Requirements at a glance
| Agency | Montana State Electrical Board (Department of Labor and Industry); exams by PSI |
|---|---|
| Experience | Documented on your Board application. See the Board site for the hours required for this license. |
| Exam | 50 questions, 2.5 hours, 70% |
| Books allowed | NEC (tabs and indexes), Montana Building Codes Amendments and a non-programmable calculator |
| Fees | $75 to PSI (non-refundable, valid one year), plus Board application and license fees |
Electricians applying to the Montana State Electrical Board for a residential electrician license after documenting their experience.
Official links
How to get licensed, step by step
Apply to the Board
Send the Montana State Electrical Board your application and documentation of your experience.
Wait for your admission letter
When the Board approves you, it mails or e-mails an admission letter. You can't schedule before then.
Pay and schedule with PSI
Register at PSI online or call 855-746-8173. If you fail once you can retest right away; after a second failure you need an 8-hour Board-approved code seminar before a third try.
Schedule with PSI (Montana electrical) (opens in a new tab)PSI: Montana electrical exam bulletin (opens in a new tab)
Pass and get licensed
Send the Board your results and fees to receive your license.
How to prepare
- Check the NEC edition on the current PSI bulletin before you buy a book. The bulletin lists the 2020 NEC, while Montana's code list shows the 2023 NEC effective September 26, 2026.
- Bring the Montana Building Codes Amendments with your NEC. Tabs and indexes are allowed, and highlights and notes made before the exam are fine; writing in your books during the exam is not.
- A silent, non-programmable calculator is allowed. Calculators built for electrical estimating are not.
- Focus on the dwelling-unit articles: 210, 220 Part III, 230, 250, 300 series wiring methods and 406.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below, and most questions come from the NEC and the Montana amendments. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
NFPA 70: National Electrical Code (NEC)Essential
Open book, tabs and indexes allowed. The PSI bulletin lists the 2020 edition; Montana's code list shows the 2023 edition effective September 26, 2026, so confirm on the current bulletin.
NFPA store (opens in a new tab)Free online access (opens in a new tab)
Montana Building Codes Amendments (ARM Title 24, Chapter 301)Essential
Listed in the PSI bulletin as allowed. Free online.
ARM 24.301.401 and electrical rules (ARM Title 24, Chapter 301) (opens in a new tab)
Printreading by David L. Hittinger
Listed in the PSI bulletin as allowed (based on the 2020 NEC). Useful for the general trade knowledge section.
Official reference list (as published by the testing agency)
- National Electrical Code (NFPA 70), 2020 edition per the PSI bulletin; tabs and indexes allowed (see the edition note in the details)
- Montana Building Codes Amendments (ARM Title 24, Chapter 301)
- Printreading by David L. Hittinger, based on the 2020 NEC (listed in the bulletin)
- A silent, non-printing, non-programmable calculator (not an electrical-estimating calculator)
What's on the exam
Estimated topic weighting. No official breakdown is published:
| Topic | Questions | |
|---|---|---|
| National Electrical Code | 1 | |
| General Trade Knowledge & Theory | 1 |
Exam day details
- Administered by PSI Services for the Montana State Electrical Board.
- Fee: $75 to PSI, non-refundable and valid for one year. Board application and license fees are separate.
- 50 questions plus a few unscored experimental items in 2.5 hours (150 minutes); 70% correct to pass.
- The PSI bulletin (page dated 1/23/2026) lists the 2020 NEC and the Montana Building Codes Amendments, and titles the exams '2020'. DLI's code list shows the 2023 NEC taking effect in Montana on September 26, 2026. Check the current PSI bulletin for the edition on your test date.
- Open book: bring your own NEC (tabs and indexes allowed), the Montana Building Codes Amendments and a silent, non-programmable calculator. Highlighting and notes in approved material before the exam are allowed; writing in your books during the exam is not.
- PSI adds a small number of unscored experimental questions to each exam.
- The Board approves your application first and mails or e-mails an admission letter; then you pay and schedule with PSI. Exam fees are non-refundable, non-transferable and valid for one year.
- After a first failure you may reschedule with no waiting period. After a second failure you must show proof of an 8-hour Board-approved electrical code seminar before a third attempt.
Note: PSI does not publish a topic breakdown for this exam, so the topic split in our practice tests is an estimate.
Frequently asked questions
What's on the Montana residential electrician exam?
50 questions in two areas: the National Electrical Code, and general trade knowledge and theory. PSI does not publish the split.
Is the residential exam open book?
Yes. You bring your own NEC with tabs and the Montana Building Codes Amendments, plus an approved calculator.
How do I schedule the exam?
Wait for the Board's admission letter, then register with PSI online at test-takers.psiexams.com/maseb or by phone at 855-746-8173.
Free questions with answers
Show all 10 free questions and answers
A Montana electrical permit for a home remodel was issued on January 10, 2025 and was not renewed before it expired. The permittee applied for the one renewal the rules allow, inside the grace period, and the department granted it on August 1, 2026. When does the renewed permit expire?
