and Cabinets4
Services5
Feeders4
Motors and Motor Controls5
Special Occupancies5
Load Calculations6
Lighting3
Appliances3
Box and Raceway Fill4
Power Limited Circuits3
General Electrical Trade Knowledge3
Electrical Theory2
Planning and Supervising Electrical Installations4
Skilled Trades Regulation Act, Part 8 Rules and PA 2304

Exam day details

  • Administered by PSI Services for the Michigan Department of Licensing and Regulatory Affairs (LARA), Bureau of Construction Codes.
  • Fee: $100 to PSI per attempt, non-refundable and valid for one year. LARA application and license fees are separate.
  • 76 questions in 3 hours; 75% to pass.
  • The bulletin lists topics but no per-topic weights. Our topic weights are an estimate that adds up to 76. The master exam covers the same installation topics as the journeyman exam plus the knowledge needed to plan and supervise electrical installations.
  • Master, journeyman and sign specialist candidates are limited to 2 attempts within 1 year. After that you must reapply with the State to become eligible again. Under state law, failing the master exam 2 times within 2 years also means waiting at least 1 year and completing a board-approved course before retesting (MCL 339.5713(2)).
  • Reference material must be bound. Material printed from the BCC website must be stapled in 3 places on the left edge in separate documents, with no highlighting, marking or tabs. You may bring a straight edge rule without calculations.
  • The Department (LARA BCC) must approve your application first. It sends a notification letter with instructions to pay and schedule with PSI; only the State decides eligibility.
  • PSI may add up to ten unscored experimental questions; they are not counted in your score and don't take time from the exam.
  • Cancel or reschedule at least 2 days before the appointment to keep your fee; late cancellations and no-shows forfeit it.

Frequently asked questions

What's different about the Michigan master electrician exam?

It covers the same installation topics as the journeyman exam and adds the knowledge required to plan and supervise electrical installations, plus the Skilled Trades Regulation Act, Part 8 rules and PA 230.

Is there a separate Michigan electrical contractor exam?

No. LARA issues the electrical contractor license to someone who holds a master electrician license or employs one, so the master electrician exam is the one to pass.

Which references can I bring?

The NEC (factory markings and tabs only; no NEC Handbook), 2016 PA 407, 1972 PA 230 and the Michigan Electrical Code Rules Part 8, all bound and unmarked.

Free questions with answers

Show all 10 free questions and answers
  1. A service has 4/0 AWG copper ungrounded conductors. The grounding electrode conductor runs to a metal underground water pipe and to the building steel. What is the minimum size copper grounding electrode conductor?

    Answer: 2 AWG

    Table 250.66: 4/0 AWG falls in 'over 3/0 through 350 kcmil', which requires 2 AWG copper. 4 AWG is the row for 2/0 or 3/0 conductors, and 1/0 is the row for conductors over 350 through 600 kcmil.

    Reference: NEC 2023 (NFPA 70), Table 250.66

  2. A 400-ampere feeder breaker supplies a 10-ft field-installed feeder tap. The tap conductors leave the enclosure in which the tap is made and terminate in a disconnect containing the tap's overcurrent device. Under the 10-ft tap rule, what minimum tap conductor ampacity is set by the feeder overcurrent device rating alone?

    Answer: 40 amperes

    240.21(B)(1) requires, among other conditions, that the tap conductor ampacity be at least one-tenth of the rating of the device protecting the feeder: 400 x 0.10 = 40 A. The tap must also carry the calculated load and be not less than the rating of the device it terminates in. 133 A (one-third) is the 25-ft tap rule.

    Reference: NEC 2023 (NFPA 70), 240.21(B)(1)

  3. Rigid metal conduit carrying 480-volt feeders will be buried beneath a commercial parking lot. What is the minimum cover from Table 300.5(A)?

    Answer: 24 in.

    Table 300.5(A) gives 24 in. for every wiring method under streets, highways, roads, alleys, driveways and parking lots. The 6 in. figure for rigid metal conduit applies in the 'all locations not specified' row and does not apply under vehicle traffic.

    Reference: NEC 2023 (NFPA 70), Table 300.5(A)

  4. A pull box has an angle pull. Conductors of 6 AWG or larger enter through the left wall in one row of three conduits: 2 in., 2 in. and 1-1/2 in. They leave through the bottom wall. What is the minimum distance from the entering conduits to the wall opposite them (the right wall)?

    Answer: 15.5 in.

    314.28(A)(2): distance = 6 x the largest raceway plus the sum of the other raceways in the same row on the same wall: 6 x 2 = 12, plus 2 + 1.5 = 3.5, giving 15.5 in. Using only 6 x 2 gives 12 in.; adding all three raceways (5.5) gives 17.5 in.; adding only the 1.5 in. gives 13.5 in.

