Kentucky licensing exam

Kentucky Journeyman HVAC Exam: Practice Test & Licensing Guide

The ICC Kentucky Journeyman HVAC exam (598): 60 questions in 3 hours on the 2015 IMC and NFPA 54, covering venting, combustion air, gas piping, ducts, boilers and plan analysis. Open book, 70% to pass.

Questions
60
Time limit
3 hours
Passing score
70%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10HVAC Principles, Terminology, Administration, and Safety

Under the 2015 IMC as published, an installer keeps running a violation after the code official has served due notice. How does Section 108.4 treat each day the violation continues?

Requirements at a glance

AgencyKentucky DHBC, Division of HVAC; exam by ICC at Pearson VUE (DHBC also gives in-person exams)
Experience2 years under a master HVAC contractor; 1 year = 1,500 hours (KRS 198B.658)
Exam60 questions, 3 hours, 70% to pass
Books allowed2015 IMC, NFPA 54 (2009), Refrigeration and Air Conditioning Technology (8th or 9th ed.)
Fees$100 exam; $50 journeyman application

Applicants for a Kentucky journeyman HVAC license from the Department of Housing, Buildings and Construction.

How to get licensed, step by step

  1. Apply to DHBC

    Send DHBC your license application with proof of experience. Licenses are issued by the Department, not the testing vendor.

    Kentucky Department of Housing, Buildings and Construction (DHBC) (opens in a new tab)Kentucky Revised Statutes (KRS 227A, 198B, 318) (opens in a new tab)

  2. Schedule the journeyman HVAC exam

    Register and pay the $100 exam fee ($60 for Business and Law) for a Pearson VUE testing center. If you fail, you wait 10 days before you retest. Schedule through Pearson VUE (ICC); DHBC also accepts Prov and NASCLA electrical results.

    ICC: Kentucky candidate bulletin (1/17/2026) (opens in a new tab)DHBC: Electrical new application checklists (2/4/2025) (opens in a new tab)

  3. Pass and get licensed

    You need 70% to pass. Your passing score is valid for 3 years, so file your license application and any required insurance before it expires.

    Kentucky Department of Housing, Buildings and Construction (DHBC) (opens in a new tab)815 KAR: DHBC administrative regulations (opens in a new tab)

How to prepare

  • Bring the exact editions on the bulletin: the 2023 NEC for electricians and the 2015 IMC with NFPA 54 (2009) for HVAC (the 2018 Kentucky Building Code references NFPA 54 2012, but the bulletin lists 2009). Kentucky amends the NEC, so read the state amendments.
  • Tab your books before exam day. Both ICC electrical and HVAC exams are open book with four-option questions.
  • HVAC principles, terminology, administration and safety is the largest section at 23%.
  • Venting, combustion air and gas piping (21%) and boilers, duct, electrical and exhaust (21%) come from the IMC and NFPA 54.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the 2015 IMC and NFPA 54 (2009). Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

  • International Mechanical Code (IMC), 2015 EditionEssential

    The edition named in the ICC Kentucky HVAC bulletin: ducts, venting, combustion air, boilers and exhaust.

    ICC store (opens in a new tab)

  • NFPA 54: National Fuel Gas Code, 2009 EditionEssential

    Gas piping and venting. The bulletin names the 2009 edition; the 2018 Kentucky Building Code references the 2012 edition. NFPA sells the current edition, so find the 2009 edition used or through NFPA.

    NFPA store (opens in a new tab)Free online access (current edition, not 2009) (opens in a new tab)

  • Refrigeration and Air Conditioning Technology, 8th or 9th Edition

    Textbook for HVAC principles and refrigeration. Either edition is listed in the bulletin.

Official reference list (as published by the testing agency)
  • International Mechanical Code (IMC), 2015 edition
  • NFPA 54: National Fuel Gas Code, 2009 edition (the edition on the ICC bulletin; the 2018 Kentucky Building Code references the 2012 edition)
  • Refrigeration and Air Conditioning Technology, 8th or 9th edition

What's on the exam

Official content outline from ICC (Pearson VUE) (number of questions per topic):

TopicQuestions
HVAC Principles, Terminology, Administration, and Safety23
HVAC Installation Requirements15
Venting, Combustion Air, and Gas Piping21
Boilers, Duct, Electrical, and Exhaust21
Plan Analysis20

The outline totals 100; the other items on the 60-question exam are unscored or unassigned.

