Oklahoma licensing exam

Oklahoma Residential Plumbing Journeyman and Natural Gas Exam: Practice Test & Licensing Guide

The PSI exam for an Oklahoma residential plumbing journeyman license: 85 scored questions on the plumbing and fuel gas chapters of the International Residential Code with Oklahoma revisions. Open book, 70% to pass from November 1, 2026.

Questions
85
Time limit
3 hours
Passing score
70%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10Vents

A vent terminates through the wall of a house at a point 6 feet horizontally from an openable window. What is the minimum height of the vent opening above the top of that window?

Requirements at a glance

AgencyOklahoma Construction Industries Board (CIB); exams by PSI
ExperienceResidential plumbing experience (hours not stated in the bulletin; see the CIB)
Exam85 scored questions, 3 hours, 70% (60)
Books allowedIRC (2018 or 2024 with Oklahoma revisions), Mathematics for Plumbers and Pipefitters 8th ed., 29 CFR 1926
Fee$92 to PSI per exam portion (non-refundable), plus CIB application and license fees
Retest30 days after a fail; 90 days after each later fail (electrical is always 30)

Plumbers applying to the Oklahoma Construction Industries Board for a residential plumbing journeyman license. The Residential Plumbing Contractor and Natural Gas exam uses the same blueprint and references.

How to get licensed, step by step

  1. Register and log your hours

    Register with the CIB as an apprentice and log your hours under a licensed contractor (1 year is 2,000 hours). Have your employer's affidavits notarized.

    Oklahoma Construction Industries Board (CIB) (opens in a new tab)

  2. Apply to the CIB

    Send the CIB your application and notarized experience affidavits. When it approves you, you receive an Ok Con ID.

    Oklahoma Construction Industries Board (CIB) (opens in a new tab)

  3. Schedule with PSI

    Book your exam with PSI online or at (855) 834-8750. Contractor applicants also take the Business and Law portion.

    Schedule with PSI (Oklahoma contractor exams) (opens in a new tab)PSI: Oklahoma CIB Candidate Information Bulletin (effective 9/11/2026) (opens in a new tab)

  4. Pass and get licensed

    After you pass, send the CIB your results and license fee to receive your license.

    Oklahoma Construction Industries Board (CIB) (opens in a new tab)

How to prepare

  • All Oklahoma trade exams are open book, so the skill is finding answers fast: bound books, permanent tabs only, highlighting allowed, no writing.
  • Bring a silent, non-programmable calculator. The exam adds up to 10 unscored experimental questions that count against your time.
  • Vents (13) is the biggest section: tab the IRC plumbing vent chapter and the drain sizing tables.
  • Fuel gas (10) comes from the IRC fuel gas chapter (Chapter 24): tab pipe sizing tables and the testing rules.
  • The Residential Plumbing Contractor exam has the same blueprint; contractors add Plumbing Business and Law.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the IRC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

  • International Residential Code (IRC) with Oklahoma revisionsEssential

    The bulletin allows the 2018 or 2024 edition; 2024 only after 12/14/2026. Plumbing and fuel gas chapters are tested.

    ICC store (opens in a new tab)Read free (UpCodes) (opens in a new tab)

  • Mathematics for Plumbers and Pipefitters, Lee Smith, 8th Edition

    Allowed in the exam room; useful for offsets, pipe volumes and sizing.

Official reference list (as published by the testing agency)
  • International Residential Code for One- and Two-Family Dwellings, 2018 or 2024 edition, with Oklahoma revisions
  • Mathematics for Plumbers and Pipefitters, Lee Smith, 8th Edition
  • 29 CFR Part 1926 (OSHA construction), or PSI's selections

What's on the exam

Official content outline from PSI Services (number of questions per topic):

TopicQuestions
General Plumbing Knowledge and Regulations10
Piping, Valves, and Control Valves8
Fixtures and Equipment8
Water Supply10
Drains and Sewers10
Vents13
Traps, Interceptors, Indirect, and Special Waste5
Isometric Analysis7
Fuel Gas10
Safety4

Exam day details

  • Administered by PSI Services for the Oklahoma Construction Industries Board (CIB).
  • Fee: $92 to PSI per exam portion, non-refundable. CIB application and license fees are separate.
  • 85 scored questions in 3 hours (180 minutes); 60 correct (70%) to pass. Before November 1, 2026 the pass mark was 75% (64).
  • Edition note: the bulletin allows the 2018 or 2024 IRC with Oklahoma revisions. The 2024 code may be used from 9/14/2026 and the 2018 code is no longer allowed as of 12/14/2026 (the CIB notice says 2024 only from 12/15/2026). Our questions follow the 2024 IRC with Oklahoma amendments.
  • If you fail, wait 30 days to retest; after each later failure the wait is 90 days.
  • Open book: bring your own bound copies of the allowed references. You may highlight, underline and index them beforehand with permanent tabs only; no writing and no sticky notes.
  • PSI may add up to 10 unscored experimental questions, which count against your time. A silent, non-printing, non-programmable calculator is allowed.
  • The CIB must approve your application first (you receive an Ok Con ID) before you can schedule with PSI.

Frequently asked questions

What's on the Oklahoma residential plumbing journeyman exam?

