The Contract Administration exam for Florida certified residential contractors: 45 questions on preconstruction, contracts, permits and construction procedures. Open book, 70% to pass.

Questions
45
Time limit
4.5 hours
Passing score
70%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10Preconstruction

A residential contractor's total estimated cost for a new home is $184,000. The company adds a 12% markup on cost. What is the bid price?

Requirements at a glance

AgencyFlorida DBPR, Construction Industry Licensing Board (CILB); Professional Testing, Inc. registers and Pearson VUE delivers the exams
ExperienceAbout 4 years as a skilled worker or foreman (1 year as foreman); college credit may substitute. Confirm current requirements with DBPR.
ExamsBusiness and Finance, Contract Administration (45 questions, 4.5 hours, 70%) and Project Management
Books allowedContractors Manual, AIA A201/A401/A701, Principles and Practices of Commercial Construction 11th Edition, 2023 Florida Building Code volumes and 29 CFR 1926
Fees$135 to Professional Testing, Inc., plus a Pearson VUE administration fee per exam ($40 to $80); after you pass, a $40 DBPR application fee and the initial license fee ($200, or $100 in the second year of the cycle). Rule 61G4-12.009

Candidates for CILB certification as a residential contractor (one-, two- or three-family residences), in addition to Business and Finance and Project Management.

How to get licensed, step by step

  1. Check the license type

    Only certified (statewide) contractors take these exams. Registered contractors are licensed by local jurisdictions.

    Florida DBPR: construction examinations (CILB) (opens in a new tab)Florida Statutes Chapter 489 (contracting) (opens in a new tab)

  2. Apply to the CILB

    Submit the application with proof of experience, a credit report or financial-responsibility course, and a background check. Insurance is required for the license.

    Florida DBPR: construction examinations (CILB) (opens in a new tab)

  3. Register and schedule

    Register with Professional Testing, Inc., then schedule your exam with Pearson VUE. Passing is 70%, and you can review missed items within 21 days. A retake needs a new application.

    Professional Testing, Inc. (register for CILB exams) (opens in a new tab)Pearson VUE: Florida construction exams (opens in a new tab)

How to prepare

  • The exams are open book, but only the approved, bound references on the January 2026 to December 2026 list are allowed. Underline or highlight, but no handwritten notes and no loose tabs.
  • Florida's reference lists change each January. The 2023 Florida Building Code (8th edition) is on the 2026 lists; the 9th edition takes effect December 31, 2026 and several 2027 lists move to 2026 editions.
  • Project contracts (40%) and preconstruction (29%) are over two thirds of the exam. Tab the AIA A201, A401 and A701 documents.
  • A residential contractor builds one-, two- or three-family residences (Section 489.105(3)(c)); expect residential examples.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the Contractors Manual and the Florida Building Code. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

  • Contractors Manual, Association of Builders and Contractors Institute (ABC)Essential

    On the Business and Finance, general contractor and electrical business reference lists. The 2025 edition is used from February 1, 2026.

  • Florida Building Code, 8th Edition (2023): Building, Residential, Plumbing, Mechanical, Fuel Gas, Energy Conservation, AccessibilityEssential

    Approved references on the 2026 lists; the volumes vary by exam. The 9th edition takes effect December 31, 2026.

    ICC store (opens in a new tab)Read free (Florida Building Code online) (opens in a new tab)

  • 29 CFR 1926 (OSHA Construction Standards), sections on your reference list

    Trenching, scaffolds, fall protection and ladders. Print just the listed sections.

    Read free (eCFR) (opens in a new tab)

Official reference list (as published by the testing agency)
  • Contractors Manual, Association of Builders and Contractors Institute
  • AIA A201 (2017), A401 (2017) and A701 (2018)
  • Principles and Practices of Commercial Construction, 11th Edition
  • Florida Building Code 2023 (8th edition): Building, Residential, Existing Building, Accessibility and Energy Conservation
  • 29 CFR Part 1926 (OSHA construction)

What's on the exam

Official content outline from Professional Testing, Inc. and Pearson VUE (number of questions per topic):

TopicQuestions
Preconstruction29
Project Contracts40
Licenses, Permits, Approvals20
Construction Procedures11

The outline totals 100; the other items on the 45-question exam are unscored or unassigned.

Exam day details

  • Administered by Professional Testing, Inc. and Pearson VUE for the Florida Construction Industry Licensing Board (CILB).
  • Fee: $135 to Professional Testing, Inc. when you register, plus $40 to Pearson VUE when you schedule this exam ($40 more for Project Management). A retake costs both again. After you pass, DBPR charges a $40 application fee and the initial license fee ($200, or $100 in the second year of the two-year cycle).
  • 45 questions in 4.5 hours; 70% to pass.
  • Residential contractors take Business and Finance, Contract Administration and Project Management. Each passed part is valid for four years.
  • Under Section 489.105(3)(c), a residential contractor may build one-, two- or three-family residences and accessory structures not over two habitable stories above one uninhabitable story.
  • The 2026 reference lists use the 2023 Florida Building Code (8th edition). The 9th edition (2026, based on the 2024 I-codes) takes effect December 31, 2026, and the 2027 lists move several books to 2026 editions, so check the current list for your test date.
  • Open book with approved references only. They must be bound and stay bound; underlining and highlighting are allowed, handwritten notes and loose tabs are not. The reference lists change each January.
  • Questions are equally weighted and a score of 70% is required to pass (not rounded). The printed topic percentages are approximate, plus or minus 3 points. Pretest items are not scored.
  • If you fail you may review the items you missed within 21 days. A retake needs a new application.
  • Certified contractors are licensed statewide. Registered contractors are licensed locally and do not take these exams.
  • Fees are set by Board rule (61G4-12.009) and DBPR's test-administration fee table; confirm the current amounts with Professional Testing, Inc. and DBPR before you apply.

