Question 1 of 10General Electrical Knowledge

Under the Article 100 definition, a load is a continuous load when the maximum current is expected to continue for at least how long?

Requirements at a glance

AgencyWest Virginia Office of the State Fire Marshal, Regulatory and Licensing Division
ExperienceAge 18, plus 2 years as a journeyman electrician in work of enough breadth to show you can perform all types of electrical work (103 CSR 5, 4.1)
ExamMaster electrician exam: 50 multiple choice plus 5 calculations, 4 hours, 70%. Paper, in person, open book
Books allowedNEC (2023 per the State Fire Marshal; some forms still say 2020, so confirm) with tabs
Fees$25 non-refundable application review fee (103 CSR 5, 5.2.2); $50 a year license fee (103 CSR 5, 7.2)

Electricians applying to the West Virginia State Fire Marshal for a master license, which lets you contract for and direct all types of electrical work.

How to get licensed, step by step

  1. Confirm you qualify

    You must be 18 (a student in an approved vocational electrical program may test earlier and be licensed at 18) and meet the experience for your level.

    State Fire Marshal: Regulatory and Licensing Division (opens in a new tab)West Virginia Code 29-3B (Electricians) (opens in a new tab)

  2. Apply to the State Fire Marshal

    Send the application and the $25 review fee at least 10 working days before the exam date you want. You receive a written authorization form to bring to the exam.

    State Fire Marshal: Regulatory and Licensing Division (opens in a new tab)

  3. Sit the in-person exam

    Exams are on set dates in Charleston, Beckley, Clarksburg, Martinsburg and Wellsburg; see the 2027 schedule on the State Fire Marshal's page. You forfeit the fee if you no-show without 24 hours' notice.

    State Fire Marshal: Regulatory and Licensing Division (opens in a new tab)

  4. Get licensed

    After you pass with 70%, send the license fee and the State Fire Marshal issues your license.

    State Fire Marshal: Regulatory and Licensing Division (opens in a new tab)

How to prepare

  • The State Fire Marshal publishes no outline, only the format: 50 multiple-choice questions and 5 calculations in 4 hours. Practice both, and do the calculations first or last on a set plan so time doesn't run out.
  • Tab Articles 90, 100, 110, 210, 215, 220, 230, 240, 250, 310, 314, 430 and Chapter 9 of your NEC, and the Annex tables you use for calculations.
  • Master questions add service and feeder sizing, load calculations, transformers and special occupancies.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the NEC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

Official reference list (as published by the testing agency)
  • NFPA 70: National Electrical Code (2023 edition per the State Fire Marshal; see the edition note)
  • Ugly's Electrical References and similar field references with tabs are reported as allowed; check your exam authorization.

What's on the exam

Estimated topic weighting. No official breakdown is published:

TopicQuestions
General Electrical Knowledge7
Wiring and Protection12
Wiring Methods and Materials14
Equipment for General Use6
Motors and Controls4
Special Occupancies and Equipment7
Calculations5

Exam day details

  • Administered by West Virginia Office of the State Fire Marshal.
  • Fee: $25 non-refundable application review fee to the State Fire Marshal (103 CSR 5, 5.2.2). After you pass, the license fee is $50 a year (103 CSR 5, 7.2).
  • 50 multiple-choice questions plus 5 calculation problems in 4 hours; 70% to pass.
  • Master applicants need 2 years as a journeyman electrician in work of enough breadth and independence to show you can perform all types of electrical work (103 CSR 5, 4.1).
  • This is a State Fire Marshal exam, not a Prov exam. It is given on paper in person at Charleston, Beckley, Clarksburg, Martinsburg and Wellsburg on published dates (the 2027 schedule has six Charleston dates).
  • Apply to the State Fire Marshal at least 10 working days before the exam date; you must bring the written authorization form you receive. You must be 18 (a student in an approved vocational electrical program may test earlier and be licensed at 18).
  • 70% is required to pass (103 CSR 5, 5.13). The exam is open book. The SFMO does not publish a content outline; our topic weights are an estimate based on the NEC.
  • If you do not appear you forfeit the exam fee unless you give 24 hours notice, and you pay again when you reapply.

Note: The State Fire Marshal's electrical page says all electrical exams use the 2023 NEC from January 1, 2026, but its application form and some other pages still say 2020. Our questions follow the 2023 NEC. Confirm the edition with the State Fire Marshal before you test. The SFMO publishes no exam outline, so the topic weights shown are our estimate.

Frequently asked questions

How much experience do I need for the master electrician exam in West Virginia?

At least 2 years as a journeyman electrician, doing electrical work broad and independent enough to show you can handle all types of work and direct others (103 CSR 5).

Is the master exam open book?

Yes. It is an open-book NEC exam of 50 multiple-choice questions and 5 calculations in 4 hours; 70% passes.

Which NEC edition does the master exam use?

The State Fire Marshal says the 2023 NEC from January 1, 2026. Some forms still say 2020, so confirm before you test.

Free questions with answers

Show all 10 free questions and answers
  1. Under the Article 100 definition, a load is a continuous load when the maximum current is expected to continue for at least how long?

    Answer: 3 hours or more

    Article 100 defines a continuous load as one whose maximum current is expected to continue for 3 hours or more. That is why 210.19(A)(1), 210.20(A) and 215.2(A)(1) apply the 125 percent factor to such loads. One and two hours are common wrong recollections; 8 hours is a shift length, not the Code threshold.

    Reference: NFPA 70, National Electrical Code, 2023, Article 100, Continuous Load

  2. A 480Y/277-volt panelboard has exposed live parts on its front. A grounded concrete wall is directly opposite across the working space. Using Table 110.26(A)(1), what is the minimum depth of working space?

