Alabama licensing exam

Alabama General Contractor Business and Law Exam: Practice Test & Licensing Guide

The PSI business and law exam required of all Alabama general contractors: 50 open-book questions on licensing, estimating, liens, finance, payroll, contracts, risk and safety. 70% to pass.

Questions
50
Time limit
2 hours
Passing score
70%
Books
Open book

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10Licensing

A property owner builds a warehouse on land the owner holds in fee, using only the owner's own non-contractual forces. The owner then wants to award the electrical work, a $62,000 contract, to a subcontractor. What does Rule 230-X-1-.07 require?

Requirements at a glance

AgencyAlabama Licensing Board for General Contractors (LBGC); exam by PSI
Exam50 scored questions, 2 hours, 70% to pass, open book
Book allowedNASCLA Contractors Guide to Business, Law and Project Management, Alabama General, 3rd Edition
Fee$96 to PSI per exam registration
RetakesUnlimited within your 1-year eligibility; PSI fee each time

Every applicant for an Alabama general contractor license from the Licensing Board for General Contractors, in addition to the trade exam.

How to get licensed, step by step

  1. Apply to the Board

    Submit your application to the Licensing Board for General Contractors. Your eligibility is valid for 1 year from the date the state receives the application.

    Alabama Licensing Board for General Contractors (opens in a new tab)

  2. Schedule with PSI

    Register at test-takers.psiexams.com/alcon or call (855) 257-1619. The fee is $96 per exam registration.

    Schedule with PSI (Alabama general contractors) (opens in a new tab)

  3. Take the exam

    Bring your open-book references (highlighting, underlining and permanent tabs are allowed; no writing, loose papers or sticky notes) and a silent, non-programmable calculator. You see your result on screen right away.

    Schedule with PSI (Alabama general contractors) (opens in a new tab)

How to prepare

  • Licensing (8) is the largest section: know the Board's licensing rules, including that commercial work of $50,000 or more needs a license.
  • Payroll and taxes (6) and contracts (6) come next, then estimating, financial and personnel and labor (5 each).
  • PSI's bulletin lists this exam as required of all general contractors.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

    Official reference list (as published by the testing agency)
    • NASCLA Contractors Guide to Business, Law and Project Management, Alabama General, 3rd Edition (allowed in the exam room; you may bring your own copy)

    What's on the exam

    Official content outline from PSI Services (number of questions per topic):

    TopicQuestions
    Licensing8
    Estimating and Bidding5
    Liens2
    Financial5
    Payroll and Taxes6
    Personnel and Labor5
    Project Management3
    Contracts6
    Business Organization2
    Risk Management4
    Safety Recordkeeping and Environmental4

    Exam day details

    • Administered by PSI Services for the Alabama Licensing Board for General Contractors.
    • Fee: $96 to PSI per exam registration. Board application and license fees are separate.
    • 50 scored questions in 2 hours; 70% to pass.
    • PSI gives the exam for the Alabama Licensing Board for General Contractors (LBGC). Eligibility is valid for 1 year from the date the state receives your application; you can test an unlimited number of times in that year, paying the PSI fee each time.
    • PSI may add one to ten unscored experimental questions (about 10% of the exam), which count against your time.
    • Open book. Bring your own references: you may highlight, underline and index them, but not write in them or add papers; only permanent tabs are allowed. PSI does not provide them in the exam center. A silent, non-printing, non-programmable calculator is allowed.
    • You see your result on screen right after the exam; a failing candidate also gets a diagnostic report by subject area.

    Frequently asked questions

    What's on the Alabama GC business and law exam?

    50 questions: licensing 8, payroll and taxes 6, contracts 6, estimating and bidding 5, financial 5, personnel and labor 5, risk management 4, safety recordkeeping and environmental 4, project management 3, liens 2 and business organization 2.

    Which book is allowed?

    The NASCLA Contractors Guide to Business, Law and Project Management, Alabama General, 3rd Edition. Later editions are acceptable for non-code references.

    Can I retake it?

    Yes, as many times as you like during the 1-year eligibility window, paying the PSI fee each time.

    Free questions with answers

    Show all 10 free questions and answers
    1. A property owner builds a warehouse on land the owner holds in fee, using only the owner's own non-contractual forces. The owner then wants to award the electrical work, a $62,000 contract, to a subcontractor. What does Rule 230-X-1-.07 require?

      Answer: The $62,000 contract must be awarded to a properly licensed prime contractor

      The owner/builder exemption lets an owner use its own forces without a license, but the owner may only let or award contracts of $50,000 ($5,000 for swimming pools) or more to a properly licensed prime contractor. Splitting the payments does not avoid the rule (see 230-X-1-.09).