Frequently asked questions

What is on the Florida residential contractor Contract Administration exam?

Project contracts 40%, preconstruction 29%, licenses, permits and approvals 20% and construction procedures 11%.

What work does a Florida residential contractor license cover?

One-, two- or three-family residences not over two habitable stories above one uninhabitable story, and accessory structures, under Section 489.105(3)(c).

Free questions with answers

Show all 10 free questions and answers
  1. A residential contractor's total estimated cost for a new home is $184,000. The company adds a 12% markup on cost. What is the bid price?

    Answer: $206,080

    Markup is applied to cost: $184,000 x 0.12 = $22,080, and $184,000 + $22,080 = $206,080. Dividing cost by 0.88 ($209,091) treats 12% as a margin on the selling price. Quoting only $22,080 leaves out the cost itself.

    Reference: General construction estimating practice, Markup on cost: bid price calculation

  2. A homebuilding contract calls for liquidated damages of $350 per calendar day. Substantial completion was due August 12, and the home reached substantial completion on September 3 of the same year. What is the total assessed?

    Answer: $7,700

    August 12 to September 3 is 19 days left in August plus 3 days in September = 22 days. 22 x $350 = $7,700. Counting 21 or 23 days is an off-by-one slip.

    Reference: General construction estimating practice, Liquidated damages calculation

  3. Two days before bids are due, the designer issues Addendum No. 3 to a residential bid set; it changes the specified exterior cladding. What should a bidder do?

    Answer: Price the revised cladding and acknowledge the addendum with the bid

    Addenda become part of the bidding documents and the contract. A bidder must price them and normally acknowledge them on the bid form; ignoring one risks a nonresponsive bid or an underpriced job.

    Reference: General construction estimating practice, Obtaining and evaluating bids: addenda

  4. A cost-plus contract with a fixed fee pays reimbursable costs plus a $22,000 fee. The contractor estimated costs at $190,000, but the job finishes at $212,400 with no change in scope. What is the total owed to the contractor?

    Answer: $234,400

    Reimbursable costs are paid as incurred and the fixed fee does not move: $212,400 + $22,000 = $234,400. The estimate-based total ($212,000) is what the owner expected, not what is owed; scaling the fee with cost ($236,994) treats it as a percentage fee.

    Reference: General construction management practice, Types of contracts: cost-plus with a fixed fee

  5. A custom-home contract carries a guaranteed maximum price of $640,000. The final cost of the work is $598,000, and savings below the GMP are shared 60% to the owner and 40% to the builder. What is the builder's share?

    Answer: $16,800

    Savings = $640,000 - $598,000 = $42,000. Contractor's 40% share = $42,000 x 0.40 = $16,800. The owner receives 60% ($25,200); $42,000 is the whole savings; 40% of the actual cost is not a savings share.

    Reference: General construction management practice, Types of contracts: guaranteed maximum price

  6. A general contractor wants a standard subcontract form that can incorporate the A201 general conditions by reference. Which AIA document is the standard agreement between contractor and subcontractor?

    Answer: AIA A401

    AIA A401 is the Standard Form of Agreement Between Contractor and Subcontractor. A201 is the General Conditions, A701 is Instructions to Bidders, and G702 is the Application and Certificate for Payment.

    Reference: AIA A401-2017 Standard Form of Agreement Between Contractor and Subcontractor, Document title and scope

  7. Under FBC Building s. 105.4.1, a permit becomes invalid if the authorized work is not commenced within what period after issuance?

    Answer: 6 months

    Section 105.4.1 provides that a permit becomes invalid unless the work is commenced within 6 months after issuance, or if work is suspended or abandoned for 6 months after it has commenced.

    Reference: Florida Building Code, Building, 8th Edition (2023), s. 105.4.1

  8. A homeowner applies for a permit for a new 2,400 sq ft single-family house, using the local government's plans reviewer. Under FBC Building s. 105.3.4.1, within how many business days must the local government approve, approve with conditions, or deny a complete and sufficient application, unless the applicant waives the time in writing?

    Answer: 30 business days

    Section 105.3.4.1: for a single-family residential dwelling (and other listed permits) under 7,500 sq ft, the period is 30 business days after receipt of a complete and sufficient application; 60 business days applies at 7,500 sq ft or more.

    Reference: Florida Building Code, Building, 8th Edition (2023), s. 105.3.4.1

  9. A remodel schedule has five activities: A (3 days, first); B (5 days, follows A); C (4 days, follows A); D (6 days, follows B); E (2 days, follows both C and D). How much total float does activity C have?

    Answer: 7 days

    Path A-B-D-E = 3 + 5 + 6 + 2 = 16 days (critical). Path A-C-E = 3 + 4 + 2 = 9 days. Float of C = 16 - 9 = 7 days. C is not on the critical path, so 0 is wrong.

    Reference: General construction management practice, Critical Path Method: float calculation

  10. The framing is complete on a house and the plumber, electrician and HVAC subcontractor are finished with rough-in. The contractor wants to start insulation and drywall tomorrow. Under FBC Building ss. 110.3, 110.5 and 110.6, what must happen first?

    Answer: The permit holder requests inspections and gets approval first

    Section 110.5 makes the permit holder responsible for notifying the building official when work is ready, and s. 110.6 says work may not proceed beyond a required inspection point without the building official's approval. Concealing rough-in work before approval invites tear-out and a violation.

    Reference: Florida Building Code, Building, 8th Edition (2023), ss. 110.5, 110.6