Question 1 of 10Major Load Calculations

Using the standard method (Part III of Article 220), size the 120/240-volt single-phase service for a new 2,640 sq ft Montana house. Loads: general lighting at 3 VA per sq ft, two 20-amp small-appliance circuits, one laundry circuit, a 12 kW range, a 5,000 VA dryer, four fastened-in-place appliances (dishwasher 1,000 VA, water heater 4,500 VA, disposal 750 VA, trash compactor 800 VA) and 8,000 VA of electric baseboard heat. A 4,800 VA air conditioner is also installed. What is the calculated service load in amperes?

Requirements at a glance

AgencyMontana State Electrical Board (Department of Labor and Industry); exams by PSI
ExperienceDocumented on your Board application. See the Board site for the hours required for this license.
Exam80 questions, 4 hours, 75%
Books allowedNEC (tabs and indexes), Montana Building Codes Amendments and a non-programmable calculator
Fees$85 to PSI (non-refundable, valid one year), plus Board application and license fees

Electricians applying to the Montana State Electrical Board for a master license after documenting their experience.

How to get licensed, step by step

  1. Apply to the Board

    Send the Montana State Electrical Board your application and documentation of your experience.

    Montana State Electrical Board (opens in a new tab)

  2. Wait for your admission letter

    When the Board approves you, it mails or e-mails an admission letter. You can't schedule before then.

    Montana State Electrical Board (opens in a new tab)

  3. Pay and schedule with PSI

    Register at PSI online or call 855-746-8173. If you fail once you can retest right away; after a second failure you need an 8-hour Board-approved code seminar before a third try.

    Schedule with PSI (Montana electrical) (opens in a new tab)PSI: Montana electrical exam bulletin (opens in a new tab)

  4. Pass and get licensed

    Send the Board your results and fees to receive your license.

    Montana State Electrical Board (opens in a new tab)

How to prepare

  • Check the NEC edition on the current PSI bulletin before you buy a book. The bulletin lists the 2020 NEC, while Montana's code list shows the 2023 NEC effective September 26, 2026.
  • Bring the Montana Building Codes Amendments with your NEC. Tabs and indexes are allowed, and highlights and notes made before the exam are fine; writing in your books during the exam is not.
  • A silent, non-programmable calculator is allowed. Calculators built for electrical estimating are not.
  • The master exam adds major load calculations. Practice service, feeder and multi-family load calculations in Article 220 and Annex D.
  • The pass mark is 75%, higher than the journeyman and residential exams.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the NEC and the Montana amendments. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

Official reference list (as published by the testing agency)
  • National Electrical Code (NFPA 70), 2020 edition per the PSI bulletin; tabs and indexes allowed (see the edition note in the details)
  • Montana Building Codes Amendments (ARM Title 24, Chapter 301)
  • Printreading by David L. Hittinger, based on the 2020 NEC (listed in the bulletin)
  • A silent, non-printing, non-programmable calculator (not an electrical-estimating calculator)

What's on the exam

Estimated topic weighting. No official breakdown is published:

TopicQuestions
National Electrical Code1
General Trade Knowledge & Theory1
Major Load Calculations1

Exam day details

  • Administered by PSI Services for the Montana State Electrical Board.
  • Fee: $85 to PSI, non-refundable and valid for one year. Board application and license fees are separate.
  • 80 questions plus a few unscored experimental items in 4 hours (240 minutes); 75% correct to pass.
  • The PSI bulletin (page dated 1/23/2026) lists the 2020 NEC and the Montana Building Codes Amendments, and titles the exams '2020'. DLI's code list shows the 2023 NEC taking effect in Montana on September 26, 2026. Check the current PSI bulletin for the edition on your test date.
  • Open book: bring your own NEC (tabs and indexes allowed), the Montana Building Codes Amendments and a silent, non-programmable calculator. Highlighting and notes in approved material before the exam are allowed; writing in your books during the exam is not.
  • PSI adds a small number of unscored experimental questions to each exam.
  • The Board approves your application first and mails or e-mails an admission letter; then you pay and schedule with PSI. Exam fees are non-refundable, non-transferable and valid for one year.
  • After a first failure you may reschedule with no waiting period. After a second failure you must show proof of an 8-hour Board-approved electrical code seminar before a third attempt.

Note: PSI does not publish a topic breakdown for this exam, so the topic split in our practice tests is an estimate.