    Answer: 3 ft 6 in. (1.0 m)

    The nominal voltage to ground is 277 V, which falls in the 151-600 volt row. Exposed live parts on one side and grounded parts (concrete counts as grounded) on the other is Condition 2, which is 3 ft 6 in. in that row. Three feet would be Condition 1; 4 ft is Condition 3 (live parts on both sides).

    Reference: NFPA 70, National Electrical Code, 2023, Table 110.26(A)(1)

  3. A 125-volt, 20-ampere receptacle is being installed in the laundry area of a dwelling unit. Which statement is correct under 210.8(A)?

    Answer: It requires GFCI protection because laundry areas are listed in 210.8(A)

    The 2023 NEC lists laundry areas in 210.8(A)(11) as a dwelling-unit location where all 125- through 250-volt receptacles on single-phase circuits of 150 volts or less to ground need GFCI protection. The 6 ft sink and tub rules are separate items in the list and do not limit the laundry item.

    Reference: NFPA 70, National Electrical Code, 2023, 210.8(A)(11)

  4. A 125-volt, 20-ampere, single-phase receptacle is installed on the roof of a commercial building to serve HVAC equipment. Under 210.8(B), what protection applies?

    Answer: GFCI protection for personnel, because rooftops are listed

    210.8(B) lists rooftops among the other-than-dwelling locations where 125- through 250-volt receptacles on single-phase branch circuits of 150 volts to ground or less and 50 amperes or less need GFCI protection. The roof does not have to be open to the public. 210.63 separately requires a service receptacle near rooftop HVAC equipment.

    Reference: NFPA 70, National Electrical Code, 2023, 210.8(B)(5)

  5. Rigid PVC conduit with feeder conductors is buried in a lawn at a commercial building, with no concrete cover and no special conditions. What is the minimum cover from the top of the conduit to finished grade?

    Answer: 18 in.

    Table 300.5(A), 'All locations not specified below' row, requires 18 in. for nonmetallic raceways listed for direct burial without concrete encasement (Column 3). Rigid metal conduit needs only 6 in. (Column 2), and direct-buried cables need 24 in. (Column 1). The 12 in. figure is for residential 120 V GFCI-protected circuits of 20 A or less.

    Reference: NFPA 70, National Electrical Code, 2023, Table 300.5(A), Column 3

  6. A 6 AWG copper THHN conductor (90 degree C ampacity 75 A in Table 310.16) runs in a mechanical room with an ambient temperature of 45 degrees C. Using Table 310.15(B)(1)(1), what is the corrected ampacity?

    Answer: 65.25 A

    In the 90 degree C column, the correction factor for 41-45 degrees C is 0.87: 75 A x 0.87 = 65.25 A. A 0.82 factor (61.5 A) is the 46-50 degree C row; 0.91 (68.3 A) is the 36-40 degree C row; 56.6 A applies 0.87 to the 75 degree C ampacity of 65 A, which is the wrong column when the starting point is 90 degrees C.

    Reference: NFPA 70, National Electrical Code, 2023, Table 310.15(B)(1)(1); Table 310.16

  7. A 15-ampere, 125-volt receptacle is installed outdoors in a location fully exposed to rain. Under 406.9(B)(1), what must its enclosure be?

    Answer: Weatherproof whether or not the attachment plug is inserted

    406.9(B)(1) requires 15- and 20-ampere, 125- and 250-volt receptacles in a wet location to have an enclosure that is weatherproof whether or not the plug is inserted (an in-use cover). The weatherproof-when-closed rule is for damp locations such as under a roofed porch in 406.9(A).

    Reference: NFPA 70, National Electrical Code, 2023, 406.9(B)(1)

  8. A single continuous-duty 15-hp, 460-volt, 3-phase squirrel-cage motor is on its own branch circuit. Table 430.250 gives a full-load current of 21 A. What is the minimum branch-circuit conductor ampacity under 430.22?

    Answer: 26.25 A

    430.22 requires branch-circuit conductors to the motor to have an ampacity of at least 125 percent of the table full-load current: 21 x 1.25 = 26.25 A. 21.0 A uses no multiplier, 23.1 A applies 110 percent, and 31.5 A applies 150 percent.

    Reference: NFPA 70, National Electrical Code, 2023, 430.22; Table 430.250

  9. In a new outdoor pool area, luminaires and ceiling-suspended fans over the pool or within 5 ft horizontally of its inside walls must be at least how far above the maximum water level?

    Answer: 12 ft (3.7 m)

    680.22(B)(1) requires luminaires, lighting outlets and ceiling-suspended (paddle) fans in new outdoor pool areas, over the pool or the area extending 1.5 m (5 ft) horizontally from its inside walls, to be at a height of not less than 3.7 m (12 ft) above the maximum water level.

    Reference: NFPA 70, National Electrical Code, 2023, 680.22(B)(1)

  10. A feeder supplies three 230-volt, 3-phase motors with Table 430.250 full-load currents of 28 A (10 hp), 22 A (7.5 hp) and 9.6 A (3 hp). What is the minimum feeder conductor ampacity under 430.24?

    Answer: 66.6 A

    430.24 requires 125 percent of the largest motor's FLC plus the FLCs of the others: (28 x 1.25) + 22 + 9.6 = 35 + 22 + 9.6 = 66.6 A. 59.6 A sums all three FLCs with no 125 percent factor, 74.5 A applies 125 percent to all three motors, and 57.0 A takes 125 percent of the largest motor plus only the 22 A motor, leaving out the 3 hp motor.

    Reference: NFPA 70, National Electrical Code, 2023, 430.24

Sources