District of Columbia licensing exam

District of Columbia Master Plumber Exam: Practice Test & Licensing Guide

The PSI exam for the District of Columbia master plumber license: 100 multiple-choice questions on the 2012 IPC covering drainage, venting, water distribution and plan analysis. Open book, 4 hours.

Questions
100
Time limit
4 hours
Passing score
Not published by District of Columbia

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10Traps, Cleanouts, and Interceptors

Which of the following traps is specifically prohibited by Section 1002.3 of the 2012 IPC?

Requirements at a glance

AgencyD.C. Board of Industrial Trades, Department of Licensing and Consumer Protection (DLCP); exam by PSI
Exam100 multiple-choice questions, 4 hours (exam ID 303); Pass score not published; PSI reports PASS or FAIL
Experience8 years (16,000 work hours) (DLCP chart)
BooksOpen book: bound references only, permanent tabs, notes in ink or highlighting in code sections only; no writing during the exam
Fees$52 to PSI per exam; D.C. application and license fees are separate

Plumbers applying to the Board of Industrial Trades for a D.C. master plumber license (plumbing only, no gas). The DLCP chart lists 8 years (16,000 work hours) of experience.

How to get licensed, step by step

  1. Meet the experience requirement

    The DLCP chart lists 8 years (16,000 work hours) of experience, with tax records and an employment verification letter signed off by the master.

    D.C. Board of Industrial Trades (DLCP) (opens in a new tab)

  2. Apply to the District

    Submit the online application and fees to the Board of Industrial Trades. Approved candidates receive a notice of eligibility.

    D.C. online license application (opens in a new tab)

  3. Register with PSI

    Register by phone at (855) 557-0616 or online, giving the exam ID and title. Pay the $52 exam fee by credit or debit card when you book.

    Register with PSI: plumber exams (opens in a new tab)PSI: Washington D.C. Candidate Information Bulletin (8/25/2022) (opens in a new tab)

  4. Take the exam

    Bring your listed references and matching ID. You see PASS or FAIL right after the exam. To retest you must reapply with the District first.

    PSI: Washington D.C. Candidate Information Bulletin (8/25/2022) (opens in a new tab)

How to prepare

  • Plan and analysis is 23% of the exam, then drainage (19%) and vent (17%); practice sizing from the IPC tables.
  • The PSI bulletin (8/25/2022) lists older editions than the District's adopted 2017 DC Construction Codes (2014 NEC, 2015 ICC codes). Confirm the current reference list with PSI (855-557-0616) or the DLCP before you buy books.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the 2012 IPC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

  • 2012 International Plumbing Code (IPC), ICCEssential

    The edition on the PSI bulletin (8/25/2022). Confirm the current list with PSI or the DLCP.

    ICC (opens in a new tab)

Official reference list (as published by the testing agency)
  • 2012 International Plumbing Code (IPC)

What's on the exam

Official content outline from PSI Services (number of questions per topic):

TopicQuestions
Plumbing Fixtures and Terminology7
Plumbing Fundamentals13
Traps, Cleanouts, and Interceptors7
Special Requirements3
Drainage Requirements19
Vent Requirements17
Water Distribution11
Plan and Analysis23

Exam day details

  • Administered by PSI Services for the District of Columbia Board of Industrial Trades (DLCP).
  • Fee: $52 to PSI per computer-based exam. D.C. application and license fees are separate.
  • PSI exam ID 303: 100 multiple-choice questions, open book, 4 hours. The content outline is the PSI bulletin's.
  • The bulletin's plumbing references are the 2012 IPC (and the 2012 IFGC for the gas exams); the District's adopted construction codes are newer (2015 ICC codes). Confirm the current list with PSI or the DLCP.
  • The DLCP plumbing and gasfitting instructions say licenses expire March 31 of even-numbered years.
  • You apply to the Board online and pay the application fees first. Approved candidates get a notice of eligibility, then register with PSI at (855) 557-0616 or on PSI's D.C. pages using the exam ID and title.
  • Open book: bring only the references the bulletin lists. They must be bound (original, three-ring binder or stapled); photocopies of copyrighted material are not allowed. Notes in ink or highlighting are allowed in code sections only, and tabs must be permanently attached.
  • You may not write or mark in your references during the exam. PSI gives you a whiteboard, markers and scratch paper. Bring a battery-operated, non-programmable calculator without a printer.
  • Your name on the reservation must match your ID or you cannot test and forfeit the fee. Restroom breaks are limited to 5 minutes and the clock keeps running.
  • You see your result right after the exam. Passing candidates are told PASS with no numeric score; candidates who fail get diagnostic feedback by content area.
  • To retest you must reapply with the District before each attempt. The bulletin recommends allowing time to study before registering again.

Note: The PSI bulletin (updated 8/25/2022) lists the 2011 NEC and the 2012 IPC, IFGC and IMC, while the District's adopted construction codes are the 2017 DC Construction Codes (2014 NEC and 2015 ICC codes with D.C. amendments, effective May 29, 2020). We follow the editions on the bulletin. Confirm the current reference list with PSI (855-557-0616) or the DLCP before you buy books. No pass score is published.

Frequently asked questions

How many questions are on the D.C. master plumber exam?

PSI lists 100 multiple-choice questions in 4 hours (exam ID 303), open book. The biggest areas are Plan and Analysis (23%), Drainage Requirements (19%), Vent Requirements (17%).