Frequently asked questions

What's on the Montana master electrician exam?

80 questions in three areas: the National Electrical Code, general trade knowledge and theory, and major load calculations. PSI does not publish the split.

What score do I need on the Montana master electrician exam?

75% correct. The journeyman and residential exams need 70%.

What if I fail the exam twice?

You must show proof of an 8-hour electrical code seminar approved by the Board before a third attempt. After a first failure you can reschedule right away.

Free questions with answers

Show all 10 free questions and answers
  1. Using the standard method (Part III of Article 220), size the 120/240-volt single-phase service for a new 2,640 sq ft Montana house. Loads: general lighting at 3 VA per sq ft, two 20-amp small-appliance circuits, one laundry circuit, a 12 kW range, a 5,000 VA dryer, four fastened-in-place appliances (dishwasher 1,000 VA, water heater 4,500 VA, disposal 750 VA, trash compactor 800 VA) and 8,000 VA of electric baseboard heat. A 4,800 VA air conditioner is also installed. What is the calculated service load in amperes?

    Answer: 135.8 A

    General load: 2,640 x 3 = 7,920 VA, plus 3,000 VA small appliance and 1,500 VA laundry = 12,420 VA. First 3,000 VA at 100% plus the remaining 9,420 VA at 35% = 6,297 VA. Range (Table 220.55, 12 kW or less) 8,000 VA; dryer 5,000 VA; the four fastened-in-place appliances total 7,050 VA, taken at 75% = 5,287.5 VA (220.53). Heat and A/C are noncoincident, so only the larger, 8,000 VA of heat, is counted (220.60). Total 32,584.5 VA / 240 V = 135.8 A. Using 100% of the appliances gives 143.1 A; skipping the lighting demand gives 161.3 A; adding the A/C as well gives 155.8 A.

    Reference: NFPA 70 National Electrical Code (2020 and 2023 editions), Dwelling 3 VA/sq ft: 220.12 (2020) / 220.41 (2023); lighting demand Table 220.42 (2020) / Table 220.45 (2023); 220.52, 220.53, Table 220.55, 220.60

  2. A single household electric range is rated 15 kW. Using Table 220.55 and its Note 1, what demand load is used for this range in a dwelling feeder calculation?

    Answer: 9.2 kW

    Column C gives 8 kW for one range rated 12 kW or less. Note 1 allows ranges over 12 kW and not over 27 kW to increase the Column C value by 5% for each kW over 12. The range is 3 kW over, so 8 kW x (1 + 3 x 0.05) = 8 x 1.15 = 9.2 kW. Using 8 kW ignores the note; 8.15 kW adds 5% of one kilowatt rather than 5% of the 8 kW value per kW; 15 kW applies no demand at all.

    Reference: NFPA 70 National Electrical Code (2020 and 2023 editions), Table 220.55, Note 1

  3. A Montana apartment building feeder serves 8 dwelling units, each with a 5,200 VA electric clothes dryer. Using the dryer demand factors in Table 220.54, what is the dryer demand load on the feeder?

    Answer: 24,960 VA

    Each dryer is the larger of 5,000 VA or its nameplate, so 5,200 VA is used. Total connected = 8 x 5,200 = 41,600 VA. Table 220.54 gives 60% for eight dryers, so demand = 41,600 x 0.60 = 24,960 VA. 65% is the seven-dryer factor and 55% is the nine-dryer factor; 100% applies only to one through four dryers.

    Reference: NFPA 70 National Electrical Code (2020 and 2023 editions), 220.54, Table 220.54

  4. A contractor is wiring a new single-family house in Helena. Under the Montana amendment to NEC 210.12, which of these dwelling-unit circuits is still required to have arc-fault circuit-interrupter protection?

    Answer: The 15-amp, 120-volt circuit supplying the bedroom receptacle outlets

    ARM 24.301.401 amends 210.12 by deleting every reference to kitchens, so kitchen circuits no longer need AFCI protection in Montana. It is (4) in the 9/21/2024 rule that goes with the 2020 NEC, (9) in the rule adopted with the 2023 NEC (MAR Notice 2026-95.2, effective 9/26/2026), and (2) in the older text printed in the PSI bulletin. Bedrooms remain on the dwelling-unit AFCI list (210.12(A) in the 2020 NEC, 210.12(B) in the 2023 NEC), so the bedroom circuit still requires it. The outdoor receptacle circuit is not in a listed room or area, and the 240-volt dryer circuit is outside the list, which covers only 120-volt, 15- and 20-ampere dwelling-unit circuits.