Exam day details

  • Administered by ICC (Pearson VUE) for the Kentucky Department of Housing, Buildings and Construction.
  • Fee: $100 per exam on the ICC bulletin. DHBC application and license fees are separate. DHBC's own in-person HVAC exams are $50 (journeyman) and $150 (master).
  • 60 questions in 3 hours; 70% to pass (815 KAR 8:010).
  • Journeyman license (KRS 198B.658): at least 18 years old and 2 years of experience under a master HVAC contractor. The application is $50. One year of experience is 1,500 hours.
  • DHBC also runs in-person HVAC exams itself ($50 for the journeyman exam, results by mail).
  • Open book: bring your own copies of the listed references. Check the ICC bulletin for what tabbing and highlighting is allowed.
  • If you fail, you wait 10 days before you retake the exam.
  • A passing score is valid for 3 years (815 KAR 35:060 for electricians; 815 KAR 8:010 for HVAC).

Note: DHBC accepts Pearson VUE (ICC), Prov and NASCLA electrical exams, and gives its own in-person HVAC exams; Pearson VUE is the ICC route in the 1/17/2026 bulletin. The ICC bulletin is the source for the format and topic weights, and the 70% pass score is from 815 KAR 35:060 and 815 KAR 8:010.

Frequently asked questions

What is on the Kentucky journeyman HVAC exam?

60 questions: HVAC principles, terminology, administration and safety 23%, venting, combustion air and gas piping 21%, boilers, duct, electrical and exhaust 21%, plan analysis 20% and installation requirements 15%.

How much experience do I need?

Two years under a master HVAC contractor, with 1,500 hours counting as one year (KRS 198B.658).

Are the books the same as the master exam?

Yes. The 2015 IMC, NFPA 54 (2009) and Refrigeration and Air Conditioning Technology (8th or 9th edition) are listed for both exams.

Free questions with answers

Show all 10 free questions and answers
  1. Under the 2015 IMC as published, an installer keeps running a violation after the code official has served due notice. How does Section 108.4 treat each day the violation continues?

    Answer: As a separate offense for each day

    Section 108.4 states that each day a violation continues after due notice has been served is deemed a separate offense. The fine and jail terms are left for the jurisdiction to fill in, but the per-day rule is part of the model text. Kentucky itself administers mechanical permits and inspections under Kentucky Building Code Chapter 1 and KRS 198B / 815 KAR 8, so local procedure can differ; the ICC exam tests the IMC as published.

    Reference: 2015 International Mechanical Code, 108.4

  2. Under the 2015 IMC as published, a contractor submits construction documents for a mechanical permit on a building more than two stories tall. Besides the usual scaled drawings, what must the documents indicate?

    Answer: Where mechanical penetrations will be made and how fire resistance is maintained

    IMC 106.3.1 requires construction documents for buildings more than two stories in height to show where penetrations will be made for mechanical systems and the methods for maintaining structural safety, fire-resistance rating and fireblocking. Equipment serial numbers, subcontractor names and past energy bills are not part of that requirement. Kentucky itself administers mechanical permits and inspections under Kentucky Building Code Chapter 1 and KRS 198B / 815 KAR 8, so local procedure can differ; the ICC exam tests the IMC as published.

    Reference: 2015 International Mechanical Code, 106.3.1

  3. Under the 2015 IMC as published, within how many days after the notice was served must an application for appeal of the code official's decision be filed?

    Answer: 20 days

    Section 109.1 requires the application, on a form from the code official, to be filed within 20 days after the notice was served. The board then meets within 10 days of the filing under Section 109.3, which is why 10 is a tempting wrong choice. Kentucky itself administers mechanical permits and inspections under Kentucky Building Code Chapter 1 and KRS 198B / 815 KAR 8, so local procedure can differ; the ICC exam tests the IMC as published.

    Reference: 2015 International Mechanical Code, 109.1

  4. An oil-fired unit heater is installed in a private garage where cars are parked. What is the minimum height above the floor required by Section 304.7 when the appliance is not otherwise protected from vehicle impact?

    Answer: 6 feet

    Section 304.7 requires appliances in private garages and carports to be installed with a minimum clearance of 6 feet above the floor, unless they are protected from vehicle impact and installed with the ignition source elevated per Section 304.3. The 8-foot value is the public garage rule of Section 304.6, and 18 inches is the ignition-source elevation of Section 304.3.

