The Contract Administration exam for Florida certified building contractors: 50 questions on preconstruction, contracts, permits and construction procedures. Open book, 70% to pass.

Questions
50
Time limit
4.5 hours
Passing score
70%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10Preconstruction

A contractor prices a commercial tenant improvement with a direct cost of $215,000 and adds an 18% markup on cost. What is the bid price?

Requirements at a glance

AgencyFlorida DBPR, Construction Industry Licensing Board (CILB); Professional Testing, Inc. registers and Pearson VUE delivers the exams
ExperienceAbout 4 years as a skilled worker or foreman (1 year as foreman); college credit may substitute. Confirm current requirements with DBPR.
ExamsBusiness and Finance, Contract Administration (50 questions, 4.5 hours, 70%) and Project Management
Books allowedContractors Manual, AIA A201/A401/A701, Principles and Practices of Commercial Construction 11th Edition, 2023 Florida Building Code volumes and 29 CFR 1926
Fees$135 to Professional Testing, Inc., plus a Pearson VUE administration fee per exam ($40 to $80); after you pass, a $40 DBPR application fee and the initial license fee ($200, or $100 in the second year of the cycle). Rule 61G4-12.009

Candidates for CILB certification as a building contractor (commercial buildings and residential buildings not over three stories), in addition to Business and Finance and Project Management.

How to get licensed, step by step

  1. Check the license type

    Only certified (statewide) contractors take these exams. Registered contractors are licensed by local jurisdictions.

    Florida DBPR: construction examinations (CILB) (opens in a new tab)Florida Statutes Chapter 489 (contracting) (opens in a new tab)

  2. Apply to the CILB

    Submit the application with proof of experience, a credit report or financial-responsibility course, and a background check. Insurance is required for the license.

    Florida DBPR: construction examinations (CILB) (opens in a new tab)

  3. Register and schedule

    Register with Professional Testing, Inc., then schedule your exam with Pearson VUE. Passing is 70%, and you can review missed items within 21 days. A retake needs a new application.

    Professional Testing, Inc. (register for CILB exams) (opens in a new tab)Pearson VUE: Florida construction exams (opens in a new tab)

How to prepare

  • The exams are open book, but only the approved, bound references on the January 2026 to December 2026 list are allowed. Underline or highlight, but no handwritten notes and no loose tabs.
  • Florida's reference lists change each January. The 2023 Florida Building Code (8th edition) is on the 2026 lists; the 9th edition takes effect December 31, 2026 and several 2027 lists move to 2026 editions.
  • Project contracts (38%) and preconstruction (28%) are two thirds of the exam. Tab the AIA A201, A401 and A701 documents.
  • A building contractor builds commercial buildings and residential buildings not over three stories (Section 489.105(3)(b)); keep that scope in mind for permit and procedure questions.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the Contractors Manual and the Florida Building Code. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

  • Contractors Manual, Association of Builders and Contractors Institute (ABC)Essential

    On the Business and Finance, general contractor and electrical business reference lists. The 2025 edition is used from February 1, 2026.

  • Florida Building Code, 8th Edition (2023): Building, Residential, Plumbing, Mechanical, Fuel Gas, Energy Conservation, AccessibilityEssential

    Approved references on the 2026 lists; the volumes vary by exam. The 9th edition takes effect December 31, 2026.

    ICC store (opens in a new tab)Read free (Florida Building Code online) (opens in a new tab)

  • 29 CFR 1926 (OSHA Construction Standards), sections on your reference list

    Trenching, scaffolds, fall protection and ladders. Print just the listed sections.

