Requirements at a glance
| Agency | Connecticut Department of Consumer Protection (DCP); exams by PSI |
|---|---|
| Experience | A completed bona fide apprenticeship in the specific area of the trade; the experience required for a limited license may be less than 4 years (CGS 20-334a(a)(2)); age 18 |
| Exams | PV-2 solar electric exam: 50 questions, 2 hours, 70% (35 items) |
| Books allowed | NEC or NEC Handbook (2020 or 2023), Ugly's, Dunlap Photovoltaic Systems 3rd edition, Komp Practical Photovoltaics, Pieper and Barber solar guides and 29 CFR 1926 |
| Fees | $59 at PSI; DCP $90 application fee (CGS 20-333) and $120 initial license fee (CGS 20-335); renews yearly for $120 |
Workers with a registered apprenticeship and experience in the trade (or equivalent DCP accepts) applying for a Connecticut PV-2 license from the Department of Consumer Protection.
Official links
How to get licensed, step by step
Confirm you qualify
Journeyperson licenses need a completed registered apprenticeship with at least 4 years of experience (or equivalent experience and training DCP accepts), then the trade exam only.
Connecticut DCP: trade license examinations (opens in a new tab)Connecticut General Statutes Chapter 393 (trade licensing) (opens in a new tab)
Apply to DCP
DCP decides whether you are eligible to test. Once approved, you contact PSI to pay and schedule.
Connecticut DCP: trade license examinations (opens in a new tab)
Pass the trade exam with PSI
Both are open book at $59 each. You can test as often as needed for up to one year from your eligibility date. A passing Business and Law score counts for 2 years toward another contractor license.
Schedule with PSI (Connecticut occupational licenses) (opens in a new tab)
Get licensed
Send DCP your passing score report or reports with the license fee shown on it.
Connecticut DCP: trade license examinations (opens in a new tab)
How to prepare
- Bring the exact editions on PSI's list. You can highlight, underline, annotate and index them with permanent tabs, but you can't write in them during the exam and Post-It notes are not allowed.
- Connecticut's 2022 State Building Code uses the 2021 IPC and IMC and the 2020 NEC, each with Connecticut amendments, and points to NFPA 54 and NFPA 58 for fuel gas (the IFGC is not adopted). The bulletin allows several editions, so check it for your test date.
- Components (8) and photovoltaic installation (8) are the largest sections; know NEC Articles 690 and 705.
- Photovoltaic theory, general electrical knowledge and estimating and design are 7 each; safety 6, batteries 3 and wind power 4.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below, and most questions come from the NEC and Ugly's. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
NFPA 70: National Electrical Code (NEC), 2020 Edition (or the NEC Handbook; 2023 also allowed)Essential
Allowed in the exam room. Connecticut adopts the 2020 NEC with state amendments. Tab Articles 100, 110, 210, 215, 220, 230, 240, 250, 310, 314, 430, 690 and Chapter 9.
NFPA store (opens in a new tab)Free online access (opens in a new tab)
Ugly's Electrical References, 2020 or 2023 EditionEssential
Allowed in the exam room. Formulas for voltage drop, power, motors and transformers.
Photovoltaic Systems, 3rd Edition (James P. Dunlop; the PSI bulletin spells it Dunlap)
Allowed in the exam room. Source for the photovoltaics section.
Practical Photovoltaics: Electricity from Solar Cells (Komp, 2002); Easy Guide to Solar Electric (Pieper); Convert Your Home to Solar Energy (Barber)
All allowed in the exam room. Photovoltaic theory, components, installation and design.
29 CFR 1926 (OSHA Construction Standards), sections on your reference list
Trenching, scaffolds, fall protection and ladders. Print just the listed sections.
Official reference list (as published by the testing agency)
- National Electrical Code or NEC Handbook, 2020 or 2023 edition (allowed in the exam room)
- Ugly's Electrical References, 2020 or 2023 (allowed in the exam room)
- Photovoltaic Systems, 3rd Edition (2012), James Dunlap (allowed in the exam room)
- Practical Photovoltaics: Electricity from Solar Cells (2002), Richard J. Komp (allowed in the exam room)
- The Easy Guide to Solar Electric Part II Installation Manual (2001), Adi Pieper, and Convert Your Home to Solar Energy, Barber and Provey (allowed in the exam room)
- 29 CFR Part 1926 (OSHA), or the PSI selections (allowed in the exam room)
- Solar Photovoltaic Systems Installer Trainee Guide, NCCER, 2012 (recommended for study; NOT allowed in the exam room)
What's on the exam
Official content outline from PSI Services (number of questions per topic):
| Topic | Questions | |
|---|---|---|
| Photovoltaic Theory | 7 | |
| General Electrical Knowledge and Theory | 7 | |
| Batteries | 3 | |
| Components | 8 | |
| Photovoltaic Installation | 8 | |
| Estimating and Design | 7 | |
| Wind Power | 4 | |
| Safety | 6 |
Exam day details
- Administered by PSI Services for the Connecticut Department of Consumer Protection.
