New Mexico licensing exam

New Mexico EE-98 Electrical Contractor Exam: Practice Test & Licensing Guide

New Mexico's EE-98 residential and commercial electrical contractor exam, three parts: commercial and industrial code (80), residential (40) and specialties such as low voltage, signs and sound (50). Open book, 75% on each part.

Questions
170
Time limit
7.25 hours
Passing score
75% per part

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10General Knowledge and Electrical Installation Requirements

A 480Y/277-volt panelboard is installed on one wall of an electrical room. The opposite wall is bare concrete, which is treated as a grounded surface, and there are no exposed live parts on that wall. What minimum depth of clear working space is required in front of the panelboard?

Requirements at a glance

AgencyNew Mexico Regulation and Licensing Department, Construction Industries Division (CID); exams by PSI
ExamPart 1: 80 questions, 200 minutes. Part 2: 40, 100 minutes. Part 3: 50, 135 minutes. 75% on each part, open book
Books allowedNEC 2020 (or NEC Handbook) and New Mexico Electrical Code NMAC 14.10.4 (2020); NFPA 72 (2010) for Part 3
FeesExam fees are paid to PSI (see the exam details above); license fees are separate. Check CID for current license fees.
TimingTest within 6 months of becoming eligible. The exam fee and a passing score are each valid for 1 year.

Electrical contractors applying to Construction Industries Division for an EE-98 license. You must pass all three parts; if you fail one, you retake only that part.

How to get licensed, step by step

  1. Apply to CID through PSI

    Candidates must be pre-approved before they can schedule. Submit your application and proof of qualifications through PSI's New Mexico construction page, or call PSI's approvals line at 877-663-9267.

    PSI: apply and schedule New Mexico exams (opens in a new tab)New Mexico Construction Industries Division (CID) (opens in a new tab)

  2. Get your references

    Buy the exact code editions in PSI's bulletin. Books must be bound; highlighting, underlining and permanent tabs are allowed, but no loose notes or Post-its.

    PSI Contractor Candidate Information Bulletin (opens in a new tab)New Mexico Administrative Code (NMAC) titles (opens in a new tab)

  3. Schedule and pay PSI

    After approval, contact PSI to schedule a seat and pay. Test sites include Albuquerque, Farmington, Las Cruces, Roswell and Santa Fe.

    PSI: apply and schedule New Mexico exams (opens in a new tab)

  4. Pass and finish your license

    You need 75%. You may not take the same exam more than twice in 30 days. Contractors also need the Business and Law exam; journeyman candidates take a hands-on practical exam too.

    New Mexico Construction Industries Division (CID) (opens in a new tab)PSI Contractor Candidate Information Bulletin (opens in a new tab)

How to prepare

  • New Mexico tests the 2020 NEC. Do not study from a 2023 NEC; some rules changed between editions.
  • Part 3 is specialties: low voltage and alarms (20), telephone and computer systems (10) and sound and communication systems (10). Tab NEC Chapters 7 and 8 and NFPA 72.
  • Each part has 4 to 8 New Mexico State Code questions, so tab NMAC 14.10.4 as well.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the 2020 NEC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

Official reference list (as published by the testing agency)
  • NFPA 70: National Electrical Code (NEC), 2020 edition, or the NEC Handbook
  • New Mexico Electrical Code (NMAC 14.10.4), 2020
  • NFPA 72: National Fire Alarm Code, 2010 (Part 3)

What's on the exam

Official content outline from PSI, (number of questions per topic):

TopicQuestions
General Knowledge and Electrical Installation Requirements20
Services, Feeders, and Branch Circuits18
Overcurrent Protection8
Grounding and Bonding14
Conductors and Cables12
Raceways and Boxes12
Hazardous Locations, Special Occupancies, and Special Equipment13
Lighting, Signs, and General-Use Equipment9
Motors, Transformers, and Generators6
New Mexico State Code8
Low Voltage, including Alarms20
Electrical Signs and Outline Lighting5
Cathodic Protection and Lightning Protection Systems5
Telephone and Computer Systems10
Sound and Communication Systems10

The parts are timed and scored separately, and you must pass each one. Our simulations score each part the same way and give you the combined time (435 minutes).

