Delaware licensing exam

Delaware Master Electrician Exam: Practice Test & Licensing Guide

The Prov exam for Delaware's master electrician license: 80 questions on the NEC, led by general electrical knowledge, wiring and protection, and wiring methods and materials. Open book.

Questions
80
Time limit
3 hours
Passing score
75%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10General Electrical Knowledge

A balanced three-phase, 480-volt resistive heating load is rated 36 kW. What is the approximate line current?

Requirements at a glance

AgencyDelaware Division of Professional Regulation, Board of Electrical Examiners; exams by Prov
Experience6 years of full-time experience under a master electrician; or 8,000 hours plus 576 hours of related instruction or a registered apprenticeship; or 4 years plus 2 years of technical training (24 Del.C. 1408(a)(1))
ExamMaster electrician exam: 80 questions, 3 hours, 75%
Books allowedNEC (edition per the Prov bulletin) and American Electrician's Handbook, 17th Edition
Fees$100 to Prov per exam (2022 bulletin); DPR application and license fees are separate

Electricians applying to the Delaware Board of Electrical Examiners for a master electrician license, which lets you run electrical work and supervise journeypersons.

How to get licensed, step by step

  1. Apply to DPR

    Create an account in the DELPROS portal and submit your application. The Board approves it before you can test.

    Delaware DPR: Board of Electrical Examiners, exams (opens in a new tab)

  2. Get your bulletin

    Prov emails the candidate information bulletin, usually within 1 to 2 weeks. It lists the books and editions for your test date.

    Prov, Inc. (Delaware exams) (opens in a new tab)

  3. Pass the exam with Prov

    Schedule at a Delaware test site or from home with remote proctoring. Results come the same day.

    Prov, Inc. (Delaware exams) (opens in a new tab)

  4. Get licensed

    Send DPR your result and license fee, plus proof of general liability insurance as the Board requires (24 Del.C. 1411(a)). You can wait up to 12 months after passing to submit the fee and insurance proof; after that you retake the exam (1408(f)). Electrical licenses renew every 2 years.

    Delaware DPR: Board of Electrical Examiners, exams (opens in a new tab)Delaware Code Title 24, Chapter 14 (Electricians) (opens in a new tab)

How to prepare

  • Open book: bring the titles Prov lists (older or newer editions are allowed). Permanent tabs are fine; sticky notes and handwritten notes are not. Use a simple 4-function calculator.
  • Delaware's State Fire Prevention Commission adopted the 2023 NEC effective January 1, 2026, and DPR says the exams follow the latest NEC adopted in Delaware. The 3/2022 Prov bulletin we could obtain lists 2020, so confirm the edition in the bulletin Prov sends you after DPR approves your application.
  • General electrical knowledge is the largest section (19 of 80), followed by wiring and protection and wiring methods and materials (15 each).
  • Motors and controls is 7 questions: know Article 430 tables and overload and short-circuit protection.
  • The 3/2022 bulletin also lists Ugly's Electrical References for the master exam.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the NEC and the American Electrician's Handbook. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

  • NFPA 70: National Electrical Code (NEC), 2023 Edition (2020 edition listed in the 3/2022 bulletin)Essential

    Allowed in the exam room. Delaware adopted the 2023 NEC effective January 1, 2026. Tab Articles 100, 110, 210, 220, 230, 240, 250, 310, 314, 430 and Chapter 9.

    NFPA store (opens in a new tab)Free online access (opens in a new tab)

  • American Electrician's Handbook, 17th Edition (McGraw Hill)Essential

    Allowed in the exam room. Theory, calculations and general trade practice that the NEC does not cover.

  • Ugly's Electrical References (listed for the master electrician exam in the 3/2022 bulletin)

    Allowed on the master exam. Quick tables for conductors, motors and conduit fill.