- Fee: $59 to PSI per exam portion. DCP license fees are separate.
- 50 questions in 2 hours; 70% to pass. Open book.
- The license covers photovoltaic and wind electric generation work up to the point inside or adjacent to the structure (RCSA 20-332).
- Connecticut's 2022 State Building Code (effective 10/1/2022) is based on the 2021 IPC and IMC and the 2020 NEC, each with Connecticut amendments. The PSI bulletin (updated 2/4/2026) still lists the 2020 or 2023 NEC and the 2015, 2018 or 2021 IPC or IMC; check the current bulletin for your test date.
- Passing score is 70% (35 items).
- Open book: bring your own copies of the allowed references. You may highlight, underline, annotate and index them beforehand, but not write in them during the exam. Permanent tabs only; Post-It notes are not allowed.
- Use a silent, nonprinting, non-programmable calculator. For code questions the exam is based only on the edition of the code book listed in the bulletin.
- Candidates may test as often as needed for up to one year from the date of eligibility. Contractor exam portions (business and trade) are each valid for 2 years from the date passed.
- Contractor and dealer licenses need two portions: the Business and Law exam and the trade exam. Journeyperson licenses need only the trade exam.
Frequently asked questions
What's on the Connecticut PV-2 exam?
50 questions: components 8, photovoltaic installation 8, photovoltaic theory 7, general electrical knowledge and theory 7, estimating and design 7, safety 6, then batteries 3 and wind power 4.
Is the PV-2 open book?
Yes. You may bring the allowed references listed on the PSI bulletin, tabbed with permanent tabs, and use a silent, non-programmable calculator.
Do I need the Business and Law exam for the PV-2?
No. Journeyperson applicants take only the trade exam.
Free questions with answers
Show all 10 free questions and answers
A fixed array at about 41 degrees north latitude is adjusted seasonally. Which seasonal tilt rule of thumb gives the best performance in winter?
Answer: Latitude plus about 15 degrees, so the array sits steeper to face the low winter sun
The sun is lower in winter, so a steeper tilt (latitude plus about 15 degrees) faces it more directly. In summer the sun is high, so latitude minus about 15 degrees works better. The yearly-best fixed tilt is near the latitude, and the sun is never overhead at 41 degrees north.
Reference: General practice (PV systems), Array tilt and seasonal adjustment
A PV output circuit has a calculated maximum circuit current of 62 A under 690.8(A). All terminations are rated 75 degrees C and the conductors are copper with no ambient or fill adjustment needed. What is the smallest copper conductor that meets 690.8(B)(1) and the 75 degrees C column of Table 310.16 (6 AWG = 65 A, 4 AWG = 85 A, 3 AWG = 100 A)?
Answer: 4 AWG, since 62 x 1.25 = 77.5 A and 4 AWG carries 85 A at 75 degrees C
690.8(B)(1) requires conductors sized for not less than 125 percent of the 690.8(A) current: 62 x 1.25 = 77.5 A. At 75 degrees C terminals, 6 AWG (65 A) is too small and 4 AWG (85 A) is the smallest that works. 3 AWG would only be needed if a second 125 percent factor were applied to the 77.5 A value, which the rule does not do.
Reference: 2020 National Electrical Code (NFPA 70), 690.8(B)(1); Table 310.16; 110.14(C)
A battery bank is 48 V and 600 Ah (28.8 kWh nominal). The designer limits the maximum depth of discharge to 50 percent. How much energy is usable?
Answer: 14.4 kWh, which is 48 V x 600 Ah x 0.50 = 14,400 Wh of usable energy
Nominal energy is 48 V x 600 Ah = 28,800 Wh. Limiting depth of discharge to 50 percent leaves 28,800 x 0.50 = 14,400 Wh = 14.4 kWh usable. Keeping the discharge shallow extends the life of lead-acid batteries.