Exam day details

  • Administered by PSI, for the New Mexico Regulation and Licensing Department, Construction Industries Division (CID).
  • Fee: $269.06 for the three-part exam, paid to PSI (retake of one part $89.69). License and application fees are separate.
  • Part 1 is 80 questions in 200 minutes, Part 2 is 40 in 100 minutes and Part 3 is 50 in 135 minutes. 75% to pass each part.
  • Open book. Bring bound references; you may highlight, underline and index them with permanent tabs only. No loose papers, notes or Post-it tabs, and no writing in the books.
  • New Mexico tests the 2020 NEC plus NMAC 14.10.4, not the 2023 NEC. Rules that changed in 2023 can give a wrong answer here.
  • Get CID pre-approval through PSI first (PSI approvals line 877-663-9267). Once you are eligible you must test within 6 months, or reapply with the Division. Your exam fee is valid for 1 year and a passing score is valid for 1 year.
  • You may not take the same exam more than twice in a 30-day period; after two fails you must wait 30 days from your first attempt.
  • You also need the Business and Law exam. Part 2 topics (residential general knowledge, services, grounding and so on) are merged into the matching code sections in our practice mix.

Frequently asked questions

What's on the New Mexico EE-98 exam?

PSI's outlines combined, 170 questions across three parts: General Knowledge and Electrical Installation Requirements 20; Services, Feeders, and Branch Circuits 18; Overcurrent Protection 8; Grounding and Bonding 14; Conductors and Cables 12; Raceways and Boxes 12; Hazardous Locations, Special Occupancies, and Special Equipment 13; Lighting, Signs, and General-Use Equipment 9; Motors, Transformers, and Generators 6; New Mexico State Code 8; Low Voltage, including Alarms 20; Electrical Signs and Outline Lighting 5; Cathodic Protection and Lightning Protection Systems 5; Telephone and Computer Systems 10; Sound and Communication Systems 10.

Which NEC edition do I bring to the New Mexico electrical exam?

The 2020 NEC (or the NEC Handbook) plus the New Mexico Electrical Code, NMAC 14.10.4 (2020). Part 3 also lists NFPA 72 (2010). Do not rely on 2023 NEC changes.

Who gives the New Mexico contractor and journeyman exams?

PSI, for the Construction Industries Division (CID) of the Regulation and Licensing Department. CID pre-approves your application, then you schedule with PSI at a New Mexico test center (Albuquerque, Farmington, Las Cruces, Roswell or Santa Fe) or an approved center elsewhere.

Free questions with answers

Show all 10 free questions and answers
  1. A 480Y/277-volt panelboard is installed on one wall of an electrical room. The opposite wall is bare concrete, which is treated as a grounded surface, and there are no exposed live parts on that wall. What minimum depth of clear working space is required in front of the panelboard?

    Answer: 3 1/2 ft (1.07 m)

    This is a 151 to 600 volt-to-ground system (277 V) with exposed live parts on one side and a grounded surface on the other, which is Condition 2 in Table 110.26(A)(1). Condition 2 at that voltage requires 3 1/2 ft. 3 ft is the Condition 1 value at that voltage (and the 0-150 V value), and 4 ft is Condition 3 (live parts on both sides).

    Reference: NFPA 70, National Electrical Code, 2020, Table 110.26(A)(1)

  2. How many switches or circuit breakers may be grouped to serve as the service disconnecting means for one service?

    Answer: No more than six

    230.71(A) allows the service disconnecting means for each service to consist of not more than six switches or six circuit breakers mounted in a single enclosure, in a group of separate enclosures or in or on a switchboard. This is the six-handle rule.