85 scored questions: vents 13, general plumbing knowledge, water supply, drains and sewers and fuel gas 10 each, piping and valves and fixtures and equipment 8 each, isometric analysis 7, traps and interceptors 5 and safety 4.

Is the residential plumbing contractor exam different?

The blueprint and references are the same; contractors also pass Plumbing Business and Law.

Which IRC edition can I bring?

The 2018 or 2024 IRC with Oklahoma revisions until December 14, 2026; after that only the 2024 edition.

Free questions with answers

Show all 10 free questions and answers
  1. A vent terminates through the wall of a house at a point 6 feet horizontally from an openable window. What is the minimum height of the vent opening above the top of that window?

    Answer: 3 feet

    P3103.5 prohibits a vent terminal within 10 feet horizontally of a door, openable window or air intake unless it is at least 3 feet above the top of the opening. It also may not be less than 4 feet directly beneath such an opening. The 4-foot figure is the below-the-opening rule, not the above-the-opening rule.

    Reference: 2024 International Residential Code, P3103.5

  2. A required cleanout is to be placed in a crawl space. The height from the crawl space floor to the nearest obstruction along the path from the opening to the cleanout is 20 inches. How does the code treat that location?

    Answer: It is concealed, so the cleanout cannot be installed there

    P3005.2.10 prohibits required cleanouts in concealed locations and lists crawl spaces where that height is less than 24 inches as concealed. At 20 inches the space fails, so the cleanout must be moved or the route made accessible. Clearance in front of the opening (P3005.2.9) is a separate requirement.

    Reference: 2024 International Residential Code, P3005.2.10

  3. What is the maximum vertical distance from a fixture outlet to the weir of its trap?

    Answer: 24 inches

    P3201.6 limits the vertical distance from the fixture outlet to the trap weir to 24 inches and the horizontal distance, centerline of outlet to centerline of trap inlet, to 30 inches. 30 inches is the horizontal limit.

    Reference: 2024 International Residential Code, P3201.6

  4. Individual gas lines serving outdoor grills and lights may be buried at what minimum depth, provided the installation is approved and not subject to physical damage?

    Answer: 8 inches below finished grade

    G2415.12.1 allows individual lines to outdoor lights, grills and other appliances to be installed not less than 8 inches below finished grade where approved and located where physical damage is unlikely. The general 18-inch depth applies to all other underground piping.

    Reference: 2024 International Residential Code, G2415.12.1

  5. A lavatory faucet has an effective opening of 1/2 inch or less and is away from any wall. What is the minimum air gap above the flood level rim?

    Answer: 1 inch

    Table P2902.3.1 gives 1 inch for lavatories and fixtures with effective openings of 1/2 inch or less when away from a wall, and 1.5 inches when close to a wall. 2 inches applies to over-rim bath fillers away from a wall.

    Reference: 2024 International Residential Code, Table P2902.3.1

  6. Which fixture is NOT required to have a shutoff valve on its water supply pipe?

    Answer: A bathtub

    P2903.10.3 requires shutoff valves on each fixture supply and each plumbing appliance supply except for bathtubs and showers. Valves must be accessible.

    Reference: 2024 International Residential Code, P2903.10.3

  7. What are the minimum interior area and minimum dimension of a shower compartment (without the exception)?

    Answer: 900 square inches and 30 inches

    P2708.1 requires at least 900 square inches of cross-sectional area and a minimum dimension of 30 inches, measured at the top of the threshold, up to 70 inches above the drain. The exception allows 25 inches only if the area is at least 1,300 square inches.

    Reference: 2024 International Residential Code, P2708.1

  8. Before a drainage system may be covered or concealed, what must have happened?

    Answer: It must have been tested, inspected and approved by the building official

    P2503.2 states a plumbing or drainage system, or part of it, shall not be covered, concealed or put into use until it has been tested, inspected and approved by the building official. Photographs or manufacturer sign-off do not replace the official's approval.

    Reference: 2024 International Residential Code, P2503.2

  9. A riser diagram shows a vertical drain stack serving two full bath groups with 1.6 gpf water closets (2 baths), one kitchen group and one laundry group. What is the smallest stack size allowed?

    Answer: 3 inches

    Table P3004.1 gives 2 baths = 8 d.f.u., kitchen group = 2 and laundry group = 3, so the stack carries 8 + 2 + 3 = 13 d.f.u. In Table P3005.4.1 a 2-1/2 inch stack would hold 20 d.f.u., but footnote b prohibits water closets on sizes below 3 inches. The smallest stack that can carry the closets is 3 inches (48 d.f.u.).

    Reference: 2024 International Residential Code, Table P3004.1 and Table P3005.4.1

  10. A trench is 5 feet deep. What is the maximum lateral travel allowed to reach a ladder, stairway or ramp?

    Answer: 25 feet

    29 CFR 1926.651(c)(2) requires a stairway, ladder, ramp or other safe means of egress in trench excavations 4 feet or more in depth so that employees need no more than 25 feet of lateral travel. The 5-foot depth is not the limit that matters here, because the rule starts at 4 feet.

    Reference: 29 CFR Part 1926, 1926.651(c)(2)

Sources