Kentucky licensing exam

Kentucky Master HVAC Exam: Practice Test & Licensing Guide

The ICC Kentucky Master HVAC exam (595): 100 questions in 4 hours on the 2015 IMC and NFPA 54, covering ducts, venting, combustion air, gas piping, boilers and plan analysis. Open book, 70% to pass.

Questions
100
Time limit
4 hours
Passing score
70%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10HVAC Principles, Terminology, Administration, and Safety

A mechanical permit has been issued but no work has started. Under the 2015 IMC as published, after how many days from the date of the permit does it expire and become void if work has not commenced?

Requirements at a glance

AgencyKentucky DHBC, Division of HVAC; exam by ICC at Pearson VUE (DHBC also gives in-person exams)
Experience2 years as a journeyman or equivalent; 1 year = 1,500 hours (KRS 198B.658)
Exam100 questions, 4 hours, 70% to pass
Books allowed2015 IMC, NFPA 54 (2009), Refrigeration and Air Conditioning Technology (8th or 9th ed.)
Fees$100 exam; $250 master application

Applicants for a Kentucky master HVAC license from the Department of Housing, Buildings and Construction.

How to get licensed, step by step

  1. Apply to DHBC

    Send DHBC your license application with proof of experience. Licenses are issued by the Department, not the testing vendor.

    Kentucky Department of Housing, Buildings and Construction (DHBC) (opens in a new tab)Kentucky Revised Statutes (KRS 227A, 198B, 318) (opens in a new tab)

  2. Schedule the master HVAC exam

    Register and pay the $100 exam fee ($60 for Business and Law) for a Pearson VUE testing center. If you fail, you wait 10 days before you retest. Schedule through Pearson VUE (ICC); DHBC also accepts Prov and NASCLA electrical results.

    ICC: Kentucky candidate bulletin (1/17/2026) (opens in a new tab)DHBC: Electrical new application checklists (2/4/2025) (opens in a new tab)

  3. Pass and get licensed

    You need 70% to pass. Your passing score is valid for 3 years, so file your license application and any required insurance before it expires.

    Kentucky Department of Housing, Buildings and Construction (DHBC) (opens in a new tab)815 KAR: DHBC administrative regulations (opens in a new tab)

How to prepare

  • Bring the exact editions on the bulletin: the 2023 NEC for electricians and the 2015 IMC with NFPA 54 (2009) for HVAC (the 2018 Kentucky Building Code references NFPA 54 2012, but the bulletin lists 2009). Kentucky amends the NEC, so read the state amendments.
  • Tab your books before exam day. Both ICC electrical and HVAC exams are open book with four-option questions.
  • Plan analysis is 20% and venting, duct and combustion air is 18%: tab IMC Chapters 5, 6, 7 and 8.
  • Know the principles and administration material (16%) from the Refrigeration and Air Conditioning Technology textbook and 815 KAR 8.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the 2015 IMC and NFPA 54 (2009). Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

  • International Mechanical Code (IMC), 2015 EditionEssential

    The edition named in the ICC Kentucky HVAC bulletin: ducts, venting, combustion air, boilers and exhaust.

    ICC store (opens in a new tab)

  • NFPA 54: National Fuel Gas Code, 2009 EditionEssential

    Gas piping and venting. The bulletin names the 2009 edition; the 2018 Kentucky Building Code references the 2012 edition. NFPA sells the current edition, so find the 2009 edition used or through NFPA.

    NFPA store (opens in a new tab)Free online access (current edition, not 2009) (opens in a new tab)

  • Refrigeration and Air Conditioning Technology, 8th or 9th Edition

    Textbook for HVAC principles and refrigeration. Either edition is listed in the bulletin.

