Question 1 of 10Gas Systems

A furnace rated 120,000 Btu/h and a water heater rated 40,000 Btu/h are in one confined space and will use indoor air by the standard method. Under the 2021 IFGC, what is the minimum required volume of indoor air?

Requirements at a glance

AgencyLouisiana State Licensing Board for Contractors (LSLBC); exams by PSI
Exam100 questions, 4 hours, 70%
Books allowed2018 IFGC, IMC and IPC, Modern Refrigeration, SMACNA, ACCA Manuals D and N, NFPA 58 and 13 and others
RequirementsBusiness and Law course (not an exam), net worth statement, insurance and other LSLBC requirements
Fees$140 to PSI, plus LSLBC application and license fees

Qualifying parties for a Louisiana commercial mechanical contractor license from the LSLBC. The Mechanical classification covers plumbing, gas, HVAC and refrigeration work.

How to get licensed, step by step

  1. Apply to the LSLBC

    Submit an application for licensure, or a request to add a classification or qualifying party to your license. The Board reviews it before you can test.

    LSLBC: apply for a license (opens in a new tab)Louisiana State Licensing Board for Contractors (LSLBC) (opens in a new tab)

  2. Schedule with PSI

    Once approved you get an e-mail from PSI to pay and schedule. Eligibility is good for one year; after that you reapply with the Board.

    Schedule with PSI (Louisiana contractors) (opens in a new tab)

  3. Take the open-book exam

    Bring your own tabbed references. 70% is passing.

    Schedule with PSI (Louisiana contractors) (opens in a new tab)

  4. Finish your license

    Complete the Business and Law course and the remaining LSLBC requirements to be licensed.

    Louisiana State Licensing Board for Contractors (LSLBC) (opens in a new tab)

How to prepare

  • Bring the exact editions on PSI's outline. Louisiana's adopted codes are the 2021 ICC codes and the 2020 NEC, but several PSI exams list other editions (the 2023 NEC, 2018 ICC books). The 2023 NEC and 2024 ICC codes take effect January 1, 2027.
  • Tab your books before exam day. You can highlight, underline and index them with permanent tabs, but you can't write in them, and sticky notes are removed.
  • The exam spans plumbing, gas, HVAC and refrigeration. Gas systems (10) and isometric analysis (8) are the biggest topics.
  • Practice developed length, drainage fixture units and duct sizing by hand; they are quick points if your tabs are ready.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the 2018 ICC books. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

  • 2018 IFGC, IMC and IPC (ICC)Essential

    PSI lists the 2018 editions for the Mechanical Work exam. Louisiana has adopted the 2021 editions, so the two differ in places.

    ICC store (opens in a new tab)

  • Modern Refrigeration and Air Conditioning (20th Edition for Mechanical Work; 20th or 21st for HVACR)

    Allowed in the exam room. Refrigeration cycle, components, controls and piping.

    Goodheart-Willcox (opens in a new tab)

  • 29 CFR Part 1926: Safety and Health Regulations for Construction

    Allowed in the room for the electrical, mechanical and building exams. Free online from OSHA.

    OSHA 29 CFR 1926 (opens in a new tab)

Official reference list (as published by the testing agency)
  • International Fuel Gas Code (IFGC), International Mechanical Code (IMC) and International Plumbing Code (IPC), 2018 editions
  • Modern Refrigeration and Air Conditioning, 20th Edition
  • SMACNA HVAC Duct Construction Standards, 3rd Edition (2005)
  • ACCA Manual N, 5th Edition (2008), and Manual D, 4th Edition (2016)
  • NFPA 58 (2011), NFPA 13 (2002), Pipefitters Handbook 3rd Edition, 29 CFR Part 1926

What's on the exam

Official content outline from PSI Services (number of questions per topic):

TopicQuestions
Boilers and Hydronics6
Gas Systems10
Cleanouts3
Plumbing Fixtures and Equipment5
Water Heaters2
Piping, valves, controls5
Sheet Metal and Ducts6
Water Supply5
Hangers and Supports4
Drain, Waste, and Vent5
Backflow2
Traps and Interceptors4
Developed length3
Isometric Analysis8
Safety4
Joints and Connections3
General Plumbing Regulations3
Fire Sprinklers4
Refrigerants and Refrigeration4
Heating and Cooling Principles4
Load Calculations5
Testing, Adjusting and Balancing1
HVAC Equipment4