    Read free (eCFR) (opens in a new tab)

Official reference list (as published by the testing agency)
  • Contractors Manual, Association of Builders and Contractors Institute
  • AIA A201 (2017), A401 (2017) and A701 (2018)
  • Principles and Practices of Commercial Construction, 11th Edition
  • Florida Building Code 2023 (8th edition): Building, Residential, Existing Building, Accessibility and Energy Conservation
  • 29 CFR Part 1926 (OSHA construction)

What's on the exam

Official content outline from Professional Testing, Inc. and Pearson VUE (number of questions per topic):

TopicQuestions
Preconstruction28
Project Contracts38
Licenses, Permits, Approvals20
Construction Procedures14

The outline totals 100; the other items on the 50-question exam are unscored or unassigned.

Exam day details

  • Administered by Professional Testing, Inc. and Pearson VUE for the Florida Construction Industry Licensing Board (CILB).
  • Fee: $135 to Professional Testing, Inc. when you register, plus $40 to Pearson VUE when you schedule this exam ($40 more for Project Management). A retake costs both again. After you pass, DBPR charges a $40 application fee and the initial license fee ($200, or $100 in the second year of the two-year cycle).
  • 50 questions in 4.5 hours; 70% to pass.
  • Building contractors take Business and Finance, Contract Administration and Project Management. Each passed part is valid for four years.
  • Under Section 489.105(3)(b), a building contractor may build commercial buildings and residential buildings of one or more dwelling units not over three stories, and may do non-structural remodeling of any size building.
  • The 2026 reference lists use the 2023 Florida Building Code (8th edition). The 9th edition (2026, based on the 2024 I-codes) takes effect December 31, 2026, and the 2027 lists move several books to 2026 editions, so check the current list for your test date.
  • Open book with approved references only. They must be bound and stay bound; underlining and highlighting are allowed, handwritten notes and loose tabs are not. The reference lists change each January.
  • Questions are equally weighted and a score of 70% is required to pass (not rounded). The printed topic percentages are approximate, plus or minus 3 points. Pretest items are not scored.
  • If you fail you may review the items you missed within 21 days. A retake needs a new application.
  • Certified contractors are licensed statewide. Registered contractors are licensed locally and do not take these exams.
  • Fees are set by Board rule (61G4-12.009) and DBPR's test-administration fee table; confirm the current amounts with Professional Testing, Inc. and DBPR before you apply.

Frequently asked questions

What is on the Florida building contractor Contract Administration exam?

Project contracts 38%, preconstruction 28%, licenses, permits and approvals 20% and construction procedures 14%.

What work does a Florida building contractor license cover?

Commercial buildings and residential buildings of one or more dwelling units not over three stories, plus non-structural remodeling of buildings of any size, under Section 489.105(3)(b).

Free questions with answers

Show all 10 free questions and answers
  1. A contractor prices a commercial tenant improvement with a direct cost of $215,000 and adds an 18% markup on cost. What is the bid price?

    Answer: $253,700

    Markup is applied to cost: $215,000 x 0.18 = $38,700, and $215,000 + $38,700 = $253,700. Dividing cost by 0.82 ($262,195) treats 18% as a margin on the selling price. $38,700 is only the markup, and $218,870 adds 1.8% instead of 18%.

    Reference: General construction estimating practice, Markup on cost: bid price calculation

  2. A contract provides liquidated damages of $1,200 per calendar day. Substantial completion was due June 10 and was reached July 3 of the same year. What is the total assessed?

    Answer: $27,600

    June 10 to July 3 is 20 days remaining in June plus 3 in July = 23 calendar days late. 23 x $1,200 = $27,600. Counting 24 days gives $28,800, counting 22 gives $26,400, and $8,400 charges only seven days.

    Reference: General construction estimating practice, Liquidated damages calculation

  3. A gable roof on a 30 ft wide building has a ridge rise of 8 ft above the top plate. What is the length of a common rafter, ignoring the overhang?

    Answer: 17 ft

    Each rafter covers half the span (run = 15 ft) and rises 8 ft. The rafter is the hypotenuse: sqrt(15^2 + 8^2) = sqrt(289) = 17 ft. Adding run and rise gives 23 ft, 15 ft is only the run, and 289 is the squared value before taking the root.

