Virginia licensing exam

Virginia LP Gasfitter Exam: Practice Test & Licensing Guide

The PSI exam for Virginia's LP gasfitter license: 50 open-book questions on natural and LP gas piping, pipe sizing, LP-gas tanks, controls, testing and the Board's rules.

Questions
50
Time limit
2.5 hours
Passing score
70%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10Standards of Practice

A regulant has only one trade designation on the license and submits a signed statement asking to delete it. What is the result?

Requirements at a glance

AgencyVirginia Department of Professional and Occupational Regulation (DPOR), Board for Contractors; exams by PSI
Experience4 years of experience plus 80 hours of school, or 5 years plus 40 hours (confirm in 18VAC50-30-39)
ExamLP gasfitter exam: 50 items, 150 minutes, 35 correct (journeyman) or 37 (master)
Books allowed2021 IFGC (Virginia Fuel Gas Code) and NFPA 58 (2014)
Fees$100 (journeyman) or $125 (master) to PSI; DPOR license fee separate

Installers of LP-gas piping and tanks applying to the Virginia Board for Contractors for an LP gasfitter license.

How to get licensed, step by step

  1. Check the education and experience rules

    You must be 18 and document training and work experience. The requirements depend on the license level; see 18VAC50-30-39.

    Virginia Administrative Code 18VAC50-30 (tradesman regulations) (opens in a new tab)Virginia DPOR: Tradesmen licensing (opens in a new tab)

  2. Apply to the Board for Contractors

    The Board reviews your application first and approves you to take the exam. Disclose any convictions.

    Virginia DPOR: Tradesmen licensing (opens in a new tab)

  3. Register and schedule the LP gasfitter exam with PSI

    After approval, pay PSI and book a seat. Your eligibility is good for one year and you can retake within that year.

    Schedule with PSI (Virginia DPOR exams) (opens in a new tab)

  4. Get licensed

    Send your passing result to the Board with the license fee ($150 for an original journeyman or master license; additional designations $105). Trade licenses run three years and need continuing education (3 hours per designation) on the current code edition.

    Virginia DPOR: Tradesmen licensing (opens in a new tab)Virginia Administrative Code 18VAC50-30 (tradesman regulations) (opens in a new tab)

How to prepare

  • Bring the editions on PSI's list: the 2020 NEC for electrical and the 2021 IPC, IMC and IFGC (Virginia Plumbing, Mechanical and Fuel Gas Codes) for plumbing, HVAC and gas. Virginia's 2024 code cycle (NEC 2023 and the 2024 I-codes) is tentatively set to take effect in October 2027; until PSI publishes a new bulletin, code questions use the 2021 USBC editions.
  • Exam fees may change: a rule effective 3/11/2026 raised the Board's exam fee caps, though DPOR still lists $100 for journeyman and $125 for master exams. Confirm the fee with PSI when you register.
  • Tab your books before exam day with permanent tabs. You can highlight, underline and index, but you can't write in them, use removable tabs or bring loose papers or study guides.
  • Ten items on every journeyman and master exam (nine on the residential exams) come from the Board's rules, 18VAC50-30. They are easy points if you read the regulation once.
  • The blueprint matches the gasfitter exam: piping (12), sizing (11), LP-gas tanks (9), controls (5) and testing (3).
  • Know NFPA 58 container siting, spacing and valve requirements for the tank questions.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the Virginia Fuel Gas Code and 18VAC50-30. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

Official reference list (as published by the testing agency)
  • International Fuel Gas Code (IFGC), 2021, with Virginia amendments (Virginia Fuel Gas Code); the 2018 edition was also accepted until 5/1/2025
  • NFPA 58, Liquefied Petroleum Gas Code, 2014
  • Board for Contractors Individual License and Certification Regulations (18VAC50-30)

What's on the exam

Official content outline from PSI Services (number of questions per topic):

TopicQuestions
Standards of Practice3
Standards of Conduct2
Renewal and Reinstatement2
Definitions1
Qualification for Licensure1
Revocation1
Natural and LP Gas Piping12
Pipe Sizing11
LP-Gas Tanks9
Gas Piping Controls5
Testing3

Exam day details

  • Administered by PSI Services for the Virginia Department of Professional and Occupational Regulation (DPOR), Board for Contractors.
  • Fee: $100 (journeyman) or $125 (master) to PSI per exam, not refundable or transferable and valid for one year. DPOR application and license fees are separate.
  • 50 items in 150 minutes. Passing score 35 (70%) at the journeyman level and 37 (74%) at the master level.
  • Eligibility for the LP gas fitter license is 4 years of experience plus 80 hours of school, or 5 years plus 40 hours (18VAC50-30-39; confirm the current rule).
  • LP-gas tank questions depend on NFPA 58 (2014); tab its container location and distance tables.
  • Open book: bring your own bound copies of the listed references. You may highlight, underline and index them beforehand and add permanent tabs, but removable tabs, loose papers, writing and study guides are not allowed.
  • PSI may add unscored experimental questions to the exam.
  • Exam fees may change: a rule effective 3/11/2026 raised the Board's exam fee caps, though DPOR still lists $100 (journeyman) and $125 (master). Confirm the fee with PSI when you register.
  • The Board for Contractors must approve your application first (education and experience); then you pay and register with PSI. Your exam eligibility is good for one year and you can retake within that year.
  • Every Virginia tradesman exam includes 10 items on the Board's rules (18VAC50-30): standards of practice, standards of conduct, renewal and reinstatement, definitions, qualification for licensure and revocation.

