Arkansas licensing exam

Arkansas HVACR Class B Exam (Prov): Practice Test & Licensing Guide

The Prov exam for an Arkansas Class B HVACR license from the HVACR Licensing Board: 50 open-book questions in 3 hours on work up to the Class B size limits, 70% to pass.

Questions
50
Time limit
3 hours
Passing score
70%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10Law and Administration

A Class B contractor is asked to install a single gas-fired makeup air heater with a rated input of 1,200,000 BTUH. How does the Class B license apply?

Requirements at a glance

AgencyArkansas HVACR Licensing Board (Department of Labor and Licensing); exams by Prov
ExperienceApplicants with no license history need 2 years of experience as an HVACR contractor or employee of one, or Board-approved training (17 CAR 261; our copy is an August 2025 draft)
ExamClass B HVACR (50 questions, 3 hours, 70% to pass, open book)
Books allowedThe Arkansas HVAC/R Law and Rules, the 2018 or 2021 IMC and IFGC (or Arkansas Fuel Gas Code), ACCA Manual J (8th Edition), Modern Refrigeration and Air Conditioning (21st Edition), the 2020 NEC and Refrigeration and Air Conditioning Technology (8th Edition)
Fees$100 per computer-based exam ($55 paper/pencil), plus Board application and license fees

HVACR contractors and their designated license holders applying to the Arkansas HVACR Licensing Board for a Class B license. Applicants with no license history need 2 years of experience as an HVACR contractor or employee, or Board-approved training.

How to get licensed, step by step

  1. Apply to the Board

    Send the HVACR Licensing Board your Class B application. The Board must pre-approve you before you schedule. Questions: adll.hvac@arkansas.gov or 501-682-9201.

    Arkansas Department of Labor and Licensing: HVACR licensing (opens in a new tab)

  2. Schedule with Prov

    After approval, schedule the computer-based exam with Prov and pay the $100 exam fee. Approval lasts one year.

    Prov (schedule your exam) (opens in a new tab)Prov: Arkansas HVACR candidate bulletin (2025.07.03, archived copy) (opens in a new tab)

  3. Pass the exam

    The exam is open book and timed, with a 70% cut score. Permanent tabs are fine; photocopied books, sticky notes and test-prep guides are not allowed.

    Prov: Arkansas HVACR candidate bulletin (2025.07.03, archived copy) (opens in a new tab)

  4. Get licensed

    Pay the license fee. A Class A, B, D or E licensee is the designated license holder for the company.

    Arkansas Department of Labor and Licensing: HVACR licensing (opens in a new tab)

How to prepare

  • Download the Arkansas HVAC/R Law and Rules (free PDFs from the Department of Labor and Licensing); every HVACR exam has a law and administration section and you may bring printed copies.
  • The 2018 or 2021 IMC and IFGC (or the Arkansas Fuel Gas Code) are allowed. The Board adopted the 2021 International Mechanical Code effective July 1, 2022.
  • Fuel gas systems and maintenance are the biggest areas (8 questions each): know the Class B limits, then work the IFGC (or Arkansas Fuel Gas Code) and equipment maintenance.
  • Prov's bulletin says Class B is limited to 15 tons of cooling per unit, but Act 746 of 2025 and the August 2025 draft rule say 25 tons. Check the current limit with the Board.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the 2021 IMC and the 2018 Arkansas Fuel Gas Code. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

Official reference list (as published by the testing agency)
  • Arkansas HVAC/R Law (free PDF from the Department of Labor and Licensing; candidate-printed copies allowed)
  • Arkansas HVAC/R Rules and Regulations (free PDF from the Department; candidate-printed copies allowed)
  • International Mechanical Code (IMC), 2018 or 2021 edition
  • International Fuel Gas Code (IFGC), 2018 or 2021 edition, or the Arkansas Fuel Gas Code 2018 or 2021 edition as a substitute
  • Residential Load Calculation: Manual J, 8th Edition (ACCA, ISBN 9781892765253)
  • Modern Refrigeration and Air Conditioning, 21st Edition (ISBN 978-1-63563-877-6)
  • NFPA 70: National Electrical Code, 2020 (ISBN 9781455922970)
  • Refrigeration and Air Conditioning Technology, 8th Edition (Cengage, ISBN 1305578295)

