The ICC Kansas Standard Master Mechanical exam (KGL): 100 open-book questions on the 2018 IMC and 2018 IFGC. 75% to pass.

Questions
100
Time limit
4 hours
Passing score
75%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10Administration and General Regulations

A contractor holds an unexpired mechanical permit but cannot start work within the allowed time because equipment is back-ordered. Which statement about an extension is correct under the IMC?

Requirements at a glance

AgencyYour Kansas city or county licenses you; the International Code Council (ICC) gives the exam through Pearson VUE. There is no statewide license
ExperienceSet by your city or county. Sedgwick County/Wichita: electrical master is journeyman plus 2 years; mechanical and plumbing master is 2 years as a journeyman or 4 years in the field
ExamKGL: 100 questions, 4 hours, 75%
Books allowed2018 International Mechanical Code and 2018 International Fuel Gas Code
Fees$115 per ICC exam (national T-series exams are $120), plus your city or county's certificate or license fees

HVAC and mechanical contractors applying for a master certificate or mechanical contractor license from a Kansas city or county that accepts the ICC standard exam, such as Sedgwick County/Wichita or Johnson County.

How to get licensed, step by step

  1. Ask your city or county which exam it accepts

    Kansas law lets each jurisdiction name the standard examinations it accepts as proof of competency. Confirm the exam and the experience rules before you pay.

    Sedgwick County MABCD: master and journeyman trade certificates (opens in a new tab)Johnson County Contractor Licensing: exam information (opens in a new tab)Kansas statute K.S.A. 12-1525 (standard examinations) (opens in a new tab)

  2. Register for the master mechanical exam (KGL) with ICC and Pearson VUE

    Create an ICC account, pick the Kansas standard exam from the Exam Catalog and schedule a Pearson VUE appointment. If you fail, wait 10 days to retake.

    Schedule with Pearson VUE (ICC exams) (opens in a new tab)ICC: State of Kansas exam bulletin (PDF) (opens in a new tab)

  3. Pass at 75% with your books

    The exam is open book with four-option multiple choice and no penalty for guessing. Bring only the approved references.

    ICC: State of Kansas exam bulletin (PDF) (opens in a new tab)

  4. Apply to your city or county

    Send your passing score and proof of experience to the jurisdiction, with its fee. It issues the certificate or license and sets renewal rules.

    Sedgwick County MABCD: master and journeyman trade certificates (opens in a new tab)Johnson County Contractor Licensing: exam information (opens in a new tab)

How to prepare

  • Study the edition the exam is built on: the 2017 NEC for electrical and the 2018 IPC, IMC and IFGC for plumbing and mechanical. Your city's adopted code can be newer.
  • The exam is open book, but there is not time to look up every answer. Tab your books by chapter and table before exam day.
  • The 2014 NEC / 2015 I-Code Kansas exams end December 1, 2026. If your jurisdiction wants a 2021-based exam, ask about the national ICC T-series instead.
  • Administration and general regulations (30%) and appliances and mechanical equipment (27%) are over half the exam: IMC Chapters 1, 3, 9, 10 and 11.
  • Fuel supply (6%) and combustion air (6%) come from IFGC Chapters 4 and 3 and IMC Chapter 7.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the 2018 IMC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

Official reference list (as published by the testing agency)
  • 2018 International Mechanical Code (IMC) (allowed in the exam room)
  • 2018 International Fuel Gas Code (IFGC) (allowed in the exam room)

What's on the exam

Official content outline from International Code Council (ICC), delivered by Pearson VUE, (number of questions per topic):

TopicQuestions
Administration and General Regulations30
Appliances and Mechanical Equipment27
Exhaust and Ventilation Systems11
Duct Systems12
Combustion Air6
Chimneys and Vents8
Fuel Supply Systems6

Exam day details

  • Administered by International Code Council (ICC), delivered by Pearson VUE, for Kansas cities and counties.
  • Fee: $115 to ICC through Pearson VUE per exam. Your city or county's license fees are separate.
  • 100 multiple-choice questions in 4 hours; 75 correct (75%) to pass.
  • Open book: bring the approved references. Questions are four-option multiple choice with no penalty for guessing; 75% to pass.
  • Kansas has no statewide electrician, plumber or mechanical license. ICC only tests; the city or county where you want to work sponsors you and issues the license.
  • If you fail, wait 10 days to retake.
  • The 2014 NEC / 2015 I-Code exams stop being offered December 1, 2026. These Kansas standard exams are based on the 2017 NEC and 2018 I-Codes; the national T-series exams cover the 2020 NEC and 2021 I-Codes.

Frequently asked questions

What's on the Kansas master mechanical exam?

100 questions by weight: administration and general regulations 30%, appliances and mechanical equipment 27%, duct systems 12%, exhaust and ventilation 11%, chimneys and vents 8%, combustion air 6% and fuel supply systems 6%.

Which code books does the Kansas mechanical exam use?

The 2018 International Mechanical Code and the 2018 International Fuel Gas Code.

Which jurisdictions accept it?

Johnson County recognizes the KGL master mechanical exam, and Sedgwick County/Wichita accepts the equivalent ICC mechanical exams. Confirm with the city or county where you will work.

Free questions with answers

Show all 10 free questions and answers
  1. A contractor holds an unexpired mechanical permit but cannot start work within the allowed time because equipment is back-ordered. Which statement about an extension is correct under the IMC?

