Requirements at a glance
| Agency | Nebraska State Electrical Division and State Electrical Board; exams by PSI |
|---|---|
| Experience | 4 years or 8,000 hours as a registered apprentice with an electrical contractor (1 year of credit for a 2-year electrical associate degree); under 4,000 hours in Nebraska gives a Restricted license |
| Exam | About 80 scored questions, 4 hours, 75% |
| Books allowed | NEC (or NEC Handbook) with tabs and Ugly's Electrical References; confirm the list with PSI |
| Fees | About $120 to PSI (valid 90 days), plus the Division's $90 application and a $37.50 (even year) or $75 (odd year) license fee |
Electricians applying to the Nebraska State Electrical Division for a journeyman license after 4 years or 8,000 hours as a registered apprentice (1 year of credit for a 2-year electrical associate degree).
Official links
How to get licensed, step by step
Apply to the Division
Send the State Electrical Division your exam and licensing application. It sends your eligibility to PSI.
Division: exam information and licensing applications (opens in a new tab)Nebraska State Electrical Division (opens in a new tab)
Schedule with PSI
PSI emails you a scheduling link. Test sites are Grand Island, Lincoln, Norfolk, North Platte, Omaha, Scottsbluff and Sidney; there is no home testing.
Pass the exam
The exam is open book. After 3 attempts (270 days) you sit out 90 days, and you can test at most 3 times a year.
Get licensed and renew
Passing awards 6 hours of continuing education. The 2026 renewal window ran 10/1 to 12/31 and requires continuing education.
How to prepare
- Nebraska adopted the 2023 NEC on August 1, 2024, and the Division's exam scope lists the 2023 NEC. PSI's Nebraska bulletin was not available to us, so confirm the allowed edition and reference list in your PSI scheduling email.
- Study the State Electrical Act, basic electricity theory and emergency circuits including fire alarm along with the NEC. Tab Articles 100, 110, 210, 220, 230, 240, 250, 310 and 430 and the Chapter 9 tables.
- Each approval to test is good for 90 days, and a new application is needed for each attempt (Policy 37). Book your PSI slot soon after approval.
- Wiring and protection (20) and wiring methods and materials (15) lead the reported topic list: practice conductor sizing, overcurrent protection and grounding.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below, and most questions come from the NEC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
NFPA 70: National Electrical Code (NEC), 2023 EditionEssential
Open book, tabs allowed. Nebraska adopted the 2023 NEC on August 1, 2024. Confirm the allowed edition with PSI.
NFPA store (opens in a new tab)Free online access (opens in a new tab)
Ugly's Electrical References
Reported as allowed. Formulas for voltage drop, power, motors and load calculations.
Official reference list (as published by the testing agency)
- NFPA 70: National Electrical Code (NEC) or the NEC Handbook, 2020 or 2023 edition (allowed in the exam room; Nebraska adopted the 2023 NEC on 8/1/2024)
- Ugly's Electrical References (allowed in the exam room)
What's on the exam
Estimated topic weighting. No official breakdown is published:
| Topic | Questions | |
|---|---|---|
| General Electrical Knowledge | 10 | |
| Wiring and Protection | 20 | |
| Wiring Methods and Materials | 15 | |
| Equipment for General Use | 15 | |
| Special Occupancies | 10 | |
| Special Equipment | 5 | |
| Special Conditions | 5 |
Exam day details
- Administered by PSI Services for the Nebraska State Electrical Division.
- Fee: $120 to PSI, valid 90 days. Division application and license fees are separate.
- 80 scored questions (plus 5 to 10 unscored pretest items) in 4 hours; 60 correct (75%) to pass.
- The Division's exam scope is the 2023 NEC, basic electricity theory, the Nebraska State Electrical Act and emergency circuits including fire alarm.
- Open book: bring your own NEC with tabs. Confirm the allowed edition and reference list in your PSI scheduling email.
- You apply to the State Electrical Division first. It sends your eligibility to PSI, and PSI emails you a scheduling link. There is no home testing; test sites are Grand Island, Lincoln, Norfolk, North Platte, Omaha, Scottsbluff and Sidney.
- Each approval to test is good for 90 days. After 3 attempts (270 days) you sit out 90 days, and you can test at most 3 times a year. A new exam application is needed for each attempt (Policy 37, 7/11/2025).
- Passing awards 6 hours of continuing education credit.
Note: PSI's Nebraska candidate bulletin is not public, so the question count, time, pass mark and topic split for this exam are unverified. Confirm them with the State Electrical Division or in your PSI scheduling email.
Frequently asked questions
What's on the Nebraska journeyman electrician exam?
About 80 scored questions: wiring and protection 20, wiring methods and materials 15, equipment for general use 15, general electrical knowledge 10, special occupancies 10, special equipment 5 and special conditions 5. This split comes from a prep-site summary of the PSI bulletin and is unverified.
Which NEC edition does Nebraska use?
Nebraska adopted the 2023 NEC on August 1, 2024. The Division's exam scope lists the 2023 NEC.
How do I schedule the exam?
Apply to the State Electrical Division first. It sends your eligibility to PSI, and PSI emails you a scheduling link.
Free questions with answers
Show all 10 free questions and answers
A feeder's conductors have an adjusted ampacity of 230 A, and the feeder serves a calculated load of 200 A with no multiple receptacle cord-and-plug loads. Under the next-size-up rule, what is the largest standard overcurrent device the NEC permits for these conductors?
Answer: 250 A
Section 240.4(B) permits the next higher standard rating when the conductor ampacity does not match a standard size and the device is 800 A or less. 230 A is not a standard size in 240.6(A), so the next standard rating, 250 A, is permitted. 225 A is the next size down, which is also allowed but is not the maximum, and 300 A skips a standard size.