Official reference list (as published by the testing agency)
  • International Mechanical Code (IMC), 2015 edition
  • NFPA 54: National Fuel Gas Code, 2009 edition (the edition on the ICC bulletin; the 2018 Kentucky Building Code references the 2012 edition)
  • Refrigeration and Air Conditioning Technology, 8th or 9th edition

What's on the exam

Official content outline from ICC (Pearson VUE) (number of questions per topic):

TopicQuestions
HVAC Principles, Terminology, Administration, and Safety16
HVAC Installation Requirements14
Venting, Duct, and Combustion Air18
Gas Piping8
HVAC Electrical13
Boilers, Exhaust Systems, and Fire Protection11
Plan Analysis20

Exam day details

  • Administered by ICC (Pearson VUE) for the Kentucky Department of Housing, Buildings and Construction.
  • Fee: $100 per exam on the ICC bulletin. DHBC application and license fees are separate. DHBC's own in-person HVAC exams are $50 (journeyman) and $150 (master).
  • 100 questions in 4 hours; 70% to pass (815 KAR 8:010).
  • Master license (KRS 198B.658): at least 18 years old, 2 years as a journeyman or equivalent experience, and insurance. The application is $250. One year of experience is 1,500 hours.
  • DHBC also runs in-person HVAC exams itself ($150 for the master exam, results by mail), using the same reference books.
  • Open book: bring your own copies of the listed references. Check the ICC bulletin for what tabbing and highlighting is allowed.
  • If you fail, you wait 10 days before you retake the exam.
  • A passing score is valid for 3 years (815 KAR 35:060 for electricians; 815 KAR 8:010 for HVAC).

Note: DHBC accepts Pearson VUE (ICC), Prov and NASCLA electrical exams, and gives its own in-person HVAC exams; Pearson VUE is the ICC route in the 1/17/2026 bulletin. The ICC bulletin is the source for the format and topic weights, and the 70% pass score is from 815 KAR 35:060 and 815 KAR 8:010.

Frequently asked questions

What is on the Kentucky master HVAC exam?

100 questions: plan analysis 20%, venting, duct and combustion air 18%, HVAC principles, terminology, administration and safety 16%, installation requirements 14%, HVAC electrical 13%, boilers, exhaust systems and fire protection 11% and gas piping 8%.

Which code editions are used?

The 2015 International Mechanical Code and the 2009 edition of NFPA 54, plus the Refrigeration and Air Conditioning Technology textbook (8th or 9th edition).

What does it cost?

The ICC bulletin lists $100 for the exam. DHBC's application fee for the master license is $250.

Free questions with answers

Show all 10 free questions and answers
  1. A mechanical permit has been issued but no work has started. Under the 2015 IMC as published, after how many days from the date of the permit does it expire and become void if work has not commenced?

    Answer: 180 days

    Section 106.4.3 states a permit becomes null and void if the authorized work is not commenced within 180 days of issuance, or if work is suspended or abandoned for 180 days after starting. The same 180-day figure appears in 106.3.3 for abandoned applications. Kentucky administers permits and inspections under Kentucky Building Code Chapter 1, and HVAC work must comply with KRS 198B and 815 KAR 8 (KBC 122.3), so local practice can differ from this model text.

    Reference: 2015 International Mechanical Code, 106.4.3

  2. A mechanical contractor starts installing ductwork before obtaining the required permit. Under the 2015 IMC as published, what penalty is assessed in addition to the regular permit fee?

    Answer: A fee equal to 100 percent of the usual permit fee

    Section 106.5.1 says anyone who commences work before obtaining the necessary permits is subject to 100 percent of the usual permit fee in addition to the required permit fees. A stop work order is a separate remedy in Section 108.5. Kentucky administers permits and inspections under Kentucky Building Code Chapter 1, and HVAC work must comply with KRS 198B and 815 KAR 8 (KBC 122.3), so local practice can differ from this model text.

    Reference: 2015 International Mechanical Code, 106.5.1

  3. A hydronic system uses 2-inch copper tubing run horizontally. Using IMC Table 305.4, what is the maximum support spacing?

    Answer: 10 feet

    Table 305.4 allows copper or copper-alloy tubing 1-1/2 inches and larger 10 feet horizontal. The 6-foot value is for tubing 1-1/4 inches and smaller, 8 feet is steel tubing, and 12 feet is copper or steel pipe (not tubing).

    Reference: 2015 International Mechanical Code, Table 305.4

  4. A return air grille is being located in a room that also holds a gas furnace with a draft hood. Under IMC 601.5, how far must the return air opening be from the open combustion chamber or draft hood of an appliance in the same room?

