Florida licensing exam

Florida Air Conditioning Contractor Class B Exam: Practice Test & Licensing Guide

The CILB trade knowledge exam for Class B air conditioning contractors: 80 questions on installation, ducts, maintenance, safety and energy. Open book, 70% to pass.

Questions
80
Time limit
5 hours
Passing score
70%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10Pre-Installation

A new house has a central return, and the designer plans to rely on through-the-wall transfer grilles (with 1-inch door undercuts) so that a bedroom does not become pressurized when its door is closed. The bedroom receives 150 cfm of supply air. Using the Florida balanced-return exception, what minimum transfer grille area is needed?

Requirements at a glance

AgencyFlorida DBPR, Construction Industry Licensing Board (CILB); Professional Testing, Inc. registers and Pearson VUE delivers the exams
ExperienceAbout 4 years as a skilled worker or foreman (1 year as foreman); college credit may substitute. Confirm current requirements with DBPR.
ExamsBusiness and Finance plus Air Conditioning Class B trade knowledge (80 questions, 5 hours, 70%)
Books allowedFlorida Building Code Mechanical and Energy Conservation 2023, NFPA 90A/90B/96, SMACNA duct standards, Refrigeration and Air Conditioning Technology 9th Edition and the Trane Ductulator
Fees$135 to Professional Testing, Inc., plus a Pearson VUE administration fee per exam ($40 to $80); after you pass, a $40 DBPR application fee and the initial license fee ($200, or $100 in the second year of the cycle). Rule 61G4-12.009

Candidates for CILB certification as a Class B air conditioning contractor (systems up to 25 tons of cooling and 500,000 Btu of heating), in addition to Business and Finance.

How to get licensed, step by step

  1. Check the license type

    Only certified (statewide) contractors take these exams. Registered contractors are licensed by local jurisdictions.

    Florida DBPR: construction examinations (CILB) (opens in a new tab)Florida Statutes Chapter 489 (contracting) (opens in a new tab)

  2. Apply to the CILB

    Submit the application with proof of experience, a credit report or financial-responsibility course, and a background check. Insurance is required for the license.

    Florida DBPR: construction examinations (CILB) (opens in a new tab)

  3. Register and schedule

    Register with Professional Testing, Inc., then schedule your exam with Pearson VUE. Passing is 70%, and you can review missed items within 21 days. A retake needs a new application.

    Professional Testing, Inc. (register for CILB exams) (opens in a new tab)Pearson VUE: Florida construction exams (opens in a new tab)

How to prepare

  • The exams are open book, but only the approved, bound references on the January 2026 to December 2026 list are allowed. Underline or highlight, but no handwritten notes and no loose tabs.
  • Florida's reference lists change each January. The 2023 Florida Building Code (8th edition) is on the 2026 lists; the 9th edition takes effect December 31, 2026 and several 2027 lists move to 2026 editions.
  • Installation of systems (22%) and equipment components (14%) are the biggest sections, then maintenance service (14%) and pre-installation (12%).
  • Class B covers the same areas as Class A with different weights, for systems up to 25 tons of cooling and 500,000 Btu of heating.
  • The 2027 lists move Mechanical and Energy to the 2026 Florida Building Code editions.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the Florida Building Code. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

Official reference list (as published by the testing agency)
  • Florida Building Code, Mechanical, 2023 (8th edition)
  • Florida Building Code, Energy Conservation, 2023 (8th edition)
  • NFPA 90A (2015), NFPA 90B (2024) and NFPA 96 (2021)
  • SMACNA Fibrous Glass Duct Construction Standards, 8th Edition; HVAC Duct Construction Standards, 4th Edition; Energy Systems Analysis and Management, 2nd Edition; and the Trane Ductulator
  • Refrigeration and Air Conditioning Technology, 9th Edition
  • Air Conditioning and Refrigeration Troubleshooting Handbook, 2nd Edition; Pipefitters Handbook, 3rd Edition; Energy Efficient Building Construction in Florida (2024); Contractors Manual (2025); 29 CFR Part 1926

What's on the exam

Official content outline from Professional Testing, Inc. and Pearson VUE (number of questions per topic):

TopicQuestions
Pre-Installation12
Sheet Metal Ducts9
Installation of Refrigeration and HVAC Systems22
Installation of Refrigeration and HVAC Equipment Components14
Maintenance Analysis10
Maintenance Service14
Safety and Equipment10
Energy Management5
Indoor Air Quality4

The outline totals 100; the other items on the 80-question exam are unscored or unassigned.