    Reference: NEC 2023 (NFPA 70), 314.28(A)(2)

  5. A 4 in. square metal box contains two 12-2 NM cables with ground (four 12 AWG insulated conductors, two 12 AWG grounds), one duplex receptacle (single yoke), and two internal cable clamps. Using Table 314.16(B)(1) (12 AWG = 2.25 cu in.), what minimum box volume is required?

    Answer: 18.0 cu in.

    Count: four conductors = 4; one yoke = 2; internal clamps (one allowance for all) = 1; equipment grounding conductors (one allowance for up to four) = 1. Total 8 x 2.25 = 18.0 cu in. 15.75 omits the clamp allowance, 20.25 counts each ground separately (9 x 2.25), and 13.5 omits the device yoke (6 x 2.25).

    Reference: NEC 2023 (NFPA 70), 314.16(B)

  6. What is the maximum number of service disconnecting means permitted for each service under the 2023 NEC?

    Answer: Six

    230.71 requires one disconnecting means per service unless 230.71(B) applies. 230.71(B) permits two to six service disconnects for each service, in separate enclosures, panelboards, switchboard sections, switchgear compartments or metering centers. Seven or more per service is not permitted.

    Reference: NEC 2023 (NFPA 70), 230.71(B)

  7. Standard (Part III) service calculation for a 2,400 sq ft dwelling on a 120/240-volt single-phase service: general lighting and receptacles at 3 VA/sq ft; two 1,500 VA small-appliance circuits; one 1,500 VA laundry circuit; one 12 kW range; one 5,000 VA dryer; dishwasher 1,200 VA, disposer 900 VA, water heater 4,500 VA and trash compactor 600 VA (all fastened in place); and a 4,800 VA air conditioner. What is the calculated load?

    Answer: 29,245 VA

    General load: 2,400 x 3 = 7,200 + 3,000 (two small-appliance circuits) + 1,500 (laundry) = 11,700 VA. Table 220.45 (dwelling units): first 3,000 at 100% + 8,700 x 35% = 3,045, giving 6,045 VA. Four fastened-in-place appliances (220.53): 1,200 + 900 + 4,500 + 600 = 7,200 x 75% = 5,400 VA. Range 12 kW = 8,000 VA (Table 220.55, Column C). Dryer 5,000 VA (220.54). A/C 4,800 VA. Total 6,045 + 5,400 + 8,000 + 5,000 + 4,800 = 29,245 VA. 33,880 wrongly uses the optional-method 10,000 VA/40% split on the general load, 31,045 skips the 75% factor, and 33,245 uses 12,000 VA for the range.

    Reference: NEC 2023 (NFPA 70), 220.41, 220.52, Table 220.45, 220.53, 220.54, Table 220.55

  8. A feeder supplies 120 amperes of continuous load and 60 amperes of noncontinuous load. The overcurrent device is not listed for 100 percent continuous operation, and the conductors are copper with 75 C terminations. What is the smallest THWN copper size, using Table 310.16 (3/0 = 200 A, 4/0 = 230 A, 250 kcmil = 255 A)?

    Answer: 4/0 AWG

    215.2(A)(1): feeder conductors need an ampacity of at least 125 percent of the continuous load plus 100 percent of the noncontinuous load: 120 x 1.25 = 150 + 60 = 210 A. 3/0 AWG at 200 A is too small; 4/0 AWG at 230 A is the smallest that meets 210 A. 250 kcmil would be oversized.

    Reference: NEC 2023 (NFPA 70), 215.2(A)(1) and Table 310.16

  9. A 15-hp, 460-volt, 3-phase continuous-duty motor has a Table 430.250 full-load current of 21 A. What is the minimum ampacity of the branch-circuit conductors?

    Answer: 26.25 A

    430.22 requires conductors to carry at least 125 percent of the motor full-load current from Table 430.250 (not the nameplate): 21 x 1.25 = 26.25 A. 21 A applies no multiplier, 31.5 A uses 150 percent, and 52.5 A uses the 250 percent protective-device factor.

    Reference: NEC 2023 (NFPA 70), 430.22 and Table 430.250

  10. A permanently installed swimming pool is being built at a dwelling. What is the required location of the required 125-volt, 15- or 20-ampere general-purpose receptacle?

    Answer: At least 6 ft and not more than 20 ft from the inside wall of the pool

    680.22(A)(1) requires at least one 125-volt, 15- or 20-ampere general-purpose receptacle not less than 6 ft and not more than 20 ft from the inside wall of the pool, and not more than 6 ft 6 in. above the floor, platform or grade serving the pool.

    Reference: NEC 2023 (NFPA 70), 680.22(A)(1)

Sources