    Reference: Administrative Rules of Montana, ARM 24.301.401(9) as adopted with the 2023 NEC (eff. 9/26/2026, MAR Notice 2026-95.2); (4) in the 9/21/2024 text for the 2020 NEC; (2) in the pre-9/21/2024 text printed in the PSI bulletin; NEC 210.12(A) (2020) / 210.12(B) (2023)

  5. The Montana Department of Labor and Industry amended NEC 210.12, Arc-Fault Circuit-Interrupter Protection. What did the amendment do?

    Answer: It deleted all references to kitchens in the section

    ARM 24.301.401 states that subsection 210.12 is amended to delete all references to "kitchen" or "kitchens." It is (4) in the 9/21/2024 rule that goes with the 2020 NEC, (9) in the rule adopted with the 2023 NEC (MAR Notice 2026-95.2, effective 9/26/2026), and (2) in the older text printed in the PSI bulletin. Nothing in the rule changes device trip levels, adds garage exemptions or moves protection to feeders.

    Reference: Administrative Rules of Montana, ARM 24.301.401(9) as adopted with the 2023 NEC (eff. 9/26/2026, MAR Notice 2026-95.2); (4) in the 9/21/2024 text for the 2020 NEC; (2) in the pre-9/21/2024 text printed in the PSI bulletin

  6. Where service equipment for a manufactured or mobile home is installed separate from the home, what is the greatest distance it may be located from the exterior wall of the home under the NEC as applied in Montana?

    Answer: 50 ft (15.24 m)

    Under the 2020 NEC, 550.32(A) allows no more than 30 ft, and ARM 24.301.411(1)(b) increases that to 50 ft (15.24 m) in Montana. With the 2023 NEC, MAR Notice 2026-95.2 (effective 9/26/2026) repealed that amendment because the 2023 NEC 550.32(A) itself sets 50 ft, so 50 ft is correct under either edition.

    Reference: Administrative Rules of Montana, ARM 24.301.411(1)(b) (repealed eff. 9/26/2026); NEC 2020 550.32(A); 2023 NEC 550.32(A) (50 ft, per the repeal note in MAR 2026-95; repeal adopted eff. 9/26/2026, MAR Notice 2026-95.2)

  7. How long is a Montana electrical permit valid from the date it is issued?

    Answer: 18 months

    ARM 24.301.431(9) says electrical permits are valid for 18 months from the date of issuance. An original permit that is not renewed expires at 18 months.

    Reference: Administrative Rules of Montana, ARM 24.301.431(9)

  8. An electrical permit has expired. Under the Montana administrative rules, when may the department grant the one renewal, and how long does the renewed permit last?

    Answer: Application must be made within 30 days after expiration; the renewal lasts 18 months

    ARM 24.301.431(9) allows one renewal of 18 months if the renewal application is made not more than 30 days after the original permit expires. The renewed permit expires 18 months after the renewal date. The renewal fee is listed separately in ARM 24.301.461.

    Reference: Administrative Rules of Montana, ARM 24.301.431(9)

  9. What does a state electrical inspector apply to an installation that passes final inspection, and what happens to the provisional power designation?

    Answer: A green approved tag; the department removes the provisional power designation

    ARM 24.301.451(2): inspectors date and sign the report and apply a green approved tag to installations the department approves. On approval the department removes the provisional power designation.

    Reference: Administrative Rules of Montana, ARM 24.301.451(2)

  10. The three line currents in a 208Y/120-volt, 4-wire system supplying resistive 120-volt loads are 100 A, 80 A and 60 A. What is the neutral current?

    Answer: 34.6 A

    For a balanced-voltage wye with resistive loads, neutral current = square root of (A2 + B2 + C2 - AB - BC - CA) = sqrt(10,000 + 6,400 + 3,600 - 8,000 - 4,800 - 6,000) = sqrt(1,200) = 34.6 A. 20 A is the simple difference between the highest and lowest, 80 A is the average, and 240 A is the arithmetic sum, which only occurs on a single-phase two-wire circuit.

    Reference: Electrical theory, Unbalanced neutral current in 3-phase, 4-wire wye systems