    Reference: NFPA 70, National Electrical Code, 2020, 230.71(A)

  3. Using Table 250.66, what is the minimum size copper grounding electrode conductor for a service with 3/0 AWG copper ungrounded service-entrance conductors, where the conductor goes to a made electrode other than a single rod and no concrete-encased electrode is used?

    Answer: 4 AWG

    Table 250.66 lists 4 AWG copper for service-entrance conductors of 2/0 or 3/0 copper. 6 AWG is for 1 or 1/0, 8 AWG is for 2 AWG or smaller, and 2 AWG is for over 3/0 through 350 kcmil.

    Reference: NFPA 70, National Electrical Code, 2020, Table 250.66

  4. Using the 75 degree C column of Table 310.16, what is the ampacity of a 3 AWG copper conductor?

    Answer: 100 A

    The 75 C column of Table 310.16 in the 2020 NEC lists 100 A for 3 AWG copper. 85 A is the 60 C value for the same size, 115 A is the 90 C value, and 130 A belongs to 1 AWG at 75 C.

    Reference: NFPA 70, National Electrical Code, 2020, Table 310.16

  5. A 120-volt, 20-ampere, GFCI-protected dwelling branch circuit is wired with Type UF cable that is directly buried. What is the minimum cover?

    Answer: 12 in.

    Table 300.5 Column 4 allows 12 in. cover for residential branch circuits rated 120 V or less with GFCI protection and maximum overcurrent protection of 20 A. Direct-buried cable without those conditions needs 24 in. (Column 1).

    Reference: NFPA 70, National Electrical Code, 2020, Table 300.5

  6. Gasoline vapor is classified in which Class I group?

    Answer: Group D

    Section 500.6(A) lists gasoline, propane, butane, methane and natural gas among Group D materials. Group A is acetylene, Group B includes hydrogen, and Group C includes ethylene.

    Reference: NFPA 70, National Electrical Code, 2020, 500.6(A)

  7. Cord-connected luminaires, hanging luminaires, chain-, cable- or cord-suspended luminaires and ceiling paddle fans may not be located within what zone around a bathtub?

    Answer: Within 3 ft horizontally and 8 ft vertically of the tub rim

    410.10(D) prohibits these luminaires and fans in the zone measured 900 mm (3 ft) horizontally and 2.5 m (8 ft) vertically from the top of the bathtub rim or shower stall threshold. The zone extends to the ceiling in the same space.

    Reference: NFPA 70, National Electrical Code, 2020, 410.10(D)

  8. Which listed cable type is required for Class 2 wiring installed in an air-handling plenum when no raceway is used?

    Answer: CL2P

    725.154 and 300.22(C) require cables in plenum spaces to be plenum rated: CL2P or CL3P (or in a metal raceway). CL2R is riser rated, CL2 is general purpose and CL2X is limited use (dwellings and raceways).

    Reference: NFPA 70, National Electrical Code, 2020, 725.154

  9. What is the minimum copper size of the grounding conductor for a TV receiving antenna mast?

    Answer: 10 AWG copper

    810.21 states that copper antenna mast and discharge unit grounding conductors shall not be smaller than 10 AWG (aluminum 8 AWG and copper-clad steel 17 AWG). The grounding conductor may be bare or insulated.

    Reference: NFPA 70, National Electrical Code, 2020, 810.21(H)

  10. An information technology equipment room in a commercial building is treated under Article 645. Which disconnecting means is required?

    Answer: One that disconnects all IT equipment and HVAC, at the exit doors

    645.10(A) requires a disconnecting means to disconnect power to all electronic equipment in the IT equipment room or zone, and the HVAC systems serving it, grouped and identified and installed at the principal exit doors. A critical operations data system has an exception in 645.10(B).

    Reference: NFPA 70, National Electrical Code, 2020, 645.10(A)

Sources

Questions last verified November 2, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.