Official reference list (as published by the testing agency)
  • NFPA 70: National Electrical Code (NEC), per the Prov bulletin (2020 edition listed in the 3/2022 bulletin; see the edition note)
  • American Electrician's Handbook, 17th Edition (McGraw Hill)
  • Ugly's Electrical References, 2020 (listed in the 3/2022 bulletin)

What's on the exam

Official content outline from Prov, Inc. (number of questions per topic):

TopicQuestions
General Electrical Knowledge19
Plan Reading4
Equipment for General Use5
Wiring & Protection15
Wiring Methods & Materials15
Motors & Controls7
Special Conditions4
Special Equipment4
Special Occupancies4
Communication Systems3

Exam day details

  • Administered by Prov, Inc. for the Delaware Division of Professional Regulation.
  • Fee: $100 to Prov per exam (2022 bulletin). DPR application and license fees are separate.
  • 80 questions in 3 hours; 75% to pass (per DPR).
  • Master electrician applicants must show proof of general liability insurance to activate the license (24 Del.C. 1408 and 1410). The statute leaves the amount to the Board; 24 DE Admin Code 1400-6.1 sets $300,000 (confirm with DPR).
  • Open book: bring the exact titles Prov lists (older or newer editions are allowed). Permanent tabs are fine; repositionable tabs and sticky notes are not. Highlighting and underlining in pen are allowed, but handwritten notes, added formula sheets and stickers are not, and you may not mark your books during the test.
  • Computer-based at Prov's Delaware test sites or at home with remote proctoring (Examroom). Use a simple 4-function calculator; no special calculators.
  • Question counts and times are totals from the Prov bulletin (3/2022). The pass score comes from DPR's exam pages, not the bulletin. Prov emails the current bulletin after DPR approves your application, so use that copy for your test date.
  • Change or cancel at least 3 business days before your test date to keep your fee. After a failure you can retest after 7 days.

Note: Delaware's State Fire Prevention Commission adopted the 2023 NEC effective January 1, 2026, and DPR says the electrical exams are based on the latest NEC adopted in Delaware. The Prov bulletin we could obtain (3/2022) still lists the 2020 NEC. Confirm the edition in the bulletin Prov sends you; our questions follow the 2023 NEC.

Frequently asked questions

What's on the Delaware master electrician exam?

80 questions per the Prov bulletin: general electrical knowledge 19, wiring and protection 15, wiring methods and materials 15, motors and controls 7, equipment for general use 5, plan reading 4, special conditions 4, special equipment 4, special occupancies 4 and communication systems 3.

Can I bring Ugly's to the Delaware master electrician exam?

The 3/2022 bulletin lists Ugly's Electrical References (2020) for the master exam, along with the NEC and the American Electrician's Handbook. Check the bulletin Prov sends you.

Free questions with answers

Show all 10 free questions and answers
  1. A balanced three-phase, 480-volt resistive heating load is rated 36 kW. What is the approximate line current?

    Answer: 43.3 amperes

    For three-phase, I = P / (E x 1.732) = 36,000 / (480 x 1.732) = 36,000 / 831.4 = 43.3 A. Using single-phase math (36,000 / 480) gives 75 A, which overstates the current. Multiplying by 1.732 instead of dividing gives 129.9 A.

    Reference: General electrical theory, Three-phase power formula: I = P / (E x 1.732)

  2. In a commercial building, which 125-volt, 20-ampere receptacle location requires GFCI protection under 210.8(B)?

    Answer: A receptacle in a laundry area

    210.8(B) lists the non-dwelling locations that require GFCI protection, including bathrooms, kitchens, rooftops, outdoors, areas near sinks, locker rooms, garages, crawl spaces, unfinished basements and laundry areas. Conference rooms, corridors and dry storage areas are not on the list.

    Reference: 2023 National Electrical Code (NFPA 70), 210.8(B)(14)

  3. A residential 120-volt, 20-ampere GFCI-protected branch circuit is run in direct-burial Type UF cable under a lawn. What minimum cover does Table 300.5(A) require?

    Answer: 12 inches

    Table 300.5(A), Column 4 covers residential branch circuits rated 120 volts or less with GFCI protection and maximum overcurrent protection of 20 A, and allows 300 mm (12 in.) cover. Without GFCI protection the same cable would need the Column 1 depth of 24 in.

    Reference: 2023 National Electrical Code (NFPA 70), Table 300.5(A), Column 4

  4. A 15-hp, 460-volt, three-phase squirrel-cage (not Design B energy-efficient) motor has a Table 430.250 full-load current of 21 A. What is the maximum rating of a dual-element time-delay fuse for short-circuit and ground-fault protection, using the next higher standard size where permitted by 430.52(C)(1)(a)?