Exam day details

  • Administered by PSI Services for the Louisiana State Licensing Board for Contractors (LSLBC).
  • Fee: $140 to PSI. LSLBC application and license fees are separate.
  • 100 questions in 4 hours; 70 correct (70%) to pass.
  • PSI lists the 2018 ICC books for this exam, while Louisiana's adopted codes are the 2021 editions. Our questions name the edition they use.
  • Open book: bring your own copies of the allowed references. You may highlight, underline and index them beforehand, but not write in them during the exam. Temporary tabs such as sticky notes are removed.
  • PSI may add unscored experimental questions, which count against your time.
  • The LSLBC must approve your application (or your request to add a classification) first. PSI then e-mails your eligibility, which is good for one year; if you haven't passed by then you reapply with the Board.
  • Business and Law is a required course, not an exam, so there is no separate business exam to take.
  • Code questions are based only on the edition PSI lists. For other references, later editions are fine.

Frequently asked questions

What's on the Louisiana Mechanical Work exam?

100 questions in 23 topics. The biggest are gas systems 10, isometric analysis 8, boilers and hydronics 6, sheet metal and ducts 6, plumbing fixtures, piping, water supply, drain, waste and vent, and load calculations 5 each.

Does the Mechanical exam include plumbing?

Yes. LSLBC's Mechanical classification includes plumbing, gas and HVAC work, and the exam covers fixtures, water supply, drain, waste and vent, traps, backflow and developed length alongside heating and cooling.

Which code editions apply?

PSI's outline lists the 2018 IFGC, IMC and IPC. Louisiana's adopted codes are the 2021 editions, so check your test date's PSI outline before you buy books.

Free questions with answers

Show all 10 free questions and answers
  1. A furnace rated 120,000 Btu/h and a water heater rated 40,000 Btu/h are in one confined space and will use indoor air by the standard method. Under the 2021 IFGC, what is the minimum required volume of indoor air?

    Answer: 8,000 cubic feet

    Section 304.5.1 requires 50 cubic feet per 1,000 Btu/h of input, summed for all appliances in the space. 160,000 Btu/h / 1,000 = 160; 160 x 50 = 8,000 cubic feet. 16,000 would use 100 cubic feet per 1,000 Btu/h, and 4,000 uses 25.

    Reference: 2021 International Fuel Gas Code, Section 304.5.1

  2. Under 2021 IPC Table 308.5, what is the maximum horizontal hanger spacing for PVC drainage pipe?

    Answer: 4 feet

    Table 308.5 lists PVC pipe at 4 feet maximum horizontal spacing and 10 feet vertical. 10 feet is the horizontal spacing for brass pipe; copper tubing 1-1/4 inch and smaller is 6 feet.

    Reference: 2021 International Plumbing Code, Table 308.5

  3. Using 2021 IPC Table 604.3, what are the minimum flow rate and flow pressure required at the fixture supply outlet for a residential kitchen sink?

    Answer: 1.75 gpm at 8 psi

    Table 604.3 lists residential sinks at 1.75 gpm and 8 psi. 2.5 gpm at 8 psi is a shower; 3 gpm is a service sink or a close-coupled tank water closet, which needs 20 psi.

    Reference: 2021 International Plumbing Code, Table 604.3

  4. Under 2021 IPC Table 604.4, what is the maximum water consumption per flushing cycle for a standard (non-blowout) water closet?

    Answer: 1.6 gallons

    Table 604.4 sets water closets at 1.6 gallons per flushing cycle and urinals at 1.0 gallon. Blowout-design water closets are excepted up to 3-1/2 gallons under Section 604.4. 2.2 gpm is the flow rate for private lavatory and sink faucets.