What's on the exam

Official content outline from Prov (number of questions per topic):

TopicQuestions
General Knowledge4
Systems & Sizing7
Equipment4
Piping5
Refrigeration Systems5
Fuel Gas Systems8
Electrical5
Maintenance8
Law and Administration4

Exam day details

  • Administered by Prov for the Arkansas HVACR Licensing Board (Department of Labor and Licensing).
  • Fee: $100 for the computer-based exam ($55 paper/pencil) per Prov's bulletin; 17 CAR 261-106(g) also sets $100. Board application and license fees are separate.
  • Prov's bulletin: 50 questions in 3 hours, open book, 70% cut score. Our practice exam uses the same counts and the same nine subject areas.
  • Computer-based exam from Prov (paper/pencil is cheaper). The HVACR Licensing Board must pre-approve you before you schedule; approval lasts one year.
  • All Prov HVACR exams are open book and timed, with a 70% cut score. Books may carry permanent tabs; photocopied books, sticky notes and test-prep study guides are not allowed. The Arkansas HVAC/R Law and Rules may be printed.
  • 17 CAR Part 261 was rewritten after Act 746 of 2025. The copy we studied is an August 2025 draft, so check the final rule.

Note: Prov's July 2025 bulletin still describes Class B as limited to 15 tons of cooling per unit, but Act 746 of 2025 and the August 2025 draft rule raise Class B to 25 tons. Confirm the current limit with the Board. Format and subject areas come from Prov's bulletin dated July 3, 2025.

Frequently asked questions

What can a Class B HVACR licensee do?

HVACR work up to 1,000,000 BTUH of heating input and 15 horsepower of refrigeration per unit, and up to 25 tons of cooling under Act 746 of 2025 and the August 2025 draft rule (Prov's bulletin still says 15 tons per unit). Larger systems need a Class A license.

What's on the exam?

Nine subject areas: fuel gas systems (8 questions), maintenance (8), systems and sizing (7), piping (5), refrigeration systems (5), electrical (5), general knowledge (4), equipment (4) and law and administration (4).

How much does the exam cost?

$100 for the computer-based exam ($55 paper/pencil), plus Board application and license fees.

Free questions with answers

Show all 10 free questions and answers
  1. A Class B contractor is asked to install a single gas-fired makeup air heater with a rated input of 1,200,000 BTUH. How does the Class B license apply?

    Answer: The unit exceeds the 1,000,000 BTUH per-unit heating input limit, so the job needs a Class A license

    Class B work is limited to not more than 1,000,000 BTUH heating input per unit (17 CAR 261-103(b)). A 1,200,000 BTUH heater is over the limit, so a Class A licensee must do the work. The 25-ton figure is the cooling limit; heating has its own limit, and Class D covers only sheet metal duct work.

    Reference: 17 CAR 261 (HVACR Licensing Board rules, 2025 draft), 17 CAR 261-103(b)

  2. The IMC conflicts with a provision of a standard it references. Which governs under IMC Section 102.8.1?

    Answer: The IMC provision applies

    Section 102.8.1 states that where the code and a referenced standard conflict, the code's provisions apply. (Section 102.8 does carve out the conditions of an equipment listing and the manufacturer's installation instructions when enforcing the code would violate the listing.)

    Reference: 2021 International Mechanical Code (Arkansas, 17 CAR 261-121), Section 102.8.1

  3. A new house will use a continuously running kitchen exhaust fan rather than an intermittent range hood. What minimum rate does IMC Table 403.3.2.3 give for the kitchen?

    Answer: 25 cfm continuous

    For Group R-2, R-3 and R-4 occupancies, Table 403.3.2.3 requires kitchens to have 100 cfm intermittent or 25 cfm continuous exhaust. The 100 cfm value only applies if the fan runs intermittently, and 20 cfm is the bathroom continuous rate.

