Requirements at a glance
| Agency | New Hampshire Mechanical Safety and Licensing Board (OPLC); exam by Prov |
|---|---|
| Exam | 100 questions drawn from a pool of 300, 200 minutes, 70% to pass; not listed as open book |
| What a pass does | Bypasses year 1 of plumbing apprenticeship related instruction; your sponsor decides whether to accept it |
| Approval | New approval from your licensing authority before each attempt; 30-day wait after a fail |
| Fees | $90 to Prov |
Plumbing apprentices who already know the content taught in year 1 of plumbing related instruction in New Hampshire Department of Education classes and want to go straight to year 2. Prov says a pass bypasses year 1 of apprenticeship related instruction. Your registered apprenticeship sponsor decides whether to accept the result in place of year 1, and you need new approval from your licensing authority before each attempt.
Official links
- New Hampshire Mechanical Safety and Licensing Board (OPLC) (opens in a new tab)
- Prov: New Hampshire Mechanical Board (Gas & Plumbing) Candidate Information Bulletin (opens in a new tab)
- Schedule with Prov (opens in a new tab)
- RSA 153:27-38 (Mechanical Safety and Licensing Board) (opens in a new tab)
- Mec 100-600 (Mechanical Licensing Board rules) (opens in a new tab)
How to get licensed, step by step
Talk to your sponsor
Ask your registered apprenticeship sponsor whether they will accept a pass in place of year 1 related instruction.
New Hampshire Mechanical Safety and Licensing Board (OPLC) (opens in a new tab)
Get approved
The Mechanical Board must approve you before each attempt and pass your registration to Prov.
New Hampshire Mechanical Safety and Licensing Board (OPLC) (opens in a new tab)Mec 100-600 (Mechanical Licensing Board rules) (opens in a new tab)
Schedule with Prov
After the board pre-approves you, book at provexam.com/scheduler (New Hampshire centers, or remote through Examroom). There is no waiting period between attempts. You can reschedule free up to 3 days ahead.
Schedule with Prov (opens in a new tab)Prov: New Hampshire Mechanical Board (Gas & Plumbing) Candidate Information Bulletin (opens in a new tab)
Report the result
Prov sends your result to the board. Give it to your sponsor so year 1 instruction can be recorded as bypassed.
New Hampshire Mechanical Safety and Licensing Board (OPLC) (opens in a new tab)
How to prepare
- Prov prints no topic list. Our practice topics follow the year-1 related-instruction outline (safety, math, tools, drawings, pipes and fittings, DWV and water supply basics); the grouping is ours, not Prov's.
- Pipes and fittings is the largest year-1 block in that outline, so spend the most time on materials, joints and fittings.
- A testing-agency page for this exam describes it as closed book, but the Prov bulletin does not say. Confirm before test day.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
What to study
This is a closed-book exam, so nothing comes into the exam room. Study from these:
Official reference list (as published by the testing agency)
What's on the exam
Estimated topic weighting. No official breakdown is published:
| Topic | Questions | |
|---|---|---|
| Intro to Plumbing and Core Craft Skills | 14 | |
| Plumbing Safety | 14 | |
| Plumbing Math | 10 | |
| Plumbing Tools | 8 | |
| Blueprints and Plumbing Drawings | 9 | |
| Pipes and Fittings by Material | 29 | |
| Drain, Waste and Vent (DWV) Basics | 8 | |
| Water Supply, Fixtures and Faucets | 8 |
Exam day details
- Administered by Prov, Inc. for the New Hampshire Office of Professional Licensure and Certification.
- Fee: $90 to Prov.
- 100 questions in 200 minutes, randomly drawn from a pool of 300 year-1 questions; 70 correct (70%) to pass.
- The Prov bulletin does not list this exam as open book and names no reference book.
- Prov prints no topic breakdown. The eight topics and weights on this page are our own grouping, based on the year-1 related-instruction outline in a registered plumber apprenticeship standard and the subjects the Mechanical Board names (math, safety, fittings, tools, core plumbing practices). They are not Prov's.
- The Mechanical Board must approve you before each attempt. If you do not pass, wait 30 days before retesting.
Note: Prov prints no blueprint for this exam, so the topics and weights are our estimate from year-1 related-instruction outlines. Confirm acceptance with your apprenticeship sponsor and the Mechanical Board.
Frequently asked questions
What does the bypass test do?
Prov says a passing score of 70% bypasses year 1 of apprenticeship related instruction. It tests the content generally taught in year 1 New Hampshire Department of Education plumbing classes. Your sponsor decides whether to accept it in place of year 1.
What topics are covered?
Prov does not print a blueprint. Its sample is 100 questions drawn from 300 year-1 questions. Our practice topics (safety, math, tools, drawings, pipes and fittings, DWV and water supply basics) are our own grouping.
Can I retake it?
Yes, after 30 days, and you need a new approval from your licensing authority before each attempt.
Free questions with answers
Show all 10 free questions and answers
Who must inspect an excavation, the adjacent area and its protective systems for signs of cave-in or hazardous atmospheres, and how often?