What is the passing score?

Neither PSI nor the Board of Industrial Trades publishes a passing score. PSI shows PASS or FAIL right after the exam, with no numeric score for passing candidates and diagnostic feedback for those who fail.

Which code edition does the exam use?

PSI's bulletin lists the 2012 International Plumbing Code (and the 2012 IFGC for gas). The District has since adopted the 2015 ICC codes in the 2017 DC Construction Codes, so confirm the current reference list with PSI or the DLCP before you buy books.

Free questions with answers

Show all 10 free questions and answers
  1. Which of the following traps is specifically prohibited by Section 1002.3 of the 2012 IPC?

    Answer: A drum trap serving a lavatory

    Section 1002.3 prohibits bell traps, crown-vented traps, S traps, drum traps (except as solids interceptors or on chemical waste systems), traps relying on moving parts, and traps depending on interior partitions. Slip joints are allowed on the trap inlet, outlet and within the seal under 1002.2.

    Reference: 2012 International Plumbing Code, 1002.3

  2. What is the required height range of a standpipe above its trap weir under the 2012 IPC?

    Answer: Not less than 18 inches and not more than 42 inches

    Section 802.4 says standpipes are individually trapped and extend at least 18 inches but not more than 42 inches above the trap weir, with access for rodding.

    Reference: 2012 International Plumbing Code, 802.4

  3. A horizontal fixture branch carries 18 drainage fixture units and is sized from Table 710.1(2). What is the smallest individual or branch vent allowed for it under Section 906.2?

    Answer: 1 1/2 inches

    The 3-inch branch is the smallest horizontal branch in Table 710.1(2) that carries 18 dfu (limit 20). Section 906.2 requires a vent at least one-half the required drain size: 3 / 2 = 1.5 inches, which is also above the 1 1/4-inch minimum. A 1 1/4-inch vent would be less than half the drain.

    Reference: 2012 International Plumbing Code, 906.2; Table 710.1(2)

  4. A 3-inch horizontal sanitary drain is 40 feet long and installed at the minimum slope allowed by Table 704.1. What total drop does the pipe need from one end to the other?

    Answer: 5 inches

    Table 704.1 requires 1/4 inch per foot for pipes 2 1/2 inches and smaller, 1/8 inch per foot for 3 to 6 inches, and 1/16 inch per foot for 8 inches and larger. For a 3-inch pipe: 40 ft x 1/8 in/ft = 5 inches. Using 1/4 inch per foot gives 10 inches, and 1/16 gives 2 1/2 inches.

    Reference: 2012 International Plumbing Code, Table 704.1

  5. What is the minimum size of a building drain that serves a water closet, according to the footnote to Table 710.1(1)?

    Answer: 3 inches

    The footnote to Table 710.1(1) states that the minimum size of any building drain serving a water closet is 3 inches, even where the dfu load would fit a smaller pipe.

    Reference: 2012 International Plumbing Code, Table 710.1(1), note a

  6. What is the minimum distance from the center of a water closet to a side wall under Section 405.3.1?

    Answer: 15 inches

    Section 405.3.1 requires 15 inches from the fixture centerline to any side wall, partition or obstruction, 30 inches center to center between adjacent fixtures, and 21 inches clear in front. The 21-inch value is the front clearance, not the side distance.

    Reference: 2012 International Plumbing Code, 405.3.1

  7. What are the maximum temperature and pressure settings allowed for a temperature and pressure relief valve on a storage water heater under Section 504.5?

    Answer: 210 degrees F, and the lesser of the tank's rated working pressure or 150 psi

    Section 504.5 sets a temperature setting of not more than 210 degrees F and a pressure setting not exceeding the tank's rated working pressure or 150 psi, whichever is less. The valve's relieving capacity must equal or exceed the heat input.

    Reference: 2012 International Plumbing Code, 504.5

  8. Under Section 606.1, which location must have a full-open valve?

    Answer: The water supply pipe to every water heater

    Section 606.1 lists full-open valves at the curb service, the entrance to the structure, the discharge side of every meter, riser bases and down-feed tops in certain occupancies, dwelling unit entrances, tank supplies, and the water supply to every water heater. Fixture stops are shutoff valves under 606.2.

    Reference: 2012 International Plumbing Code, 606.1

  9. A 4-inch building sewer is 60 feet long and is laid at the minimum slope allowed in Table 704.1. How much total fall does the run need?

    Answer: 7 1/2 inches

    A 4-inch pipe is in the 3 to 6 inch row requiring 1/8 inch per foot: 60 ft x 1/8 = 7.5 inches. Using 1/4 inch per foot gives 15 inches, and 1/16 gives 3 3/4 inches.

    Reference: 2012 International Plumbing Code, Table 704.1

  10. A restaurant kitchen's fixtures drain through a total flow-through rating of 35 gpm to a hydromechanical grease interceptor. What grease retention capacity does Table 1003.3.4.1 call for?

    Answer: 70 pounds

    Table 1003.3.4.1 lists 35 gpm at 70 pounds retention (25 gpm = 50 pounds; 50 gpm = 100 pounds). Capacity in pounds is twice the rating in gpm here.

    Reference: 2012 International Plumbing Code, Table 1003.3.4.1

Sources

Questions last verified November 17, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.