Requirements at a glance
| Agency | South Carolina Department of Labor, Licensing and Regulation (LLR), Residential Builders Commission; exams by PSI |
|---|---|
| Experience | Residential builder: at least 1 year of experience under a licensed builder or equivalent approved by the Commission (S.C. Code 40-59-220). Licensed specialty contractors (HVAC, plumbing, electrical): 1 year of Commission-approved experience under the supervision of a licensee in the trade |
| Exams | Residential Builder: 110 questions, 6 hours, 70%, plus Business Management and Law for Residential Builders |
| Books allowed | IRC 2021 or 2024 (SC), Carpentry and Building Construction, ACI Contractor's Guide, Modern Masonry and others on PSI's list |
| Fees | PSI exam fees ($78 for one portion, $98 for both with the builder exam), plus the Commission's application and license fees and a bond |
Applicants for a South Carolina residential builder license from the Residential Builders Commission, for one-, two- or multi-family residences up to three stories and 16 units.
Official links
How to get licensed, step by step
Apply to the Commission
Apply to the Residential Builders Commission first. Eligibility is valid for 1 year.
SC Residential Builders Commission (LLR) (opens in a new tab)S.C. Code Title 40 Chapter 59 (residential builders) (opens in a new tab)
Schedule Business and Law and the Residential Builder exam with PSI
You must pass both portions within 12 months and get 3 attempts in that period. After three failures you wait twelve months.
Schedule with PSI (residential builders) (opens in a new tab)
Get licensed
After you pass both portions, send the Commission your results, the license fee and your bond. The residential builder bond is $15,000 (S.C. Code 40-59-220).
SC Residential Builders Commission (LLR) (opens in a new tab)
How to prepare
- Code editions are changing. From November 1, 2026 PSI accepts the 2021 or the 2024 South Carolina codes (ICC codes with state modifications) and the 2023 or the 2020 NEC. After July 1, 2027 only the 2024 codes and the 2023 NEC. Bring one edition you know well and expect questions that read the same in both.
- Tab your books before exam day: highlighting, underlining and permanent tabs are allowed, but sticky notes and writing during the exam are not.
- General building construction is 74 of 110 questions: carpentry, concrete and reinforcement, estimating and plan reading, masonry, roofing and foundations.
- Residential electrical, HVAC and plumbing are 12 questions each. Tab the matching IRC chapters (electrical, mechanical, fuel gas and plumbing).
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below, and most questions come from the SC IRC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
International Residential Code (IRC), 2021 or 2024 edition with South Carolina modificationsEssential
On PSI's list. The code book for the residential builder exam, including its electrical, mechanical and plumbing chapters.
ICC store (opens in a new tab)Read free (UpCodes) (opens in a new tab)
29 CFR Part 1926 (OSHA construction regulations)
On PSI's list for the building, electrical, plumbing and HVAC exams. Safety questions.
Official reference list (as published by the testing agency)
- International Residential Code (IRC), 2021 or 2024 edition with South Carolina modifications
- Carpentry and Building Construction; ACI Contractor's Guide, 3rd Edition; Modern Masonry; BCSI 2013; Gypsum Construction Handbook, 7th Edition (all on PSI's list)
What's on the exam
Official content outline from PSI Services (number of questions per topic):
| Topic | Questions | |
|---|---|---|
| General Building Construction | 74 | |
| Residential Electrical | 12 | |
| Residential HVAC | 12 | |
| Residential Plumbing | 12 |
Exam day details
- Administered by PSI Services for the South Carolina Department of Labor, Licensing and Regulation (Residential Builders Commission).
- Fee: $78 to PSI for the trade portion alone, or $98 for both portions (business and law plus Residential Builder). Board application and license fees are separate.
- 110 scored questions plus 1 to 10 unscored experimental items (they count against your time) in 360 minutes; 77 correct (70%) to pass.
- General building construction covers general carpentry, concrete and reinforcement, estimating and plan reading, masonry, roofing, and site work, footings and foundations.
- Scope on PSI's outline: construction, remodeling, repair or improvement of one-, two- or multi-family residences up to three stories and 16 units in any single apartment building.
- Code editions: from November 1, 2026 PSI accepts the 2021 or 2024 South Carolina codes (NEC 2023 or 2020); after July 1, 2027 only the 2024 codes and the 2023 NEC. Our questions are written to be correct under both.
- Open book: bring the references on PSI's list. You may highlight, underline and add permanent tabs; sticky notes and removable tabs are not allowed.
- Apply to the Residential Builders Commission first. Eligibility is valid for 1 year and you get 3 attempts within 12 months; you must pass Business Management and Law and the trade portion within that 12 months.
- After three failures you wait twelve months from the last attempt before testing again.
Frequently asked questions
What's on the South Carolina residential builder exam?
110 scored questions: General Building Construction 74, residential electrical 12, residential hvac 12, residential plumbing 12.
How is the Residential Builder exam split?
110 scored questions: general building construction 74, and 12 each on residential electrical, residential HVAC and residential plumbing.
How long do I have?
6 hours. You need 77 correct (70%).
Free questions with answers
Show all 10 free questions and answers
Without special approval, what is the maximum depth of compacted earth fill that may be placed under a slab-on-ground inside the foundation walls?
Answer: 8 inches
Fill under a slab must be vegetation-free and compacted to give uniform support, and the fill depth may not exceed 24 inches for clean sand or gravel or 8 inches for earth unless approved. The 24-inch limit applies only to clean sand or gravel. In the 2024 IRC the fill requirement is R506.3.1.