    Answer: At least 10 feet in any direction

    Section 601.5 requires return air openings to be at least 10 feet, measured in any direction, from an open combustion chamber or draft hood of another appliance in the same room or space. The rule protects against pulling flue products into the return.

    Reference: 2015 International Mechanical Code, 601.5

  5. Under IMC 601.5, return air must NOT be taken from which of the following locations?

    Answer: A bathroom

    Section 601.5 prohibits return air from a closet, bathroom, toilet room, kitchen, garage, boiler room, furnace room or unconditioned attic. Limited exceptions allow a kitchen return at least 10 feet from the cooking appliance and a dedicated garage-only system.

    Reference: 2015 International Mechanical Code, 601.5

  6. A gas piping system will operate at a maximum working pressure of 10 psig and is tested at the minimum test pressure with a mechanical gauge. Under NFPA 54, what is the highest scale reading the gauge may have?

    Answer: 75 psig

    Test pressure is 1-1/2 x 10 = 15 psig (NFPA 54 8.1.4.2; not less than 3 psi). A mechanical gauge must have a range whose highest end is not greater than 5 times the test pressure (8.1.4.1, same in the 2006 and 2024 editions): 5 x 15 = 75 psig. The 150 psig value is ten times the test pressure, 30 psig is three times the working pressure, and 15 psig is the test pressure itself.

    Reference: NFPA 54 (2006/2024 IBR copies; IFGC 2015 406.4 same rule), 8.1.4.1

  7. Under IMC 1005.1, how must shutoff valves be provided for a multiple-boiler installation?

    Answer: Each boiler must have its own shutoff valves in the supply and return piping

    Section 1005.1 requires every boiler to have a shutoff valve in the supply and return piping, and each boiler in a multiple installation must have individual valves. The only exception is a system with a single low-pressure steam boiler.

    Reference: 2015 International Mechanical Code, 1005.1

  8. A hermetic refrigerant motor-compressor has a nameplate rated-load current of 20.8 A and is the only load on a disconnect. Using NEC 440.12(A)(1), what is the minimum ampere rating of the disconnecting means?

    Answer: 23.9 A

    The ampere rating must be at least 115 percent of the nameplate rated-load current: 20.8 x 1.15 = 23.9 A. The 26.0 A value uses 125 percent, which is the conductor rule in 440.32, and 36.4 A uses the 175 percent overcurrent device figure.

    Reference: NFPA 70 (NEC) 2023, 440.12(A)(1)

  9. A closet holds a 100,000 Btu/h furnace and a 60,000 Btu/h water heater. Combustion air comes from outdoors through two openings directly to the outside, each covered by a metal louver of unknown free area. What is the minimum gross area of each opening?

    Answer: 53.3 square inches

    Two direct openings need 1 square inch per 4,000 Btu/h each (NFPA 54 9.3.3.1(1)): 160,000 / 4,000 = 40 square inches of free area. Where the louver free area is unknown, metal louvers are assumed to be 75 percent free (9.3.7.1): 40 / 0.75 = 53.3 square inches. Using 40 ignores the louver, 30 multiplies instead of dividing, and 160 is the total input in Btu/h divided by 1,000 rather than 4,000.

    Reference: NFPA 54 (2006/2024 IBR copies; IFGC 2015 304.10 same rule), 9.3.3.1 / 9.3.7.1

  10. A drawing shows a 150,000 Btu/h boiler in an enclosure with two outdoor-air openings, direct to the outside, covered with metal louvers of unknown free area. What gross opening size is required for each opening?

    Answer: 50 square inches

    Direct outdoor openings need 1 square inch per 4,000 Btu/h: 150,000 / 4,000 = 37.5 square inches of net free area each (NFPA 54 9.3.3.1(1)). With the free area unknown, metal louvers are assumed to be 75 percent free (9.3.7.1): 37.5 / 0.75 = 50 square inches. Using 25 percent would give 150, 75 doubles the net area, and 37.5 ignores the louver.

    Reference: NFPA 54 (2006/2024 IBR copies; IFGC 2015 304.6.1 same rule), 9.3.3.1 / 9.3.7.1

Sources

Questions last verified November 15, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.