Exam day details

  • Administered by Professional Testing, Inc. and Pearson VUE for the Florida Construction Industry Licensing Board (CILB).
  • Fee: $135 to Professional Testing, Inc. when you register, plus $80 to Pearson VUE when you schedule this exam. A retake costs both again. After you pass, DBPR charges a $40 application fee and the initial license fee ($200, or $100 in the second year of the two-year cycle).
  • 80 questions in 5 hours; 70% to pass.
  • Installation of systems and equipment components are 36% of the exam.
  • Class B covers the same content areas as Class A with different weights. A Class B system is limited to 25 tons of cooling and 500,000 Btu of heating per system.
  • The 2026 reference lists use the 2023 Florida Building Code (8th edition). The 9th edition (2026, based on the 2024 I-codes) takes effect December 31, 2026, and the 2027 lists move several books to 2026 editions, so check the current list for your test date.
  • Open book with approved references only. They must be bound and stay bound; underlining and highlighting are allowed, handwritten notes and loose tabs are not. The reference lists change each January.
  • Questions are equally weighted and a score of 70% is required to pass (not rounded). The printed topic percentages are approximate, plus or minus 3 points. Pretest items are not scored.
  • If you fail you may review the items you missed within 21 days. A retake needs a new application.
  • Certified contractors are licensed statewide. Registered contractors are licensed locally and do not take these exams.
  • Fees are set by Board rule (61G4-12.009) and DBPR's test-administration fee table; confirm the current amounts with Professional Testing, Inc. and DBPR before you apply.

Frequently asked questions

What is on the Florida Class B air conditioning exam?

Installation of refrigeration and HVAC systems 22%, pre-installation 12%, equipment components 14%, maintenance service 14%, maintenance analysis 10%, safety and equipment 10%, sheet metal ducts 9%, energy management 5% and indoor air quality 4%.

How is Class B different from Class A?

Class B is a separate CILB exam with 80 questions instead of 130 and slightly different topic weights. It leads to certification for systems up to 25 tons of cooling and 500,000 Btu of heating per system.

Free questions with answers

Show all 10 free questions and answers
  1. A new house has a central return, and the designer plans to rely on through-the-wall transfer grilles (with 1-inch door undercuts) so that a bedroom does not become pressurized when its door is closed. The bedroom receives 150 cfm of supply air. Using the Florida balanced-return exception, what minimum transfer grille area is needed?

    Answer: 75 square inches

    Section 601.6 (Florida text) allows through-the-wall transfer grilles sized at 50 square inches of grille area per 100 cfm of supply air, along with an unrestricted 1-inch door undercut. 150 cfm / 100 x 50 = 75 square inches. 150 square inches treats it as 1 square inch per cfm; 50 forgets to scale for the airflow; 300 doubles the rate.

    Reference: 2023 Florida Building Code, Mechanical (8th edition), Section 601.6 (Balanced Return Air)

  2. Using the minimum sheet metal thickness table for ducts in single dwelling units, what is the minimum aluminum thickness for a 13-inch round duct operating at 1-inch water gage?

    Answer: 0.023 inch

    In Table 603.4 the round row for 12 to 14 inches at 1-inch water gage shows 0.016 inch galvanized and 0.023 inch aluminum. The 0.016 value is the galvanized entry in the same box, 0.018 is the aluminum value at 1/2 inch for the same row, and 0.019 is a different row altogether.

    Reference: 2023 Florida Building Code, Mechanical (8th edition), Table 603.4

  3. Refrigerant piping must cross an open corridor that people use as a passageway in a commercial building, and it is not run against the ceiling. What minimum height above the floor does the mechanical code require?

    Answer: 7 feet 3 inches

    Section 1107.2 requires refrigerant piping that crosses an open space affording passageway to be at least 7 feet 3 inches above the floor unless it is located against the ceiling of that space. Piping also may not be placed in elevator shafts or in enclosed stairways. (Section 1109.2.1 in the 9th ed., which keeps 7 feet 3 inches but drops the against-the-ceiling wording.)