    Reference: 2021 International Plumbing Code, Table 604.4

  5. A public restroom group has 30 public water closets (1.6 gpf), 12 lavatories, 10 urinals rated 1 gallon per flush, 4 floor drains and 2 service sinks on one 1/8 inch per foot building drain. No testing has confirmed reduced fixture unit values. Using 2021 IPC Tables 709.1 and 710.1(1), what is the smallest building drain size?

    Answer: 5 inches

    Footnote e to Table 709.1 says that for building drains and sewers, water closets and urinals shall not be rated at the lower dfu values unless confirmed by testing, so use 6 dfu per public water closet and 4 per urinal. Units: 30 x 6 = 180; 12 lavatories x 1 = 12; 10 urinals x 4 = 40; 4 floor drains x 2 = 8; 2 service sinks x 2 = 4. Total = 244 dfu. At 1/8 inch per foot, Table 710.1(1) allows 180 dfu on 4 inches and 390 on 5 inches, so 5 inches is required. Using the reduced values (4 and 2) gives 164 dfu and the 4-inch answer, which the footnote does not allow for a building drain.

    Reference: 2021 International Plumbing Code, Tables 709.1 and 710.1(1)

  6. On an isometric piping drawing, how are the vertical pipe runs and the two horizontal directions normally drawn?

    Answer: Vertical runs are drawn vertical; the two horizontal directions are drawn at 30 degrees above the horizontal

    An isometric drawing shows a three-dimensional pipe route on a flat sheet using three axes 120 degrees apart: one vertical and two receding at 30 degrees from the horizontal. Lengths along each axis are drawn to the same scale.

    Reference: Pipefitting trade mathematics (offset travel factors); ASME Y14.3 isometric projection, Isometric projection axes

  7. A hydronic heating system has a maximum design pressure of 80 psi. Under the 2018 IMC, what is the minimum hydrostatic test pressure and duration?

    Answer: 120 psi for at least 15 minutes

    Section 1208.1 requires a hydrostatic test at 1-1/2 times the maximum system design pressure, but not less than 100 psi, held at least 15 minutes. 1.5 x 80 = 120 psi, which is above the 100 psi floor. 160 psi would double the design pressure.

    Reference: 2018 International Mechanical Code, Section 1208.1

  8. A new hydronic heating system will drain to the building plumbing drainage system. Which statement matches the 2018 IMC Section 1206.2?

    Answer: The system must be designed and installed so it can be drained, and the drain connection must follow the IPC

    Section 1206.2 requires hydronic piping systems to be designed and installed to permit draining, and where the system drains to the plumbing drainage system the installation must conform to the International Plumbing Code. The only exception is the buried portions of systems embedded underground or under floors, so the last choice reverses the rule.

    Reference: 2018 International Mechanical Code, Section 1206.2

  9. Under the specified-length method of 2018 IMC Section 504.8.4.1 and Table 504.8.4.1, a dryer exhaust duct uses two 4-inch radius mitered 90-degree elbows and two 4-inch radius mitered 45-degree elbows. What is the maximum length of straight duct permitted?

    Answer: 20 feet

    The maximum exhaust duct length is 35 feet, reduced by the equivalent length of fittings: each 4-inch mitered 90-degree elbow is 5 feet and each 45-degree elbow is 2 feet 6 inches. Fittings total 2(5) + 2(2.5) = 15 feet, so straight duct may be 35 - 15 = 20 feet. 25 feet forgets the 45-degree elbows.

    Reference: 2018 International Mechanical Code, Section 504.8.4.1; Table 504.8.4.1

  10. A wall has a net area of 400 square feet and a U-value of 0.08 Btu/h-sq ft-F. Inside design is 70 degrees F and outside design is 10 degrees F. What is the heat loss through the wall?

    Answer: 1,920 Btu/h

    Q = U x A x delta-T = 0.08 x 400 x (70 - 10) = 0.08 x 400 x 60 = 1,920 Btu/h. 1,600 uses a 50 degree difference, 320 uses only 10 degrees (the outdoor temperature), and 28,000 multiplies the area by the 70 degree indoor temperature and leaves out U.

    Reference: Standard load calculation relationships (conduction Q = U x A x delta-T; air Q = 1.08 x cfm x delta-T), Conduction Q = U x A x delta-T