Nebraska Residential Journeyman Electrician Exam: Practice Test & Licensing Guide

The PSI exam for a Nebraska residential journeyman electrician license: about 50 questions on the NEC, theory and the State Electrical Act. Open book.

Questions
50
Time limit
2.5 hours
Passing score
75%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10Wiring and Protection

A 1,800 sq ft house is supplied by a 120/240-V single-phase service. Using the optional method of 220.82, find the calculated load in amperes. The house has 3 VA/sq ft lighting, two small-appliance circuits and one laundry circuit at 1,500 VA each, an 8-kW range, a 5-kW dryer, a 4.5-kW water heater, a 1-kW dishwasher and a 4-kVA air conditioner. Heat is by gas.

Requirements at a glance

AgencyNebraska State Electrical Division and State Electrical Board; exams by PSI
Experience3 years or 6,000 hours as a registered apprentice
ExamReported at 50 questions; time and pass mark not published
Books allowedNEC (or NEC Handbook) with tabs and Ugly's Electrical References; confirm the list with PSI
FeesAbout $120 to PSI (valid 90 days), plus the Division's application and license fees (see the Division's fee schedule)

Electricians applying to the Nebraska State Electrical Division for a residential journeyman license after 3 years or 6,000 hours as a registered apprentice.

How to get licensed, step by step

  1. Apply to the Division

    Send the State Electrical Division your exam and licensing application. It sends your eligibility to PSI.

    Division: exam information and licensing applications (opens in a new tab)Nebraska State Electrical Division (opens in a new tab)

  2. Schedule with PSI

    PSI emails you a scheduling link. Test sites are Grand Island, Lincoln, Norfolk, North Platte, Omaha, Scottsbluff and Sidney; there is no home testing.

    Division: PSI exam information (opens in a new tab)

  3. Pass the exam

    The exam is open book. After 3 attempts (270 days) you sit out 90 days, and you can test at most 3 times a year.

    Division: PSI exam information (opens in a new tab)

  4. Get licensed and renew

    Passing awards 6 hours of continuing education. The 2026 renewal window ran 10/1 to 12/31 and requires continuing education.

    Nebraska State Electrical Division (opens in a new tab)

How to prepare

  • Nebraska adopted the 2023 NEC on August 1, 2024, and the Division's exam scope lists the 2023 NEC. PSI's Nebraska bulletin was not available to us, so confirm the allowed edition and reference list in your PSI scheduling email.
  • Study the State Electrical Act, basic electricity theory and emergency circuits including fire alarm along with the NEC. Tab Articles 100, 110, 210, 220, 230, 240, 250, 310 and 430 and the Chapter 9 tables.
  • Each approval to test is good for 90 days, and a new application is needed for each attempt (Policy 37). Book your PSI slot soon after approval.
  • Focus on the dwelling-unit articles: 210, 220 Part III, 230, 250, the 300-series wiring methods and 406.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the NEC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

Official reference list (as published by the testing agency)
  • NFPA 70: National Electrical Code (NEC) or the NEC Handbook, 2020 or 2023 edition (allowed in the exam room; Nebraska adopted the 2023 NEC on 8/1/2024)
  • Ugly's Electrical References (allowed in the exam room)

What's on the exam

Estimated topic weighting. No official breakdown is published:

TopicQuestions
General Electrical Knowledge10
Wiring and Protection20
Wiring Methods and Materials15
Equipment for General Use15
Special Occupancies10
Special Equipment5
Special Conditions5

Exam day details

  • Administered by PSI Services for the Nebraska State Electrical Division.
  • Fee: $120 to PSI, valid 90 days. Division application and license fees are separate.
  • Reported at 50 questions; the time limit and pass mark are not published.
  • The Division's exam scope is the 2023 NEC, basic electricity theory, the Nebraska State Electrical Act and emergency circuits including fire alarm.
  • Open book: bring your own NEC with tabs. Confirm the allowed edition and reference list in your PSI scheduling email.
  • You apply to the State Electrical Division first. It sends your eligibility to PSI, and PSI emails you a scheduling link. There is no home testing; test sites are Grand Island, Lincoln, Norfolk, North Platte, Omaha, Scottsbluff and Sidney.
  • Each approval to test is good for 90 days. After 3 attempts (270 days) you sit out 90 days, and you can test at most 3 times a year. A new exam application is needed for each attempt (Policy 37, 7/11/2025).
  • Passing awards 6 hours of continuing education credit.

Note: PSI's Nebraska candidate bulletin is not public, so the question count, time, pass mark and topic split for this exam are unverified. Confirm them with the State Electrical Division or in your PSI scheduling email.

Frequently asked questions

What's on the Nebraska residential electrician exam?

The NEC, basic electricity theory, the Nebraska State Electrical Act and emergency circuits including fire alarm. No residential outline is published, so our topic split follows the journeyman exam and is an estimate.

What is the residential license called?

Nebraska's Policy 36 calls it Residential Wireman; the Division's exam pages call it Residential Journeyman.

Free questions with answers

Show all 10 free questions and answers
  1. A 1,800 sq ft house is supplied by a 120/240-V single-phase service. Using the optional method of 220.82, find the calculated load in amperes. The house has 3 VA/sq ft lighting, two small-appliance circuits and one laundry circuit at 1,500 VA each, an 8-kW range, a 5-kW dryer, a 4.5-kW water heater, a 1-kW dishwasher and a 4-kVA air conditioner. Heat is by gas.