Reference: NFPA 70, National Electrical Code, 2023, 240.4(B) and 240.6(A)
A metal device box holds one single-pole switch (one yoke), two 12/2 NM cables with ground (four insulated 12 AWG conductors and two bare 12 AWG EGCs) and no internal cable clamps. Using 314.16(B) and 2.25 cubic inches per 12 AWG conductor, what minimum box volume is required?
Answer: 15.75 cubic inches
Count the volumes: 4 insulated conductors = 4, all EGCs together = 1, the switch yoke = 2 (a device counts twice). The total is 7 volumes: 7 x 2.25 = 15.75 cubic inches. 13.50 (6 volumes) leaves out the EGC allowance, 18.00 (8) adds a clamp allowance that does not apply here, and 20.25 (9) counts each EGC separately.
Reference: NFPA 70, National Electrical Code, 2023, 314.16(B) and Table 314.16(B)
Type AC cable is run exposed along a basement joist. Besides within 12 in. of each box, it must be secured at intervals of no more than what distance under 320.30(B)?
Answer: 4-1/2 ft
Section 320.30(B) requires AC cable to be secured within 300 mm (12 in.) of every outlet box, junction box, cabinet or fitting and at intervals not exceeding 1.4 m (4-1/2 ft). 6 ft is the MC cable interval and 10 ft is the EMT interval.
Reference: NFPA 70, National Electrical Code, 2023, 320.30(B)
A fixed storage-type water heater of 80 gallons is rated 4,000 W at 240 V. Under 422.13, what minimum ampacity must its branch circuit have?
Answer: 20.8 A
Section 422.13 treats a fixed storage-type water heater of 120 gallons or less as a continuous load, so the circuit must be at least 125% of the heater's current. I = P / E = 4,000 / 240 = 16.67 A, and 16.67 x 1.25 = 20.8 A. 16.7 A omits the 125% factor, 25.0 A uses 150%, and 41.7 A comes from dividing by 120 V.
Reference: NFPA 70, National Electrical Code, 2023, 422.13
A single 9,600 W, 240-volt fixed electric space heater is supplied by its own individual branch circuit. Under 424.4(B), what is the minimum branch-circuit conductor ampacity?
Answer: 50 A
Load current = 9,600 W / 240 V = 40 A. Section 424.4(B) requires branch-circuit conductors for fixed electric space-heating equipment to have an ampacity of at least 125% of the load: 40 x 1.25 = 50 A. 40 A omits the factor, 45 A is 112.5%, and 60 A is 150%. (A circuit feeding two or more heater outlets would be limited to 30 A by 424.4(A), which is why this heater is on an individual circuit.)
Reference: NFPA 70, National Electrical Code, 2023, 424.4(B)
A paint-mixing room handles volatile flammable liquids that normally stay in closed containers and could escape only by container failure. How does 500.5(B)(2) describe such a location?
Answer: Hazardous liquids or gases are normally confined and escape only by rupture or abnormal operation
A Class I, Division 2 location is one where volatile flammable liquids, vapors or gases are handled, processed or used but are normally confined within closed containers or systems and can escape only through accidental rupture or abnormal equipment operation. Ignitible concentrations under normal conditions describe Division 1. Dust is Class II and fibers are Class III.
Reference: NFPA 70, National Electrical Code, 2023, 500.5(B)(2)
A permanently installed pool at a dwelling needs a general-purpose 125-volt, 15- or 20-ampere receptacle under 680.22(A). How far from the inside wall of the pool must it be located?
Answer: At least 6 ft and not more than 20 ft
Section 680.22(A) requires at least one 125 V, 15 or 20 A general-purpose receptacle located at least 6 ft and not more than 20 ft from the inside wall of the pool, and not more than 6 ft 6 in. above the floor, platform or grade. The other ranges are not in the rule.
Reference: NFPA 70, National Electrical Code, 2023, 680.22(A)
Under Article 701, how soon must a legally required standby system be able to supply power after the normal source fails?
Answer: Within 60 seconds
Section 701.12 requires legally required standby power to be available within 60 seconds of loss of normal power. Emergency systems under Article 700 have the stricter 10-second limit.
Reference: NFPA 70, National Electrical Code, 2023, 701.12
Under the State Electrical Act, how much experience must an applicant for a journeyman electrician license have in the electrical trade?
Answer: At least four years, acceptable to the board
Section 81-2109(1) requires an applicant for a journeyman electrician license to have at least four years of experience acceptable to the board. Registration as an apprentice for those years counts as evidence of the experience on board approval. Three years is the requirement for a residential journeyman license.
Reference: Nebraska State Electrical Act (Neb. Rev. Stat. 81-2101 to 81-2145), 81-2109(1)
The 4,800-watt, 240-volt heater of 12 ohms is connected by mistake to a 208-volt source. Assuming its resistance stays constant, about how much power does it produce?
Answer: 3,605 W
Power varies with the square of the voltage: P = E squared / R = 208 x 208 / 12 = 43,264 / 12 = 3,605 W. 4,800 W ignores the lower voltage, 4,160 W is 4,800 x 208 / 240, a straight ratio, which is wrong because power goes with the square of voltage, and 2,400 W is half of rated power.
Reference: NFPA 70, National Electrical Code, 2023, Basic electricity theory: power formula (P = E x I)
Sources
- Nebraska State Electrical Division: PSI exams (opens in a new tab)
- Nebraska State Electrical Division: exam information and licensing applications (opens in a new tab)
- Nebraska State Electrical Division: 2023 NEC adoption (opens in a new tab)
Questions last verified November 6, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.