Reference: General practice (PV systems), Battery capacity and depth of discharge
With the same wind speed and the same power coefficient, a turbine's rotor diameter is doubled from 2.5 m to 5.0 m. How does the power available to the rotor change?
Answer: It increases by a factor of four, because swept area depends on the square of the diameter
Power in the wind is P = Cp x 1/2 x air density x swept area x V cubed. Swept area is pi x D squared / 4, so doubling D multiplies area, and power, by 4. The cube relationship applies to wind speed, not diameter.
Reference: U.S. DOE WINDExchange Small Wind Guidebook, Glossary: swept area; power in the wind
What is the main practical difference between a transformerless (non-isolated) string inverter and a transformer-based inverter?
Answer: The transformerless unit has no galvanic isolation, and it is lighter and a little more efficient
A transformerless inverter has no isolation transformer, so it is lighter and slightly more efficient, but the dc array is not isolated from the ac system. Such inverters are normally used with ungrounded (functional grounded) arrays and have their own ground-fault and arc-fault detection. Both types produce ac and can be grid-interactive.
Reference: General practice (PV systems), Inverter types: transformer-based versus transformerless
Two rooftop PV systems are being installed. System 1 has dc circuits with a maximum voltage of 72 V; system 2 has dc circuits with a maximum voltage of 380 V. Under 690.11 of the 2020 NEC, which needs listed PV arc-fault circuit protection (or listed equivalent components)?
Answer: Only system 2, since the rule applies at 80 V dc or more between any two conductors
690.11 requires PV systems with PV system dc circuits operating at 80 volts dc or greater between any two conductors to be protected by a listed PV arc-fault circuit interrupter or other listed system components providing equivalent protection. The 72 V system is below that threshold; the 380 V system is above it. The exception covers certain output circuits of systems not on or in buildings.
Reference: 2020 National Electrical Code (NFPA 70), 690.11
What minimum cover is required for directly buried USE-2 PV cable (no raceway, no concrete cover) in a yard at a one-family dwelling?
Answer: 24 in. (600 mm), the column 1 depth for direct burial cables
Table 300.5 column 1 (direct burial cables or conductors) requires 24 in. of cover. Rigid metal conduit needs only 6 in., and some raceways and GFCI-protected 20 A circuits at dwellings allow less. Cable direct burial is the deepest of the common choices in the table.
Reference: 2020 National Electrical Code (NFPA 70), Table 300.5, column 1
When attaching rooftop mounting feet to a shingle roof, where should the lag screws go?
Answer: Into the structural rafters, with the penetration flashed and sealed
Mounting attachments must be fastened into structural members (rafters or trusses), not just the sheathing, and every roof penetration must be flashed and sealed to keep water out. Locate the rafters first and follow the racking manufacturer's installation instructions (110.3(B)).
Reference: General practice (PV systems), Roof attachment: lagging into rafters and flashing
A 6.4 kW dc array at a site with 4.4 peak sun hours per day has these derate factors: soiling 0.95, wiring 0.98, inverter 0.96 and module mismatch 0.98. Multiply the factors together. About how many kWh per year does it produce?
Answer: About 9,000 kWh, from 6.4 x 4.4 x 365 x 0.876 (the combined derate)
The combined derate is 0.95 x 0.98 x 0.96 x 0.98 = 0.876. Energy = array kW x peak sun hours x 365 x derate = 6.4 x 4.4 x 365 x 0.876 = 9,003 kWh. Dividing by the derate overstates production, and 25 kWh is only the average daily value (6.4 x 4.4 x 0.876 = 24.7 kWh).
Reference: General practice (PV systems), Energy production estimate with derate factors
What is the required height of the top edge of a guardrail system's top rail above the walking/working level?
Answer: 42 in. plus or minus 3 in., which is the height set for guardrail top rails
1926.502(b)(1) sets the top rail at 42 inches, plus or minus 3 inches, above the walking/working level. 1926.502(b)(3) requires the top rail to resist at least 200 pounds of force applied outward or downward at any point.
Reference: 29 CFR Part 1926 (OSHA Construction Standards), 1926.502(b)(1)
Sources
- PSI: Connecticut Electrical Examinations Candidate Information Bulletin (updated 2/4/2026) (opens in a new tab)
- Connecticut Department of Consumer Protection: trade license examinations (opens in a new tab)
- Connecticut General Statutes Chapter 393 (trade licensing) (opens in a new tab)
- Connecticut DAS: State Building Code regulations (opens in a new tab)
Questions last verified November 16, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.