    Reference: 2021 International Mechanical Code (Arkansas, 17 CAR 261-121), Table 403.3.2.3

  4. Where must air filters be located in a heating and air-conditioning system under IMC Section 605.1?

    Answer: Upstream of any heat exchanger or coil, filtering all return, outdoor and makeup air

    Section 605.1 requires all return, outdoor and makeup air to be filtered upstream of any heat exchanger or coil, and filters must be placed at an approved, convenient location. Section 605.3 adds that ducts must give even air distribution over the filter.

    Reference: 2021 International Mechanical Code (Arkansas, 17 CAR 261-121), Section 605.1

  5. A furnace rated at 80,000 BTUH input and a water heater rated at 40,000 BTUH input share a room. Using the standard method for indoor combustion air in the 2018 Arkansas Fuel Gas Code, what volume of room space is required?

    Answer: 6,000 cubic feet

    Section 304.5.1 requires 50 cubic feet per 1,000 BTUH of the appliance input rating, and the volumes of all appliances in the space are added (304.5). Total input: 80,000 + 40,000 = 120,000 BTUH. Volume: 120 x 50 = 6,000 cubic feet. Using only the furnace gives 4,000; 20 cubic feet per 1,000 BTUH is an older rule that gives 2,400.

    Reference: 2018 Arkansas Fuel Gas Code, Section 304.5.1

  6. A furnace (90,000 BTUH) and water heater (30,000 BTUH) are in a closet that gets all combustion air from the outdoors through two permanent openings connected to vertical ducts. What is the minimum free area of each opening under the 2018 Arkansas Fuel Gas Code, Section 304.6.1?

    Answer: 30 square inches

    Total input is 90,000 + 30,000 = 120,000 BTUH. Openings that communicate with the outdoors directly or through vertical ducts need 1 square inch per 4,000 BTUH: 120,000 / 4,000 = 30 square inches each, one commencing within 12 inches of the top and one within 12 inches of the bottom. 60 square inches is the horizontal duct rule (1 per 2,000), 40 is the one-opening rule (1 per 3,000), and 120 is the indoor 1 per 1,000 figure.

    Reference: 2018 Arkansas Fuel Gas Code, Section 304.6.1

  7. A mechanical gauge will be used on a gas piping test at 4 psig. Under Section 406.4, what is the greatest full-scale range the gauge may have?

    Answer: 20 psig

    Section 406.4 requires that the highest end of a mechanical gauge scale be not greater than five times the test pressure: 4 x 5 = 20 psig. A 40 psig gauge would be too coarse to show a small pressure loss at a 4 psig test.

    Reference: 2018 Arkansas Fuel Gas Code, Section 406.4

  8. A gas water heater will be installed in an attic. Under Section 306.3.2, what level service space is required at its front?

    Answer: 36 inches deep by 36 inches wide

    Section 306.3.2 requires a level service space of at least 36 inches by 36 inches at the front of an attic water heater, and a clear access opening of at least 20 by 36 inches. The 30 by 30 inch service space is the general appliance requirement in Section 306.3.

    Reference: 2018 Arkansas Fuel Gas Code, Section 306.3.2

  9. Refrigerant pipe for a system using a Group A3 refrigerant runs through a corridor outside the equipment room. Besides the refrigerant designation and safety group, what must its identification include under IMC Section 1109.2.7?

    Answer: The statement: DANGER—Risk of Fire or Explosion. Flammable Refrigerant.

    Section 1109.2.7 requires refrigerant pipe outside the equipment room to be identified at intervals not exceeding 20 feet with the refrigerant designation and safety group. For Group A2, A3, B2 and B3 refrigerants the label must also say "DANGER—Risk of Fire or Explosion. Flammable Refrigerant." The "DANGER—Toxic Refrigerant" statement is for Group B refrigerants.

    Reference: 2021 International Mechanical Code (Arkansas, 17 CAR 261-121), Section 1109.2.7

  10. Can a gas piping system be used as the grounding electrode for an electrical system under the 2018 Arkansas Fuel Gas Code?

    Answer: No, gas piping may not be used as a grounding electrode

    Section 309.1 states that gas piping shall not be used as a grounding electrode. Section 310 separately requires gas piping likely to become energized to be bonded to an effective ground-fault current path.

    Reference: 2018 Arkansas Fuel Gas Code, Section 309.1

Sources

Questions last verified November 13, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.