Requirements at a glance
| Agency | New Hampshire Mechanical Safety and Licensing Board (OPLC); exam by Prov |
|---|---|
| Exam | 100 questions, 3 hours, open book, 75% to pass |
| Experience | New Hampshire journeyman license held at least 6 months (Mec 305.01(a)) |
| Books allowed | 2018 IPC; Purpose and Scope of Administrative Rules of the Board |
| Fees | $90 to Prov; initial 2-year license fee is $330 (Plc 1002.25) |
Plumbers applying to the New Hampshire Mechanical Safety and Licensing Board for a master license. You need a New Hampshire journeyman license held for at least 6 months before the board approves you to test (Mec 305.01(a)).
Official links
- New Hampshire Mechanical Safety and Licensing Board (OPLC) (opens in a new tab)
- Prov: New Hampshire Mechanical Board (Gas & Plumbing) Candidate Information Bulletin (opens in a new tab)
- Schedule with Prov (opens in a new tab)
- RSA 153:27-38 (Mechanical Safety and Licensing Board) (opens in a new tab)
- Mec 100-600 (Mechanical Licensing Board rules) (opens in a new tab)
How to get licensed, step by step
Qualify with the board
Hold a New Hampshire journeyman plumber license for at least 6 months and apply to the Mechanical Safety and Licensing Board.
New Hampshire Mechanical Safety and Licensing Board (OPLC) (opens in a new tab)Mec 100-600 (Mechanical Licensing Board rules) (opens in a new tab)
Get pre-approved
The board must approve you and pass your registration to Prov before you can schedule.
New Hampshire Mechanical Safety and Licensing Board (OPLC) (opens in a new tab)
Schedule with Prov
After the board pre-approves you, book at provexam.com/scheduler (New Hampshire centers, or remote through Examroom). There is no waiting period between attempts. You can reschedule free up to 3 days ahead.
Schedule with Prov (opens in a new tab)Prov: New Hampshire Mechanical Board (Gas & Plumbing) Candidate Information Bulletin (opens in a new tab)
Get licensed
Prov sends your result to the board, which issues the license.
New Hampshire Mechanical Safety and Licensing Board (OPLC) (opens in a new tab)
How to prepare
- You need 75%, higher than the journeyman exam. Scope and administration (15) draws on IPC Chapter 1 and the board's rules.
- Calculations, venting and drainage are 15 questions each.
- New Hampshire's building code now adopts the 2024 IPC, but the Prov bulletin still lists the 2018 IPC. Study the edition the bulletin names.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below, and most questions come from the 2018 IPC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
2018 International Plumbing Code (IPC), ICCEssential
Allowed in the exam room. Nearly all of the plumber exams come from it.
ICC (opens in a new tab)Read free (ICC codes) (opens in a new tab)
Official reference list (as published by the testing agency)
- International Plumbing Code 2018, ICC (open book)
- Purpose and Scope of Administrative Rules of the Board (open book)
What's on the exam
Official content outline from Prov, Inc. (number of questions per topic):
| Topic | Questions | |
|---|---|---|
| Plumbing Fundamentals (Master) | 10 | |
| Scope and Administration (Master) | 15 | |
| Calculations (Master) | 15 | |
| Traps and Interceptors (Master) | 10 | |
| Venting Requirements (Master) | 15 | |
| Drainage Requirements (Master) | 15 | |
| Water Distribution (Master) | 10 | |
| Fixtures and Faucets (Master) | 10 |
Exam day details
- Administered by Prov, Inc. for the New Hampshire Office of Professional Licensure and Certification.
- Fee: $90 to Prov. Board application and license fees are separate.
- 100 questions in 3 hours; 75 correct (75%) to pass.
- Open book: the references above are permitted in the exam room.
- The Mechanical Board must pre-approve you; Prov then lets you schedule at a New Hampshire test center or remotely through Examroom.
- There is no required waiting period between attempts. You can reschedule free up to 3 days before your appointment.
Note: New Hampshire's building code (RSA 155-A:1) now adopts the 2024 IPC, but the Prov bulletin still lists the 2018 IPC for this exam. We follow the printed bulletin. Check the current bulletin before your test date.
Frequently asked questions
What's on the New Hampshire master plumber exam?
100 questions: scope and administration 15, calculations 15, venting 15, drainage 15, plumbing fundamentals 10, traps and interceptors 10, water distribution 10 and fixtures and faucets 10.
What score do I need?
75%, which is higher than the 70% for the journeyman exam.
Which plumbing code is on the exam?
Prov's bulletin lists the 2018 International Plumbing Code, even though the state building code now adopts the 2024 IPC. Check the current bulletin before you buy a book.
Free questions with answers
Show all 10 free questions and answers
A candidate applies to the board for initial master plumber licensure. Under Mec 305.01(a), which combination of requirements applies?
Answer: A New Hampshire journeyman license held at least 6 months, and a passing score of at least 75% on the master exam
Mec 305.01(a)(2) (formerly Saf-Mec 305.01, readopted eff 2-13-26) requires that the applicant has held a New Hampshire journeyman plumber license for at least 6 months, and (a)(4) requires answering at least 75% of the master exam questions correctly. The 70% figure is the journeyman pass mark in 305.01(b)(4)c, which is why the 6-month, 70% option is wrong.