    Answer: The code official may extend the time by up to 180 days for reasonable cause, and a permit may not be extended more than once

    Section 106.4.4 limits an extension to a period not exceeding 180 days where there is reasonable cause, allows only one extension per permit, and sets the fee at one-half of a new permit. The other choices invent longer or repeated extensions.

    Reference: 2018 International Mechanical Code, Section 106.4.4

  2. What is the minimum unobstructed width required for passageways around all sides of a boiler under the IMC, unless otherwise approved?

    Answer: 18 inches

    Section 1004.3 requires clearances around boilers that permit inspection, servicing, repair, replacement and visibility of all gauges, and passageways around all sides with an unobstructed width of at least 18 inches unless otherwise approved.

    Reference: 2018 International Mechanical Code, Section 1004.3

  3. Which boiler type is excepted from the low-water cutoff requirement in Section 1007.1?

    Answer: Coil-type and water-tube boilers that need forced circulation and have flow-sensing controls

    Section 1007.1 requires a low-water cutoff on steam and hot water boilers, excepting coil-type and water-tube boilers that require forced circulation of water through the boiler and are protected with a flow sensing control. Section 1007.2 requires these controls to stop combustion when the water level drops below the safe level or circulation stops.

    Reference: 2018 International Mechanical Code, Section 1007.1

  4. A 400-square-foot room is to be ventilated by natural means only. What is the minimum openable area to the outdoors required by the IMC?

    Answer: 16 square feet

    Section 402.2 requires the minimum openable area to the outdoors to be 4 percent of the floor area being ventilated. 400 square feet x 0.04 = 16 square feet. The 8 square foot answer uses 2 percent.

    Reference: 2018 International Mechanical Code, Section 402.2

  5. An office space of 2,000 square feet has the Table 403.3.1.1 default occupant density of 5 people per 1,000 square feet, a people rate of 5 cfm per person and an area rate of 0.06 cfm per square foot. What is the breathing zone outdoor airflow, Vbz = Rp x Pz + Ra x Az?

    Answer: 170 cfm

    Population Pz = 5 x (2,000 / 1,000) = 10 people. Vbz = 5 cfm x 10 + 0.06 cfm/ft2 x 2,000 ft2 = 50 + 120 = 170 cfm. The 50 cfm answer counts only the people component and 120 cfm counts only the area component.

    Reference: 2018 International Mechanical Code, Section 403.3.1.1.1.1, Table 403.3.1.1

  6. From which space may return air be taken for a forced-air system under Section 601.5, without relying on an exception?

    Answer: A conditioned living room served by the system

    Section 601.5 prohibits taking return air from a closet, bathroom, toilet room, kitchen, garage, boiler room, furnace room or unconditioned attic (with limited exceptions such as a kitchen opening 10 feet or more from cooking appliances). Return air from a conditioned living space is acceptable.

    Reference: 2018 International Mechanical Code, Section 601.5

  7. A contractor proposes to set a gas-fired duct furnace inside the above-ceiling return-air plenum of an office and to let that plenum continue across a fire barrier into the adjacent fire area. How does IMC Section 602.1 treat this plan?

    Answer: Not acceptable: plenums are limited to one fire area, and fuel-fired appliances shall not be installed within a plenum

    Section 602.1 limits plenums to one fire area, requires air systems to be ducted from the boundary of the fire area served to the air-handling equipment, and prohibits fuel-fired appliances within a plenum. The flame spread and smoke-developed limits in Section 602.2 apply to materials exposed in a plenum but do not permit either part of this plan.

    Reference: 2018 International Mechanical Code, Section 602.1

  8. A furnace of 80,000 Btu/h input and a water heater of 40,000 Btu/h input share a room that will use indoor air by the Standard Method of IFGC Section 304.5.1. What minimum room volume is required?

    Answer: 6,000 cubic feet

    Section 304.5.1 requires 50 cubic feet per 1,000 Btu/h of the appliance input rating, summed for all appliances in the space. Total input = 80,000 + 40,000 = 120,000 Btu/h, so 120 x 50 = 6,000 cubic feet. 4,000 cubic feet counts only the furnace (80 x 50), and 12,000 cubic feet doubles the 50 cubic foot rate.

    Reference: 2018 International Fuel Gas Code, Section 304.5.1

  9. A gas vent terminates near a forced air inlet that is 8 feet away horizontally. What does the IFGC require?

    Answer: The vent must terminate at least 3 feet above the forced air inlet

    Section 503.6.8 requires gas vents to terminate not less than 3 feet above any forced air inlet located within 10 feet. A vent 8 feet from the inlet is within the 10 foot distance.

    Reference: 2018 International Fuel Gas Code, Section 503.6.8

  10. A gas piping system with a proposed maximum working pressure of 5 psig is to be pressure tested before use. What is the minimum test pressure under IFGC 406.4.1?

    Answer: 7.5 psig

    Section 406.4.1 requires a test pressure of not less than 1-1/2 times the proposed maximum working pressure, and not less than 3 psig. 1.5 x 5 = 7.5 psig. 3 psig is only the floor value, which governs for working pressures of 2 psig or less.

    Reference: 2018 International Fuel Gas Code, Section 406.4.1

Sources

Questions last verified November 4, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.