Answer: February 1, 2028
Original permits run 18 months from issuance (here to July 10, 2026). One renewal of 18 months is allowed if the application is made no more than 30 days after expiration. A renewed permit runs 18 months from the renewal date, so August 1, 2026 plus 18 months is February 1, 2028. Counting from the original date again (January 10, 2028) is the common mistake.
Reference: Montana Administrative Rules, Title 24, chapter 301, subchapter 4, ARM 24.301.431(9)
Under the Montana fee schedule, a new single-family dwelling with a 400-ampere service and an attached garage wired at the same time falls under which permit fee?
Answer: $380, the 201 to 400 ampere service tier
The schedule prices single-family dwellings by service size: $200 up to 200 A, $380 for 201 to 400 A, $600 for 401 to 600 A. An attached garage wired at the same time is included in the dwelling fee, so no accessory building fee is added.
Reference: Montana Administrative Rules, Title 24, chapter 301, subchapter 4, ARM 24.301.461(1)(a)
A homeowner requests a state inspection of an existing house wiring system. The inspector spends 2 hours 10 minutes including paperwork. Ignoring travel and per diem, what is the requested-inspection fee?
Answer: $150
The fee is $60 for up to one hour, then $30 for each 30 minutes or fractional part beyond the first hour. The time over one hour is 1 hour 10 minutes: two full 30-minute blocks plus a fraction makes 3 blocks. $60 + 3 x $30 = $150. Counting only full blocks gives $120.
Reference: Montana Administrative Rules, Title 24, chapter 301, subchapter 4, ARM 24.301.461(2)
A $200 permit was refunded at the department's discretion after the state inspector had performed two required inspections. Under the refund rule, what amount is returned?
Answer: $85
A refund is reduced by the $25 refund/credit fee and, if the project was inspected, by $45 for each required inspection performed. $200 - $25 - (2 x $45) = $85. Forgetting the inspection proration gives $175.
Reference: Montana Administrative Rules, Title 24, chapter 301, subchapter 4, ARM 24.301.491(2) and (3)
Montana amends NEC 760.1 so that smoke alarms and carbon monoxide alarms must be installed in a building as required by which adopted code?
Answer: The International Building Code or International Residential Code
The amendment ties alarm requirements to the adopted IBC or IRC, whichever applies to the building. It states this applies even when the structure is exempt under 50-60-102, MCA. MAR Notice 2026-95.2 (effective 9/26/2026) repealed ARM 24.301.411 and moved the same text into ARM 24.301.401(16) with the 2023 NEC.
Reference: Montana Administrative Rules, Title 24, chapter 301, subchapter 4, ARM 24.301.411(1)(d) (repealed eff. 9/26/2026); ARM 24.301.401(16) as adopted eff. 9/26/2026 (MAR Notice 2026-95.2)
A 240-volt baseboard heater in a Montana basement draws current through a heating element with 12 ohms of resistance. How much current flows?
Answer: 20 amperes
Ohm's law: I = E / R = 240 / 12 = 20 A. Multiplying instead of dividing gives 2,880, which is not a current. The 2.0 A value results from moving the decimal wrongly.
Reference: Electrical theory: Ohm's law and the power formulas, I = E / R
What is the resistance of a 1,500-watt, 120-volt heating element, using R = E squared / P?
Answer: 9.6 ohms
R = E2 / P = 14,400 / 1,500 = 9.6 ohms. 12.5 is the current in amperes, not the resistance, and 0.08 comes from inverting the formula (120 / 1,500).
Reference: Electrical theory: Ohm's law and the power formulas, R = E squared / P
Two resistances of 12 ohms and 6 ohms are connected in parallel across a 120-volt supply. What is their combined resistance?
Answer: 4 ohms
For two resistors in parallel, R = (R1 x R2) / (R1 + R2) = 72 / 18 = 4 ohms. The sum, 18 ohms, is the series value. Parallel resistance is always smaller than the smallest branch.
Reference: Electrical theory: Ohm's law and the power formulas, Parallel resistance
A 1,500-watt electric baseboard heater runs 8 hours per day for 30 days. At 12 cents per kilowatt-hour, what does it cost to operate?
Answer: $43.20
Energy = 1.5 kW x 8 h x 30 days = 360 kWh. Cost = 360 x $0.12 = $43.20. $5.40 ignores the 8 hours, $1.44 is a single day, and $432.00 is a decimal slip.
Reference: Electrical theory: Ohm's law and the power formulas, kWh = kW x hours
A transformer has 1,000 turns in the primary winding and 250 turns in the secondary. It is connected to a 480-volt supply. What is the secondary voltage?
Answer: 120 volts
Voltage is proportional to turns: Es = Ep x (Ns / Np) = 480 x (250 / 1,000) = 120 V. 1,920 V comes from inverting the ratio.
Reference: Electrical theory: Ohm's law and the power formulas, Transformer turns ratio
Sources
- PSI: Montana Electrical Licensing Examinations Candidate Information Bulletin (opens in a new tab)
- Montana State Electrical Board (opens in a new tab)
- Montana DLI: current adopted building codes (opens in a new tab)
- ARM 24.301.401: incorporation of the National Electrical Code (opens in a new tab)
Questions last verified October 27, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.