    Reference: 2023 Florida Building Code, Mechanical (8th edition), Section 1107.2

  4. A technician pressure tests the field-erected refrigerant piping of a new 15-ton split system. Which test medium does the mechanical code permit?

    Answer: Dry nitrogen or carbon dioxide

    Section 1108.2 requires an inert dried gas such as nitrogen or carbon dioxide for the pressure test. Oxygen, air, combustible gases and mixtures containing them are not permitted, with a narrow exception allowing air for ammonia systems that are evacuated before charging. (Section 1110.3 in the 9th ed., which still lists nitrogen but limits carbon dioxide to R-744 systems.)

    Reference: 2023 Florida Building Code, Mechanical (8th edition), Section 1108.2

  5. Using Table 305.4, what is the maximum horizontal support spacing for 3/4-inch CPVC condensate piping?

    Answer: 3 feet

    Table 305.4 lists CPVC pipe or tubing 1 inch and smaller at 3 feet horizontal and 10 feet vertical, while CPVC 1 1/4 inches and larger is 4 feet horizontal. PVC pipe is 4 feet, and the 32-inch spacing belongs to PEX and similar tubing.

    Reference: 2023 Florida Building Code, Mechanical (8th edition), Table 305.4

  6. A coil moves 1,400 cfm of air with a 19 degree F temperature drop. Using the sensible heat equation, what sensible cooling capacity is the coil delivering?

    Answer: About 28,700 Btu/h

    Q = 1.08 x cfm x delta-T = 1.08 x 1,400 x 19 = 28,728 Btu/h. The 26,600 value leaves out the 1.08 factor, 119,700 uses the 4.5 total heat factor with a temperature difference, and 1,512 multiplies 1.08 by cfm only.

    Reference: Standard HVAC/R service calculation, Q (sensible) = 1.08 x cfm x delta-T

  7. A technician opens a sealed split system to replace a failed thermostatic expansion valve (TXV). Which additional component is it standard practice to replace whenever the sealed system is opened?

    Answer: The liquid line filter-drier

    Opening a sealed system lets in moisture and air, and the filter-drier is the component that holds moisture and debris. It is replaced whenever the sealed system is opened. The other parts are not affected by opening the circuit.

    Reference: Standard HVAC/R service practice, Filter-drier replacement after opening a sealed system

  8. A technician is working on a rooftop unit near an unprotected roof edge on a construction site. At what height above a lower level does the fall protection standard require guardrails, safety nets or personal fall arrest for an unprotected edge?

    Answer: 6 feet or more

    29 CFR 1926.501(b)(1) requires protection for each employee on a walking or working surface with an unprotected side or edge that is 6 feet or more above a lower level, using a guardrail, safety net or personal fall arrest system.

    Reference: 29 CFR Part 1926 (July 1, 2025), 1926.501(b)(1)

  9. A rough-in duct leakage test is done on a house with 2,400 square feet of conditioned floor area, at 25 pascals, before the air handler is installed. Using the prescriptive limit, what is the maximum allowed total duct leakage?

    Answer: 72 cfm

    Section R403.3.4: for a rough-in test where the air handler is not yet installed, total leakage must be no more than 3 cfm per 100 square feet of conditioned floor area. 2,400 / 100 x 3 = 72 cfm. With the air handler installed the limit is 4 cfm per 100 square feet, which would give 96 cfm, and 24 uses 1 cfm per 100 square feet.

    Reference: 2023 Florida Building Code, Energy Conservation (8th edition), Sections R403.3.3 and R403.3.4

  10. Under the dwelling-unit local exhaust table, what minimum rates apply to a bathroom with a continuously operating fan and to a kitchen with a continuously operating fan?

    Answer: Bathroom 20 cfm and kitchen 25 cfm

    Table 403.3.2.3 gives bathrooms and toilet rooms 50 cfm intermittent or 20 cfm continuous, and kitchens 100 cfm intermittent or 25 cfm continuous, for Group R-2, R-3 and R-4 occupancies. The larger numbers apply when the fans run intermittently. (The 9th ed. (2026) raises the continuous rates to 25 cfm for bathrooms and 50 cfm for kitchens; the intermittent rates of 50 and 100 cfm are unchanged.)

    Reference: 2023 Florida Building Code, Mechanical (8th edition), Table 403.3.2.3

Sources

Questions last verified November 15, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.