      Reference: Alabama Administrative Code ch. 230-X-1 (Licensing Board for General Contractors), 230-X-1-.07

    2. A job has direct costs of $240,000. The contractor recovers overhead at 15% of direct cost and then adds 10% profit on the sum of direct cost and overhead. What is the bid price?

      Answer: $303,600

      Overhead = 240,000 x 0.15 = $36,000; subtotal = $276,000; profit = 276,000 x 0.10 = $27,600; bid = $303,600. $300,000 adds 25% to direct cost, $276,000 omits profit, and $306,667 treats profit as a margin on price (276,000 / 0.90).

      Reference: General construction business practice (NASCLA Contractors Guide to Business Law and Project Management: estimating), Overhead and profit

    3. What is a mechanic's lien?

      Answer: A claim against the improved property securing payment for unpaid labor or materials

      A mechanic's lien gives an unpaid contractor, subcontractor or supplier a security interest in the real property it improved. It is a claim on the property, not a bond or an insurance claim; the filing deadlines and notice rules depend on state statute.

      Reference: General construction business practice (NASCLA Contractors Guide to Business Law and Project Management: liens), Mechanic's liens

    4. A contractor's balance sheet shows current assets of $640,000 and current liabilities of $400,000. What is the current ratio?

      Answer: 1.60

      Current ratio = current assets / current liabilities = 640,000 / 400,000 = 1.60. 0.63 inverts the ratio, and 2.60 adds the two figures before dividing (1,040,000 / 400,000).

      Reference: General construction accounting practice (NASCLA Contractors Guide to Business Law and Project Management: financial management), Current ratio

    5. An employee earns $1,200 for the week and is under the Social Security wage base. What is the employer's share of Social Security and Medicare tax (FICA) on those wages?

      Answer: $91.80

      The employer pays 6.2% Social Security plus 1.45% Medicare = 7.65%. 1,200 x 0.0765 = $91.80. $183.60 is both employer and employee shares, $74.40 is Social Security only, and $17.40 is Medicare only.

      Reference: IRS Publication 15 (Circular E), Employer's Tax Guide (2026), Section 9, Social security and Medicare taxes (tax rates)

    6. Under the common-law rules summarized in IRS Publication 15, when is a worker generally the contractor's employee?

      Answer: When the contractor has the right to control what will be done and how it will be done

      A worker is generally an employee if the business has the right to control what will be done and how it will be done, even when the worker has freedom of action. The label used (agent, independent contractor) and the way payment is measured do not matter.

      Reference: IRS Publication 15 (Circular E), Employer's Tax Guide (2026), Section 2, Employee status under common law

    7. A small contractor had 8 employees at all times during the last calendar year and has not been contacted by OSHA or the Bureau of Labor Statistics about recordkeeping. Which statement is correct?

      Answer: Keep no 300 Log, but report fatalities and hospitalizations

      29 CFR 1904.1(a)(1) exempts employers with 10 or fewer employees at all times during the last calendar year from keeping OSHA injury and illness records, but all OSHA-covered employers must still report fatalities, in-patient hospitalizations, amputations and eye losses under 1904.39.

      Reference: 29 CFR Part 1904 (OSHA recordkeeping), 29 CFR 1904.1(a)(1)

    8. Under a lump-sum (stipulated sum) contract, who generally carries the risk that actual costs exceed the estimate?

      Answer: The contractor

      A lump-sum contract fixes the price for the defined scope, so cost overruns come out of the contractor's profit unless a change order or an owner-caused change applies. Cost-plus contracts shift that risk to the owner.

      Reference: General construction business practice (NASCLA Contractors Guide to Business Law and Project Management: contracts), Types of contracts

    9. In a CPM network, A (3 days) must precede B (5 days) and C (8 days); both B and C must be done before D (4 days). What is the shortest project duration?

      Answer: 15 days

      Path A-B-D = 3 + 5 + 4 = 12 days; path A-C-D = 3 + 8 + 4 = 15 days. The longest path (A-C-D) is the critical path and sets the duration at 15 days. Adding every activity (20 days) ignores that B and C run in parallel.

      Reference: General construction business practice (NASCLA Contractors Guide to Business Law and Project Management: project management), Critical path method

    10. Who are the three parties to a construction surety bond?

      Answer: Principal, obligee and surety

      The principal is the contractor, the obligee is the party protected (usually the owner), and the surety is the company that guarantees the principal's obligation.

      Reference: General construction business practice (NASCLA Contractors Guide to Business Law and Project Management: risk management), Surety bonds

    Sources