Question 1 of 10Licensing

A journeyman plumber has worked in Connecticut as a licensed journeyman for 26 months and wants an unlimited plumbing contractor's license by the journeyman-service route. Under Sec. 20-334a(a)(1)(A), how much service as a journeyman in the trade is the minimum for that route?

Requirements at a glance

Who takes itEvery applicant for a Connecticut contractor or dealer license, with the trade exam
Format50 questions, 2 hours, 70% to pass, open book
Book allowedNASCLA Contractors Guide to Business, Law and Project Management, Connecticut, 6th Edition
Fee$59; a pass is good for 2 years toward other contractor licenses

Anyone applying for a Connecticut electrical, plumbing or heating, piping and cooling contractor license (E-1, P-1, S-1 and the other contractor classes), in addition to the trade exam.

How to get licensed, step by step

  1. Get the Connecticut guide

    Buy the NASCLA Connecticut 6th edition and tab it with permanent tabs. You bring your own copy.

    NASCLA store: Connecticut 6th edition (opens in a new tab)

  2. Learn the biggest sections

    Estimating and bidding (7), contracts (6) and licensing, tax laws, labor laws, project management and environmental and safety (5 each) make up most of the exam.

    Schedule with PSI (Connecticut occupational licenses) (opens in a new tab)

  3. Schedule with PSI

    Once DCP approves you, schedule this exam along with your trade exam.

    Schedule with PSI (Connecticut occupational licenses) (opens in a new tab)

How to prepare

  • Bring the exact editions on PSI's list. You can highlight, underline, annotate and index them with permanent tabs, but you can't write in them during the exam and Post-It notes are not allowed.
  • Practice markup, overhead and payroll math for estimating and financial management.
  • Know the licensing basics in CGS Chapter 393 and that home improvement contractors register under Chapter 400 with no exam.
  • Review federal basics the guide cites: IRS payroll tax rules and OSHA recordkeeping and construction safety (29 CFR 1904 and 1926).
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the NASCLA Connecticut guide. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

Official reference list (as published by the testing agency)
  • Contractors Guide to Business, Law and Project Management, Connecticut, 6th Edition, NASCLA (allowed in the exam room)

What's on the exam

Official content outline from PSI Services (number of questions per topic):

TopicQuestions
Licensing5
Estimating and Bidding7
Lien Law2
Financial Management4
Tax Laws5
Labor Laws5
Project Management5
Contracts6
Business Organization2
Risk Management4
Environmental and Safety5

Exam day details

  • Administered by PSI Services for the Connecticut Department of Consumer Protection.
  • Fee: $59 to PSI per exam portion. DCP license fees are separate.
  • 50 questions in 2 hours; 70% to pass.
  • A passing Business and Law score counts toward another contractor license for 2 years.
  • Open book: bring your own copies of the allowed references. You may highlight, underline, annotate and index them beforehand, but not write in them during the exam. Permanent tabs only; Post-It notes are not allowed.
  • Use a silent, nonprinting, non-programmable calculator. For code questions the exam is based only on the edition of the code book listed in the bulletin.
  • Candidates may test as often as needed for up to one year from the date of eligibility. Contractor exam portions (business and trade) are each valid for 2 years from the date passed.
  • Contractor and dealer licenses need two portions: the Business and Law exam and the trade exam. Journeyperson licenses need only the trade exam.

Frequently asked questions

What's on the Connecticut Business and Law exam?

50 questions: estimating and bidding 7, contracts 6, licensing 5, tax laws 5, labor laws 5, project management 5, environmental and safety 5, financial management 4, risk management 4, lien law 2 and business organization 2.

Do I have to retake Business and Law for a second contractor license?

Not if you passed it within the past 2 years. After that you retake it along with the new trade exam.

Which book is allowed?

The NASCLA Contractors Guide to Business, Law and Project Management, Connecticut, 6th Edition. You may highlight and index it with permanent tabs but not write in it during the exam.

Free questions with answers

Show all 10 free questions and answers
  1. A journeyman plumber has worked in Connecticut as a licensed journeyman for 26 months and wants an unlimited plumbing contractor's license by the journeyman-service route. Under Sec. 20-334a(a)(1)(A), how much service as a journeyman in the trade is the minimum for that route?

    Answer: Not less than two years of service as a journeyman in the trade

    Sec. 20-334a(a)(1)(A) allows an unlimited contractor's license for a person who has served as a journeyman in the trade for not less than two years (out-of-state service must be shown comparable). The four-year figure belongs to the journeyman license, which requires a bona fide apprenticeship program with at least four years of experience.

    Reference: Connecticut General Statutes, Sec. 20-334a(a)(1)(A)

  2. A plumbing contractor with a direct contract with the homeowner stopped work on a house on March 1 and was not paid. Under Sec. 49-34, by what deadline must the contractor lodge the sworn mechanic's lien certificate with the town clerk?