Answer: A competent person, daily and as needed through the shift
29 CFR 1926.651(k)(1) requires daily inspections by a competent person before work begins and as needed throughout the shift, and again after rain or other hazard-increasing events. A weekly check, or a one-time check before digging, is not enough.
Reference: OSHA 29 CFR Part 1926, 1926.651(k)(1)
A cylindrical storage tank is 24 inches in diameter and 36 inches tall. About how many gallons does it hold? (1 gallon = 231 cubic inches.)
Answer: About 70.5 gallons
Radius = 24 / 2 = 12 in. Volume = pi x 12 x 12 x 36 = 16,286 cu in. 16,286 / 231 = 70.5 gal. Multiplying diameter by radius instead of squaring the radius gives 141 gal; halving the answer gives 35.3 gal, and using a 6-inch radius gives 17.6 gal.
Reference: Plumbing trade math (worked calculation), Arithmetic shown in explanation
Which ASTM standard covers copper water tube in Types K, L and M, as listed for water distribution pipe in the plumbing code?
Answer: ASTM B88
Table 605.4 lists copper or copper-alloy tubing (Type K, WK, L, WL, M or WM) under ASTM B75, B88, B251 and B447, and B88 is the one for water tube. A53 is galvanized steel pipe, D2661 is ABS drain pipe and F876 is PEX tubing.
Reference: 2018 International Plumbing Code, Table 605.4
IPC Table 702.1 lists copper tubing for above-ground drainage and vent pipe. Which ASTM standard is copper Type DWV tube itself made to?
Answer: ASTM B306
Table 702.1 lists copper or copper-alloy tubing (Type K, L, M or DWV) under ASTM B75, B88, B251 and B306. Of those, B306 is the specification for seamless copper drainage tube (Type DWV); B88 covers the pressure-rated water tube Types K, L and M. ASTM A74 is cast-iron soil pipe and F441 is CPVC pipe.
Reference: 2018 International Plumbing Code; Mueller Streamline copper tube data sheet, Table 702.1; Key Specifications (DWV made to ASTM B306)
A pipe that carries sewage containing fecal matter to the building drain is called a:
Answer: Soil pipe
A soil pipe carries sewage containing fecal matter to the building drain or building sewer. A waste pipe carries only waste (no fecal matter), such as from a sink, and a vent pipe moves air, not liquid.
Reference: 2018 International Plumbing Code, Section 202, Definitions: Soil Pipe; Waste Pipe
A cleanout is installed in a drain line so that:
Answer: Blockages can be reached and removed
The code defines a cleanout as an access opening in the drainage system used for the removal of obstructions; it may be a removable plug or cap or a removable fixture or trap.
Reference: 2018 International Plumbing Code, Section 202, Definitions: Cleanout
After cutting copper tube with a tubing cutter, what tool removes the burr on the inside of the cut end?
Answer: A reamer
The code requires cut tube ends to be reamed to the full inside diameter before soldering (Section 705.6.3). A reamer or the reaming blade on a tubing cutter removes the inside burr; a flaring tool belongs to flared joints.
Reference: 2018 International Plumbing Code, Section 705.6.3
On a print, a reducing tee is labeled 3 x 3 x 2. Following the fitting size convention, which opening is the 2-inch one?
Answer: The outlet (branch)
For tees the size order is the largest run opening first, the opposite run opening second and the outlet last. In 3 x 3 x 2 the two run openings are 3 inch and the branch outlet is 2 inch.
Reference: US Navy, NAVEDTRA 14040 Blueprint Reading and Sketching (Plumbing prints), Plumbing prints, fitting designations
How must vent and branch vent pipes be graded?
Answer: So they drain back to the drainage pipe by gravity
Section 905.2 requires vent and branch vent pipes to be graded and connected so that they drain back to the drainage pipe by gravity, so condensation or water in the vent does not collect and block it.
Reference: 2018 International Plumbing Code, Section 905.2
What is the minimum fixture supply pipe size for a water closet with a flushometer valve?
Answer: 1 inch
Table 604.5 requires 1 inch for a flushometer-valve water closet, while flush-tank water closets can use 3/8 inch. A flushometer needs a large flow in a short time. 3/4 inch is for a flushometer-valve urinal.
Reference: 2018 International Plumbing Code, Table 604.5
Sources
- Prov: New Hampshire Mechanical Board (Gas & Plumbing) Candidate Information Bulletin (opens in a new tab)
- New Hampshire Mechanical Safety and Licensing Board (OPLC) (opens in a new tab)
- RSA 153:27-38 (Mechanical Safety and Licensing Board) (opens in a new tab)
- First Year Plumbing Apprentice Bypass Testing Policy and Procedures (NH Gasfitters, testing agency page) (opens in a new tab)
- Plumber registered apprenticeship standard, related instruction outline (ApprenticeshipStandards.org) (opens in a new tab)
Questions last verified November 17, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.