Note: These facts come from the PSI bulletin dated 1/14/2025; no newer bulletin was found. The 2021 Virginia USBC (NEC 2020 and the 2021 I-codes) is in force now. Virginia's 2024 code cycle (NEC 2023 and the 2024 I-codes) is tentatively scheduled to take effect in October 2027, and PSI will likely update its bulletin then; that date is not confirmed. Check the current PSI bulletin before you test. NFPA 58 (2014) is not freely readable, so questions on it were written from general knowledge and not checked against the text.

Frequently asked questions

How many questions are on the Virginia LP gasfitter exam?

50 items in 150 minutes. Ten cover the Board's rules (18VAC50-30) and the rest cover LP and natural gas piping, sizing, tanks, controls and testing.

Which books can I bring?

The 2021 IFGC (Virginia Fuel Gas Code) and NFPA 58 (2014).

What are the fees?

$100 for a journeyman-level exam and $125 for master level, paid to PSI. Fees may change, so confirm when you register.

Free questions with answers

Show all 10 free questions and answers
  1. A regulant has only one trade designation on the license and submits a signed statement asking to delete it. What is the result?

    Answer: The license is terminated

    Under 18VAC50-30-150 C a regulant deleting a designation must provide a signed statement listing it. If it is the only trade or level designation, deleting it terminates the license; there is no inactive status.

    Reference: Virginia Board for Contractors Individual License and Certification Regulations (18VAC50-30), 18VAC50-30-150 C

  2. Which experience and education combination qualifies an applicant to sit for the journeyman LP gas fitter exam?

    Answer: Four years of experience with 80 hours of formal vocational training

    18VAC50-30-39 C allows journeyman LP gas fitters either 80 hours of training with four years of experience, or 40 hours with five years. The two-, three- and six-year combinations are for other licenses.

    Reference: Virginia Board for Contractors Individual License and Certification Regulations (18VAC50-30), 18VAC50-30-39 C

  3. A licensed LP gas fitter keeps a customer's $600 deposit for a tank set but never starts the work. Which prohibited act is most directly involved?

    Answer: Abandonment, including keeping funds paid for work not performed

    18VAC50-30-190 (6) makes abandonment prohibited for LP gas fitters on jobs under $1,000, including retention or misapplication of funds paid for work not performed or performed only in part.

    Reference: Virginia Board for Contractors Individual License and Certification Regulations (18VAC50-30), 18VAC50-30-190 (6)

  4. What is the status of a regulant who reinstates a license after it lapsed?

    Answer: Regarded as continuously licensed, so the Board keeps disciplinary authority over the lapse

    18VAC50-30-140 B says a regulant who reinstates is regarded as continuously licensed, so the regulant remains under the Board's disciplinary authority throughout. Work during a lapse may also be unlicensed activity (18VAC50-30-130 E).

    Reference: Virginia Board for Contractors Individual License and Certification Regulations (18VAC50-30), 18VAC50-30-140 B

  5. Under 18VAC50-30-10, which work is included in gas fitting-related work?

    Answer: Installing, repairing or removing LP and natural gas piping, tanks and appliances

    The 18VAC50-30-10 definition of gas fitter includes installation, repair, improvement or removal of industrial gas, fuel gas, gaseous hydrogen, liquefied petroleum or natural gas piping, tanks, chimneys and vents, direct vents, equipment and appliances annexed to real property.

    Reference: Virginia Board for Contractors Individual License and Certification Regulations (18VAC50-30), 18VAC50-30-10 (D, Gas fitter)

  6. Which table is used to size Schedule 40 metallic pipe for undiluted propane between a second-stage (low-pressure) regulator and the appliances, at 11 in. w.c. inlet with a 0.5 in. w.c. drop?

    Answer: Table 402.4(28)

    Each propane table in the IFGC is headed with its inlet pressure, pressure drop and intended use. Table 402.4(28) is Schedule 40 pipe, undiluted propane, 11.0 in. w.c. inlet, 0.5 in. w.c. drop, for sizing between the single- or second-stage regulator and the appliance. Table 402.4(25) is the 10 psi first-stage to second-stage table and 402.4(27) is for 2 psi service.

    Reference: 2021 International Fuel Gas Code (Virginia Fuel Gas Code), Table 402.4(28)

  7. The IFGC covers LP-gas piping systems up to what operating pressure?

    Answer: 20 psig

    Section 301.1 lists LP-gas piping systems with an operating pressure of 20 psig or less within the code's scope (natural gas systems up to 125 psig). The 5 psig figure is the Section 402.7 limit inside buildings.

    Reference: 2021 International Fuel Gas Code (Virginia Fuel Gas Code), Section 301.1

  8. How deep must underground gas piping normally be buried under Section 404.12?

    Answer: At least 12 inches below grade

    Section 404.12 sets a minimum depth of 12 inches below grade. Section 404.12.1 allows individual lines to outdoor lights, grills and other outdoor appliances at 8 inches where approved and not exposed to physical damage.

    Reference: 2021 International Fuel Gas Code (Virginia Fuel Gas Code), Section 404.12

  9. An MP regulator is connected to rigid piping. Under Section 410.2, where must unions be placed?

    Answer: Within 1 foot of either side of the regulator

    Section 410.2 requires, where the MP regulator is connected to rigid piping, a union within 1 foot of either side of the regulator, so the regulator can be removed for service.

    Reference: 2021 International Fuel Gas Code (Virginia Fuel Gas Code), Section 410.2

  10. Which test medium is prohibited for pressure-testing gas piping under Section 406.2?

    Answer: Oxygen

    Section 406.2 allows air, nitrogen, carbon dioxide or an inert gas as the test medium and says oxygen shall not be used.

    Reference: 2021 International Fuel Gas Code (Virginia Fuel Gas Code), Section 406.2

Sources