Reference: Mec 305, New Hampshire Code of Administrative Rules, Mec 305.01(a)(2) and (a)(4)
How many consecutive terms may a member of the New Hampshire Mechanical Licensing Board be appointed to, and how long is each term?
Answer: Terms are 3 years and a member may not serve more than 2 consecutive terms
RSA 153:27-a provides for 3-year terms continuing until a successor is appointed, staggered for the initial members, and no member may be appointed to more than 2 consecutive terms. Board rule Mec 103.01(b) repeats it.
Reference: NH RSA 153:27-153:36, RSA 153:27-a; Mec 103.01(b)
What range of liquid seal depth must each fixture trap have under the 2018 IPC, excluding special designs for accessible fixtures?
Answer: At least 2 inches and not more than 4 inches
Section 1002.4 requires a liquid seal of not less than 2 inches and not more than 4 inches, or deeper for special designs relating to accessible fixtures. A seal under 2 inches is easily lost to siphonage or evaporation, and one over 4 inches slows scouring.
Reference: 2018 International Plumbing Code, Section 1002.4
A dry vent connects to a horizontal drain pipe. Where on the pipe must the vent connection be made under the 2018 IPC?
Answer: Above the centerline of the horizontal drain pipe
Section 905.3 requires every dry vent connecting to a horizontal drain to connect above the centerline of the drain pipe, which keeps waste from flowing into the vent and plugging it.
Reference: 2018 International Plumbing Code, Section 905.3
A building drain run has a first change of horizontal direction greater than 45 degrees, and a second one 30 feet of developed length farther along. Under Section 708.1.4 of the 2018 IPC, what is required?
Answer: One cleanout at the first change, which also serves the second change within 40 feet of developed length
Section 708.1.4 requires a cleanout at a change of horizontal direction greater than 45 degrees. Where more than one such change occurs within 40 feet of developed length, the cleanout installed for the first change serves as the cleanout for all changes within that 40 feet.
Reference: 2018 International Plumbing Code, Section 708.1.4
Under Section 305.4 of the 2018 IPC, exterior water supply piping must be installed at least how far below the frost line and below grade?
Answer: 6 inches below the frost line and 12 inches below grade
Section 305.4 says exterior water supply piping shall be installed not less than 6 inches below the frost line and not less than 12 inches below grade, and that pipes in attics, crawl spaces or outside walls must be protected from freezing by insulation, heat or both.
Reference: 2018 International Plumbing Code, Section 305.4
Where a water service pipe and a building sewer share a trench and the sewer pipe is not one of the Table 702.2 materials, what horizontal separation does the 2018 IPC require?
Answer: 5 feet of undisturbed or compacted earth
Section 603.2 requires 5 feet of undisturbed or compacted earth horizontal separation where the building sewer is not made of a material listed in Table 702.2. If the sewer is a Table 702.2 material, the two pipes may share a trench.
Reference: 2018 International Plumbing Code, Section 603.2
A public coin-operated laundry has several automatic washers in one room. What does Section 413.4 of the 2018 IPC require for floor drains?
Answer: Floor drains located to drain the entire floor, with outlets of not less than 3 inches
Section 413.4 requires rooms containing automatic clothes washers in public coin-operated laundries and in central washing facilities of multiple-family dwellings to have floor drains located to readily drain the entire floor, with outlets of not less than 3 inches in diameter.
Reference: 2018 International Plumbing Code, Section 413.4
A fixture branch serves a domestic kitchen sink with a food waste disposer, a residential automatic clothes washer, a lavatory and a floor drain. Using Table 709.1 of the 2018 IPC, what is the total drainage fixture unit load?
Answer: 7 dfu
From Table 709.1: kitchen sink with disposer, dishwasher or both = 2, residential automatic clothes washer = 2, lavatory = 1, floor drain = 2. The total is 2 + 2 + 1 + 2 = 7 dfu. Counting the lavatory as 2 gives 8, and adding the disposer as an extra fixture gives 9.
Reference: 2018 International Plumbing Code, Table 709.1
A horizontal branch in a public toilet room serves 3 public water closets (1.6 gpf), 3 lavatories, 1 service sink and 1 floor drain. Using Tables 709.1 and 710.1(2) of the 2018 IPC, what is the minimum size of the horizontal branch?
Answer: 3 inches
Table 709.1: public water closet (1.6 gpf) = 4 dfu each, lavatory = 1, service sink = 2, floor drain = 2. Total = 3 x 4 + 3 x 1 + 2 + 2 = 19 dfu. Table 710.1(2) allows 12 dfu on a 2-1/2 inch horizontal branch and 20 dfu on a 3-inch horizontal branch, so 3 inches is the smallest size that carries 19 dfu (and water closets need at least 3 inches).
Reference: 2018 International Plumbing Code, Tables 709.1, 710.1(2)
Sources
- Prov: New Hampshire Mechanical Board (Gas & Plumbing) Candidate Information Bulletin (opens in a new tab)
- New Hampshire Mechanical Safety and Licensing Board (OPLC) (opens in a new tab)
- RSA 153:27-38 (Mechanical Safety and Licensing Board) (opens in a new tab)
Questions last verified November 17, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.