    Answer: Within ninety days after the contractor ceased furnishing services or materials

    Sec. 49-34 makes a mechanic's lien invalid unless the claimant lodges a sworn certificate with the town clerk within ninety days after ceasing to furnish services or materials. March 1 plus 90 days is May 30. The one-year period applies later, to starting the foreclosure action under Sec. 49-39.

    Reference: Connecticut General Statutes, Sec. 49-34(1)

  3. Under Sec. 20-338d(d), when must a contractor give the owner a copy of a written residential contract, and at what cost?

    Answer: At the time the contract is executed, free of charge

    Sec. 20-338d(d) requires the contractor to deliver to each owner, free of charge, a copy of the contract at the time it is executed, and a copy of any amendment when it is made.

    Reference: Connecticut General Statutes, Sec. 20-338d(d)

  4. A plumbing contractor reported $62,000 in employment taxes during the lookback period, which makes the business a semiweekly schedule depositor. Payroll taxes from a payday on Thursday, June 11, 2026 are due by what date?

    Answer: Wednesday, June 17

    Semiweekly depositors (lookback taxes over $50,000) deposit taxes for Wednesday, Thursday and Friday paydays by the following Wednesday, and for Saturday through Tuesday paydays by the following Friday. A Thursday payday on June 11 is deposited by Wednesday, June 17.

    Reference: IRS Publication 15 (2026), Employer's Tax Guide, Section 11. Semiweekly Deposit Schedule; Table 2

  5. A Connecticut contractor pays a journeyman $28.00 per hour. In one workweek the journeyman works 46 hours. Under Sec. 31-76c, what is the journeyman's total gross pay for the week, assuming no other pay and a regular rate of $28.00?

    Answer: $1,372.00

    Sec. 31-76c requires at least one and one-half times the regular rate for hours over forty in a workweek. Regular pay: 40 x $28.00 = $1,120.00. Overtime rate: $28.00 x 1.5 = $42.00, and 6 x $42.00 = $252.00. Total: $1,120.00 + $252.00 = $1,372.00.

    Reference: Connecticut General Statutes, Sec. 31-76c

  6. Under 29 CFR 1926.451(g)(1), an employee on a scaffold must be protected from falling to a lower level when the employee is more than how high above that lower level?

    Answer: More than 10 feet

    29 CFR 1926.451(g)(1) requires fall protection for each employee on a scaffold more than 10 feet above a lower level. Do not confuse it with the 6-foot general construction trigger in 1926.501(b)(1).

    Reference: 29 CFR 1926 (OSHA Construction Standards), 1926.451(g)(1)

  7. A contractor's direct cost to build a job is $60,000, and the contractor wants a 25% gross profit margin (profit as a percent of the selling price). What selling price should the contractor bid?

    Answer: $80,000

    Margin is based on price, so cost is 75% of the price: $60,000 / (1 - 0.25) = $80,000. Check: 25% of $80,000 is $20,000 profit, and $60,000 + $20,000 = $80,000. A 25% markup on cost gives only $75,000, which is a 20% margin.

    Reference: General construction estimating practice, Markup versus gross margin

  8. A contract is $900,000 with an estimated total cost of $750,000. Costs to date are $300,000, and the contractor has billed $400,000. Using the cost-to-cost percent-complete method, is the job over- or underbilled, and by how much?

    Answer: Overbilled by $40,000

    Percent complete = $300,000 / $750,000 = 40%. Earned revenue = 40% x $900,000 = $360,000. Billed $400,000 - earned $360,000 = $40,000 overbilled, which is a liability (billings in excess of costs). Comparing billing to cost ($400,000 vs $300,000) would wrongly give $100,000.

    Reference: General financial management practice, Percent-complete (cost-to-cost) method; over/underbilling

  9. Which set of items is normally part of project closeout?

    Answer: Punch list completion, as-built drawings, operation manuals, warranties and a final lien waiver

    Closeout normally includes completing the punch list, delivering as-built drawings, operation and maintenance manuals and warranties, final inspections and certificates, final payment, and a final lien waiver. Under Sec. 42-158k retainage is due within 30 days after the certificate of final completion.

    Reference: General construction project management practice, Project closeout

  10. Under Sec. 49-41(a), a contract for a Connecticut public building or public work must include a payment bond for the protection of persons supplying labor and materials when the contract exceeds what amount?

    Answer: $100,000

    Sec. 49-41(a) requires a payment bond, in the amount of the contract, for each state or municipal public building or public work contract exceeding $100,000. Sec. 49-41(b) separately limits performance bonds: none may be required for a general bid under $25,000 or a sub-bid under $50,000.

    Reference: Connecticut General Statutes, Sec. 49-41(a)