Requirements at a glance
| Agency | Georgia Construction Industry Licensing Board (Division of Electrical Contractors); exams by PSI |
|---|---|
| Experience | Age 21; 4 years of primary electrical experience (up to 1 year of secondary experience or education may count) with installations beyond single-phase, 200 amps; at least one of the 3 references from a licensed electrical contractor |
| Exam | 140 questions, 8 hours in two 4-hour parts, open book, 70 to pass |
| Books allowed | 2023 NEC (or NEC Handbook) with Georgia amendments, American Electricians' Handbook 17th Edition, the NASCLA Georgia guide, IRS Circular E, 29 CFR 1926 and Ugly's 2023 |
| Fees | $40 application fee ($30 plus a $10 processing fee) per the Secretary of State form. The PSI exam fee and license fee are not published in the candidate bulletin; confirm them with PSI and the Board. |
Qualifying agents for an unrestricted Georgia electrical contractor license from the Construction Industry Licensing Board. Class II covers work of any size and includes three-phase motors, transformer banks and special equipment.
Official links
How to get licensed, step by step
Apply to the Board
Submit the application, three references on the Board's form and the $40 fee to the Construction Industry Licensing Board (Macon; (404) 424-9966). The Board must approve you before you can register with PSI.
Georgia Division of Electrical Contractors (CILB) (opens in a new tab)Georgia Rules 121-3 (CILB license requirements) (opens in a new tab)
Register with PSI
After approval, register and pay PSI online or at 855-898-0711. Bring the allowed references and a silent, non-programmable calculator.
Schedule with PSI (Georgia CILB exams) (opens in a new tab)PSI bulletin: Georgia electrical contractors (opens in a new tab)
Take the exam
Scaled score, 70 to pass. If you fail twice, the PSI bulletin requires a Board-approved review course before a third attempt.
PSI bulletin: Georgia electrical contractors (opens in a new tab)
Finish licensing
Send your results and the license fee to the Board. Georgia has no statewide journeyman or master electrician license; local jurisdictions license those workers.
Georgia Division of Electrical Contractors (CILB) (opens in a new tab)
How to prepare
- Georgia's exams are scaled with 70 to pass. The Board's 2026 reference lists apply to exams through December 31, 2026; check for the updated list if you test later.
- Tab your books with permanent tabs before exam day. Highlighting and underlining are allowed; notes, sticky flags and loose papers are not.
- Interior electrical systems (23) and transformers (21) are the biggest technical sections. Class II adds delta and star transformer banks and three-phase motor connections.
- Special equipment, conditions and locations (21) covers health care, pools, hazardous locations, fire pumps and signs: tab NEC Chapters 5 through 7.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below, and most questions come from the 2023 NEC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
NFPA 70: National Electrical Code (NEC), 2023 Edition (or the NEC Handbook), with Georgia amendmentsEssential
Allowed in the exam room. The Georgia State Electrical Code. Tab Articles 100, 110, 210, 220, 230, 240, 250, 310, 430, 450 and Chapter 9.
NFPA store (opens in a new tab)Free online access (opens in a new tab)
American Electricians' Handbook, 17th Edition (2021), McGraw-Hill
On the electrical exam list. Trade practice, motors, transformers and controls.
Contractors Guide to Business, Law, and Project Management: Georgia Construction Industry Licensing Board, 5th Edition (NASCLA)
On the Board's reference lists for the electrical, conditioned air and plumbing exams.
Ugly's Electrical References, 2023 Edition
On the electrical and low voltage lists. Formulas for voltage drop, power, motors and transformers.
Official reference list (as published by the testing agency)
- Georgia State Electrical Code: 2023 NEC or NEC Handbook with Georgia amendments (NFPA 70)
- American Electricians' Handbook, 17th Edition (2021), McGraw-Hill
- Contractors Guide to Business, Law, and Project Management, Georgia Construction Industry Licensing Board, 5th Edition (NASCLA)
- Employer's Tax Guide (IRS Circular E, Publication 15), 2025 or 2026
- 29 CFR Part 1926 (OSHA construction standards)
- Ugly's Electrical References, 2023
What's on the exam
Official content outline from PSI Services (number of questions per topic):
| Topic | Questions | |
|---|---|---|
| Comply with Laws | 10 | |
| Comply with Regulations | 9 | |
| Comply with Administrative Requirements | 6 | |
| Plan and Organize Work | 5 | |
| Maintain Basic Electrical Circuits | 14 | |
| Install and Maintain Electrical Controls and Devices | 15 | |
| Install and Maintain D-C and A-C Rotating Equipment | 16 | |
| Install, Size, and Maintain Transformers | 21 | |
| Install and Maintain Interior Electrical Systems | 23 | |
| Special Equipment, Conditions, and Locations | 21 |
Exam day details
- Administered by PSI Services for the Georgia Construction Industry Licensing Board.