    Answer: 89.0 A

    General loads: lighting 1,800 x 3 = 5,400 VA; small-appliance and laundry 3 x 1,500 = 4,500 VA; nameplate appliances 8,000 + 5,000 + 4,500 + 1,000 = 18,500 VA; total 28,400 VA. Apply 220.82(B): first 10,000 VA at 100% plus the remaining 18,400 x 40% = 7,360 VA gives 17,360 VA. Add the 4,000-VA air conditioner at 100% under 220.82(C): 21,360 VA / 240 V = 89.0 A. 72.3 A omits the air conditioner, 79.0 A runs it through the 40% factor, and 135.0 A applies no demand factor at all.

    Reference: NFPA 70, National Electrical Code, 2023, Section 220.82(B) and (C)

  2. Type NM cable is run exposed along the side of a basement joist. Under 334.30, what are the maximum distance from a box to the first securing point and the maximum spacing between securing points?

    Answer: 12 in from the box, then every 4 1/2 ft

    Section 334.30 requires NM cable to be secured within 12 in of every box, cabinet or fitting and at intervals not exceeding 4 1/2 ft. 3 ft and 10 ft are not the NM intervals; 10 ft is the EMT support interval in 358.30.

    Reference: NFPA 70, National Electrical Code, 2023, Section 334.30

  3. A metal device box has internal cable clamps and holds one duplex receptacle. Three 14/2 NM cables with ground enter it. Using Table 314.16(B)(1) (2.0 cubic in. per 14 AWG conductor), what is the minimum box volume required?

    Answer: 20.0 cubic in.

    Count the allowances: six insulated 14 AWG conductors = 6 x 2.0 = 12.0; all equipment grounding conductors together = 1 x 2.0 = 2.0; internal clamps (one allowance) = 2.0; the receptacle yoke = 2 x 2.0 = 4.0. The total is 20.0 cubic in. 18.0 omits the clamps, 16.0 omits both the grounds and clamps, and 24.0 counts each of the three grounds separately.

    Reference: NFPA 70, National Electrical Code, 2023, Section 314.16(B); Table 314.16(B)(1)

  4. A kitchen has a wall countertop space. What is the minimum width of a wall countertop space that must have a receptacle outlet under 210.52(C)(1)?

    Answer: 12 in

    Section 210.52(C)(1) requires a receptacle outlet at each wall countertop space that is 12 in or wider. The outlets are then placed so that no point along the wall line is more than 24 in from a receptacle. 24 in is the spacing distance, not the minimum width that triggers the rule.

    Reference: NFPA 70, National Electrical Code, 2023, Section 210.52(C)(1)

  5. A one-family dwelling has an attached garage with three vehicle bays. What is the minimum number of receptacle outlets required in the garage by 210.52(G)(1)?

    Answer: Three

    Section 210.52(G)(1) requires at least one receptacle outlet for each car space in an attached garage (and in a detached garage with electric power), mounted no more than 5 1/2 ft above the floor. Three car spaces need at least three receptacles. One outlet for the whole garage was the older rule.

    Reference: NFPA 70, National Electrical Code, 2023, Section 210.52(G)(1)

  6. A temporary power pole at a house under construction has 125-volt, 20-ampere receptacles that the framing crew plugs saws into. These receptacles are not part of the permanent wiring. What does 590.6(A)(1) require for them?

    Answer: Ground-fault circuit-interrupter protection for personnel on every one of them

    Section 590.6(A)(1) requires GFCI protection for personnel on all 125-volt, single-phase, 15-, 20- and 30-ampere receptacle outlets that are not part of the permanent wiring and are in use by personnel. The assured equipment grounding conductor program is allowed only in industrial establishments with qualified personnel (590.6(A) exception), not at a house under construction. AFCI protection does not substitute for GFCI here.

    Reference: NFPA 70, National Electrical Code, 2023, Section 590.6(A)(1)

  7. At a dwelling with a permanently installed in-ground pool, where must the required 125-volt, 15- or 20-ampere general-purpose receptacle be located under 680.22(A)(1)?

    Answer: Between 6 ft and 20 ft from the inside wall of the pool, and not more than 6 1/2 ft above grade

    Section 680.22(A)(1) requires at least one 125-volt, 15- or 20-ampere receptacle on a general-purpose branch circuit, located at least 6 ft and not more than 20 ft from the inside wall of the pool, and not more than 6 1/2 ft above the floor, platform or grade. Receptacles within 20 ft of the pool also need GFCI protection under 680.22(A)(4).

    Reference: NFPA 70, National Electrical Code, 2023, Section 680.22(A)(1)

  8. When normal power is lost, how quickly must an emergency system under Article 700 have power available?

    Answer: Within the time the application requires, not to exceed 10 seconds

    Section 700.12 requires an emergency supply to make power available within the time required for the application, but not more than 10 seconds. The 60-second limit is for legally required standby systems under 701.12.

    Reference: NFPA 70, National Electrical Code, 2023, Section 700.12

  9. A 240-volt electric baseboard heater has a resistance of 48 ohms. How much current does it draw?

    Answer: 5 amperes

    Ohm's law gives I = E / R = 240 / 48 = 5 A. 11,520 results from multiplying volts by ohms, and 10 A would come from using 480 V.

    Reference: Electrical theory (Ohm's law and power relationships), Ohm's law: I = E / R

  10. A 120-volt circuit carries 20 A to a load 75 ft away (one way) on 12 AWG copper (6,530 circular mils). Using K = 12.9 ohm-cmil/ft, what is the approximate voltage drop as a percentage of 120 V?

    Answer: 4.9%

    Single-phase voltage drop is VD = 2 x K x I x L / CM = 2 x 12.9 x 20 x 75 / 6,530 = 5.93 V. As a percentage, 5.93 / 120 = 4.94%, about 4.9%. 2.5% uses the one-way length only, 5.9% treats the volts as a percent, and 9.9% doubles the result.

    Reference: Electrical theory (Ohm's law and power relationships), Voltage drop: VD = 2KIL / CM (Chapter 9, Table 8 values)

Sources

Questions last verified November 6, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.