Reference: 2021 International Residential Code (South Carolina); 2024 edition R506.3.1, R506.2.1
A footing designer asks for the smallest concrete strip footing the IRC allows regardless of soil bearing capacity. Which size is the code floor for width and thickness?
Answer: 12 inches wide and 6 inches thick
R403.1.1 requires concrete footings to be sized by the tables for soil bearing and number of stories, but never less than 12 inches in width and 6 inches in depth, with projections of at least 2 inches that do not exceed the footing thickness.
Reference: 2021 and 2024 International Residential Code (South Carolina), R403.1.1
A plumber must bore a hole through a nominal 2x10 floor joist (actual depth 9 1/4 inches) away from any notch. What is the largest hole diameter the IRC permits, and how close may it be to the top or bottom edge?
Answer: About 3 inches in diameter, no closer than 2 inches to the edge
R502.8.1 limits a bored hole to one-third of the joist depth (9.25 / 3 = 3.08 inches, so about 3 inches) and requires at least 2 inches between the hole and the top or bottom of the member or any other hole. One-half of the depth (4.6 inches) is not allowed.
Reference: 2021 and 2024 International Residential Code (South Carolina), R502.8.1
How many 20-ampere small-appliance branch circuits must serve the kitchen, dining and pantry receptacles of a new dwelling?
Answer: At least two
E3703.2 requires a minimum of two 20-ampere branch circuits for the receptacle outlets covered by E3901.3 (kitchen, pantry, breakfast and dining areas). Those circuits may serve no other outlets except those allowed by the section, and each adds 1,500 VA to the feeder load calculation.
Reference: 2021 and 2024 International Residential Code (South Carolina), Part VIII Electrical, E3703.2
Along the floor line of a living room wall space, receptacles must be placed so that no point is farther than what distance from a receptacle outlet?
Answer: 6 feet
E3901.2.1 requires receptacles so that no point measured horizontally along the floor line of any wall space is more than 6 feet from an outlet, which in practice means outlets no more than 12 feet apart. Wall space begins at 2 feet in width.
Reference: 2021 and 2024 International Residential Code (South Carolina), Part VIII Electrical, E3901.2.1
What is the minimum ampacity of the ungrounded service conductors for a new one-family dwelling?
Answer: 100 amperes, 3-wire
E3602.1 requires the ungrounded service conductors of a one-family dwelling to have an ampacity of not less than 100 amperes, 3-wire. Smaller services are limited to certain other installations (E3602.2.1).
Reference: 2021 and 2024 International Residential Code (South Carolina), Part VIII Electrical, E3602.1
A furnace is installed in an attic. What is the minimum size of the unobstructed passageway to the appliance, and what is its normal maximum length?
Answer: 30 inches high by 22 inches wide, up to 20 feet long
M1305.1.2 requires a clear passageway at least 30 inches high and 22 inches wide, not more than 20 feet long (50 feet if the passage is at least 6 feet high and 22 inches wide), with continuous solid flooring at least 24 inches wide and a level service space at the appliance.
Reference: 2021 and 2024 International Residential Code (South Carolina), mechanical and fuel gas chapters, M1305.1.2
A chimney serving a fireplace passes through a flat roof, and a wall of the same building rises 5 feet from that roof 8 feet away from the chimney. What chimney termination rule applies?
Answer: At least 3 feet above the roof penetration and at least 2 feet higher than anything within 10 feet
R1003.9 requires a chimney to extend at least 3 feet above the highest point where it passes through the roof and at least 2 feet higher than any portion of the building within 10 feet (the 3-2-10 rule). The wall 8 feet away is inside the 10-foot circle, so the chimney must be 2 feet above that wall's top as well.
Reference: 2021 and 2024 International Residential Code (South Carolina), mechanical and fuel gas chapters, R1003.9
A horizontal 4-inch building drain is 40 feet long and runs at the minimum slope allowed. What is the minimum total drop over the 40 feet?
Answer: 5 inches
P3005.3 requires at least 1/4 inch per foot for piping 2 1/2 inches and smaller and 1/8 inch per foot for 3 inches and larger. A 4-inch drain needs 1/8 inch per foot: 40 x 0.125 = 5 inches. Using 1/4 inch per foot gives 10 inches, which is the slope for smaller pipe.
Reference: 2021 and 2024 International Residential Code (South Carolina), plumbing chapters, P3005.3
A kitchen sink with a 1 1/2-inch trap is set on a trap arm sloped 1/4 inch per foot. What is the maximum developed length from the trap weir to the vent?
Answer: 6 feet
Table P3105.1 gives the maximum developed length from trap weir to vent by trap size: a 1 1/2-inch trap at 1/4 inch per foot is limited to 6 feet. The 5-foot figure is for a 1 1/4-inch trap, 8 feet for a 2-inch trap and 12 feet for a 3-inch trap at 1/8 inch per foot.
Reference: 2021 and 2024 International Residential Code (South Carolina), plumbing chapters, Table P3105.1
Sources
- PSI: South Carolina Residential Builders Commission Candidate Information Bulletin (updated 11/1/2026) (opens in a new tab)
- South Carolina Residential Builders Commission (LLR) (opens in a new tab)
- South Carolina Code of Laws Title 40 Chapter 59 (residential builders) (opens in a new tab)
Questions last verified November 16, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.