    Answer: 40 amperes

    Table 430.52(C)(1) allows 175 percent of FLC for dual-element fuses: 21 x 1.75 = 36.75 A. Because that is not a standard size, 430.52(C)(1)(a) permits the next higher standard rating in 240.6(A), which is 40 A. 35 A rounds down; 60 A is the inverse-time breaker result (21 x 2.5 = 52.5, next size 60); 70 A is the nontime-delay fuse result (63 A, next size 70).

    Reference: 2023 National Electrical Code (NFPA 70), Table 430.52(C)(1), 430.52(C)(1)(a), 240.6(A)

  5. A fixed storage-type water heater of 50-gallon capacity is rated 5,500 W at 240 volts. What is the minimum ampacity of the branch-circuit conductors under 422.13?

    Answer: 28.6 amperes

    Rated current is 5,500 / 240 = 22.9 A. 422.13 requires the branch-circuit overcurrent device and conductors for fixed storage-type heaters of 120 gallons or less to be rated at not less than 125 percent: 22.9 x 1.25 = 28.6 A. 22.9 A omits the factor, and 34.4 A applies 150 percent.

    Reference: 2023 National Electrical Code (NFPA 70), 422.13

  6. In a Class I, Division 1 location, a conduit enters an explosionproof enclosure that contains a circuit breaker that can produce arcs in normal operation. Within what distance of the enclosure must the conduit seal be installed?

    Answer: 18 inches

    501.15(A)(1) requires each conduit entry into an explosionproof enclosure containing arcing or sparking apparatus to have a seal, and the seal must be installed within 450 mm (18 in.) of the enclosure or as the enclosure marking requires. Only threaded couplings or explosionproof fittings no larger than the conduit may lie between the seal and the enclosure.

    Reference: 2023 National Electrical Code (NFPA 70), 501.15(A)(1)

  7. Two parallel PV source circuits are connected in one conductor run. Each string has a module short-circuit current of 11 A. Using 690.8(A) and 690.8(B)(1), what is the minimum conductor ampacity, before any adjustment or correction factors?

    Answer: 34.4 amperes

    690.8(A)(1)(a) gives maximum current as the sum of the parallel module short-circuit currents x 125 percent: (11 + 11) x 1.25 = 27.5 A. 690.8(B)(1) then requires conductor ampacity not less than that maximum current x 125 percent: 27.5 x 1.25 = 34.4 A. 27.5 A omits the second factor, and 22.0 A is the plain sum.

    Reference: 2023 National Electrical Code (NFPA 70), 690.8(A)(1)(a), 690.8(B)(1)

  8. Within what maximum time must a legally required standby system be available after normal power fails?

    Answer: 60 seconds

    701.12 allows legally required standby power to be available within the time required for the application, not to exceed 60 seconds. Emergency systems under 700.12 are limited to 10 seconds.

    Reference: 2023 National Electrical Code (NFPA 70), 701.12

  9. A building has an intersystem bonding termination installed under 250.94. Where must the bonding conductor from the communications primary protector be connected under 800.100(B)?

    Answer: To the intersystem bonding termination

    800.100(B)(1) requires that where the building has an intersystem bonding termination as required by 250.94, the communications bonding conductor be connected to that termination. The list in 800.100(B)(2) (including interior metal water piping within 5 ft of its entrance) applies only where no intersystem bonding termination exists. A separate rod is used only in the limited cases of 800.100(A)(4) Exception or (B)(3), and a receptacle grounding terminal is not a permitted connection point.

    Reference: 2023 National Electrical Code (NFPA 70), 800.100(B)(1)

  10. A conduit run is scaled on a plan drawn at 1/8 in. = 1 ft and measures 6-1/2 in. horizontally. Notes show a 9-ft vertical drop at each end. What is the total conduit length to be ordered, ignoring waste?

    Answer: 70 ft

    Horizontal length = 6.5 in. x 8 ft per in. = 52 ft (each 1/8 in. is 1 ft, so 8 ft per inch). Add two 9-ft drops: 52 + 18 = 70 ft. 52 ft leaves out the drops and 61 ft counts only one drop.

    Reference: General trade practice, Plan scale conversion (architect's scale, 1/8 in. = 1 ft)

Sources

Questions last verified November 17, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.