    Reference: General construction estimating practice, Reading plans: right-triangle calculation of rafter length

  4. A cost-plus contract with a fixed fee pays reimbursable costs plus a $77,000 fee. The contractor estimated cost at $1,100,000, but costs finish at $1,180,000 with no change in scope. What is the total owed to the contractor?

    Answer: $1,257,000

    With a fixed fee, the fee does not move when cost moves: $1,180,000 + $77,000 = $1,257,000. $1,177,000 adds the fee to the estimated cost, $1,180,000 leaves the fee out, and $1,262,600 treats the fee as 7% of actual cost.

    Reference: General construction management practice, Types of contracts: cost-plus with a fixed fee

  5. A cost-plus contract pays the contractor's reimbursable costs plus a fee of 8% of those costs. Reimbursable costs total $940,000. What is the total payment?

    Answer: $1,015,200

    Fee = 8% x $940,000 = $75,200. Total = $940,000 + $75,200 = $1,015,200. $75,200 is only the fee, $1,021,739 divides cost by 0.92, and $1,034,000 uses a 10% fee.

    Reference: General construction management practice, Types of contracts: cost-plus percentage of cost

  6. A guaranteed maximum price contract sets the GMP at $3,200,000. The cost of the work is $3,050,000, and the contract splits any savings 60% to the owner and 40% to the contractor. How much of the savings does the contractor receive?

    Answer: $60,000

    Savings = $3,200,000 - $3,050,000 = $150,000. The contractor's 40% share = $150,000 x 0.40 = $60,000. $90,000 is the owner's 60% share, $150,000 is the whole savings, and $75,000 assumes an even split.

    Reference: General construction management practice, Types of contracts: guaranteed maximum price

  7. A customer asks a certified building contractor to build a new three-story, 12-unit apartment building and a detached accessory storage building. Under s. 489.105(3)(b), is this within the license?

    Answer: Yes, it is a residential building of not more than three stories with accessory structures

    A building contractor may construct commercial buildings and single- or multiple-dwelling residential buildings that do not exceed three stories, with accessory use structures. A residential contractor is limited to one- to three-family residences of two habitable stories.

    Reference: Florida Statutes 2025, s. 489.105(3)(b)

  8. A certified building contractor is hired to renovate the interior of a 14-story office building by replacing finishes and relocating non-load-bearing partitions. Under s. 489.105(3)(b), is the work within the license?

    Answer: Yes, remodeling of any size building is allowed if the work does not affect structural members

    The building contractor definition has two parts: new construction of commercial or residential buildings up to three stories, and remodeling, repair or improvement of any size building if the services do not affect the structural members. The height limit does not apply to non-structural remodeling.

    Reference: Florida Statutes 2025, s. 489.105(3)(b)

  9. A building project has five activities. A (2 days) must finish before B (6 days) and C (3 days) can start. B and C must both finish before D (4 days) can start, and E (1 day) follows D. What are the project duration and the total float on C?

    Answer: 13 days; C has 3 days of float

    Path A-B-D-E = 2 + 6 + 4 + 1 = 13 days. Path A-C-D-E = 2 + 3 + 4 + 1 = 10 days. The longest path controls, so the duration is 13 days. C can slip 13 - 10 = 3 days without delaying completion. C is not on the critical path, so its float is not zero.

    Reference: General construction management practice, Critical Path Method: duration and float

  10. Activity A (5 days) has no predecessor. B (3 days) and C (6 days) both follow A. D (4 days) follows B. E (2 days) follows both C and D. Counting A as starting at time 0, what is the earliest time E can start?

    Answer: Day 12

    Forward pass: A finishes at 5. B finishes at 5 + 3 = 8, and D at 8 + 4 = 12. C finishes at 5 + 6 = 11. E needs both C (11) and D (12) finished, so it starts at the later value, day 12. Day 11 uses only C, and day 14 is the project finish.

    Reference: General construction management practice, Critical Path Method: forward pass

Sources

Questions last verified November 15, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.