    Reference: 2015 International Mechanical Code, 304.7

  5. A 90,000 Btu/h furnace and a 36,000 Btu/h water heater share a mechanical room that will use only indoor air by the standard method. What minimum volume of indoor air is required?

    Answer: 6,300 cubic feet

    NFPA 54 9.3.2.1 (standard method) requires 50 cubic feet per 1,000 Btu/h of total input of all appliances in the space. Total input is 90,000 + 36,000 = 126,000 Btu/h, so 126 x 50 = 6,300 cubic feet. Using 25 per 1,000 gives 3,150, 40 per 1,000 gives 5,040 and 100 per 1,000 gives 12,600.

    Reference: NFPA 54 (2006/2024 IBR copies; IFGC 2015 304.5.1 same rule), 9.3.2.1

  6. A horizontal upper combustion air duct is being run from an outdoor wall louver to a furnace room. Which installation is required for the duct?

    Answer: It must not slope downward toward the source of combustion air

    NFPA 54 9.3.8.6: horizontal upper combustion air ducts must not slope downward toward the source of combustion air. Under 9.3.8.4 and 9.3.8.5, a single duct may not serve both the upper and lower openings when both are used, and ducts must not be screened where they end in an attic. A downward slope toward the outdoor source is exactly what the rule prohibits.

    Reference: NFPA 54 (2006/2024 IBR copies; IFGC 2015 304.11 same rule), 9.3.8.6

  7. A hermetic motor-compressor nameplate shows a rated-load current of 22.0 A and a branch-circuit selection current of 24.0 A. What is the minimum ampere rating of its disconnecting means (no unfused motor circuit switch exception used)?

    Answer: 27.6 amperes

    Section 440.12(A)(1) requires an ampere rating of at least 115 percent of the nameplate rated-load current or branch-circuit selection current, whichever is greater. The greater value is 24.0 A, so 1.15 x 24.0 = 27.6 A. Using 22.0 A gives 25.3 A, 125 percent of 24.0 A gives 30.0 A, and 175 percent of 24.0 A gives 42.0 A, which is the overcurrent device figure.

    Reference: 2023 National Electrical Code, 440.12(A)(1)

  8. A single motor-compressor has a rated-load current of 16 A and a branch-circuit selection current of 18 A. Applying Section 440.22(A) and its Exception No. 1 (next higher standard size), but not the starting-current Exception No. 2, what is the largest inverse-time breaker permitted?

    Answer: 35 amperes

    The device may be rated up to 175 percent of the greater of the rated-load current or branch-circuit selection current: 1.75 x 18 = 31.5 A. Exception No. 1 permits the next higher standard rating, and the next standard size above 31.5 A is 35 A (Section 240.6). The 40 A choice would need the 225 percent starting-current exception, and 31.5 A is not a standard rating.

    Reference: 2023 National Electrical Code, 440.22(A), 240.6(A)

  9. A plan shows an attic furnace reached by a passageway 24 feet long, 30 inches high and 22 inches wide, with continuous solid flooring 24 inches wide and a 30 by 30 inch level service space at the furnace. No exception applies. What is the code problem?

    Answer: The passageway is longer than the 20-foot maximum

    Section 306.3 limits an attic passageway to 20 feet measured along the centerline, with a 30-inch minimum height, 22-inch minimum width and solid flooring at least 24 inches wide. Only the length fails here. A passageway up to 50 feet is allowed only by exception, when it is at least 6 feet high and 22 inches wide for its whole length.

    Reference: 2015 International Mechanical Code, 306.3

  10. A 12 by 10 foot room with an 8-foot ceiling holds a 100,000 Btu/h furnace and a 50,000 Btu/h water heater, using indoor air by the standard method. How many additional cubic feet of volume from communicating spaces are needed?

    Answer: 6,540 cubic feet

    NFPA 54 9.3.2.1 (standard method) requires 50 cubic feet per 1,000 Btu/h, so 150 x 50 = 7,500 cubic feet. The room has 12 x 10 x 8 = 960 cubic feet, leaving 7,500 - 960 = 6,540 cubic feet to come from communicating spaces. The 7,500 value ignores the room volume, 2,790 uses 25 per 1,000 and 14,040 uses 100 per 1,000.

    Reference: NFPA 54 (2006/2024 IBR copies; IFGC 2015 304.5.1 same rule), 9.3.2.1

Sources

Questions last verified November 15, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.