- Fee: The Board's initial application fee is $40 ($30 plus a $10 processing fee). The PSI exam fee and the license fee are not published in the candidate bulletin, so check PSI and the Board before you apply.
- 140 scored questions plus 22 unscored pretest questions in 8 hours, split into two 4-hour parts with a break.
- Open book: bring only the references on the Board's list (listed here for exams through December 31, 2026). Highlighting, underlining and permanent tabs are allowed; notes and extra papers are not.
- Class II adds topics Class I does not test: three-phase motor connections, delta and star transformer banks, and fire pump and other special systems.
- The Board must approve your application before you can register with PSI. Scores are scaled and you need 70 to pass.
- The time limit includes the unscored beta (pretest) questions mixed into the exam.
- If you fail twice, the PSI bulletin requires a Board-approved review course before a third attempt.
- Georgia has no statewide journeyman or master electrician exam and no statewide HVAC technician exam; local jurisdictions license those workers.
Frequently asked questions
What's on the Georgia Class II electrical contractor exam?
140 scored questions: laws 10, regulations 9, administrative requirements 6, planning and organizing work 5, basic circuits 14, controls and devices 15, rotating equipment 16, transformers 21, interior electrical systems 23 and special equipment, conditions and locations 21.
Does Georgia have a journeyman or master electrician exam?
No. The state licenses electrical contractors only (Class I restricted and Class II unrestricted). Local jurisdictions license journeymen and masters.
Which NEC edition does the Georgia exam use?
The 2023 NEC (or the NEC Handbook) with Georgia amendments, per the Board's 2026 reference list.
Free questions with answers
Show all 10 free questions and answers
A Georgia Class I Electrical Contractor licensee is asked to bid a job. Which job is outside what a Class I license allows?
Answer: A new 3-phase, 400-ampere service for a machine shop
Class I licenses are restricted to single-phase installations that do not exceed 200 amperes at the service drop or service lateral; Class II licenses are unrestricted. A 3-phase 400-ampere service exceeds both limits and needs a Class II license.
Reference: Ga. Comp. R. & Regs. 121-3-.01, 121-3-.01(1)
An employee is admitted to a hospital as an in-patient after an electrical contact injury on the job. Under 29 CFR 1904.39, within what time must the employer report it to OSHA?
Answer: Within 24 hours
Section 1904.39 requires reporting each work-related fatality within 8 hours and each in-patient hospitalization, amputation or loss of an eye within 24 hours of learning of it. Seven days is the deadline for entering a recordable case on the 300 log.
Reference: 29 CFR Part 1904 (OSHA recordkeeping), 29 CFR 1904.39
What is the purpose of a liquidated damages clause in a construction contract?
Answer: It sets in advance a daily dollar amount the contractor owes the owner if substantial completion is late
Liquidated damages are a pre-agreed amount, usually per calendar day, that compensates the owner for delay past the contract completion date. They are not profit, early-completion pay or a retainage rule.
Reference: General business practice, General business practice: liquidated damages
What is the purpose of a submittal on an electrical project?
Answer: To give the engineer product data and shop drawings for review before ordering
A submittal is the contractor's package of data sheets and shop drawings sent for review so the design team can confirm the equipment matches the plans and specifications before it is ordered or built.
Reference: General business practice, General business practice: submittal process
Three resistors of 10, 15 and 25 ohms are connected in series across a 120-volt source. What is the voltage drop across the 15-ohm resistor?
Answer: 36 volts
Total resistance is 10 + 15 + 25 = 50 ohms. Current is 120 / 50 = 2.4 A, the same in every series element. The 15-ohm drop is 2.4 x 15 = 36 V. 24 V is the drop across the 10-ohm resistor, 48 V would need a 20-ohm resistor (the 25-ohm drop is 60 V), and 120 V is the whole source.
Reference: General electrical theory, Series circuit calculation (Ohm's law)
An on-delay time-delay relay has a normally open timed-closing contact. What happens when its coil is energized?
Answer: The contact closes after the preset delay and stays closed while the coil remains energized
An on-delay (timed-closing) relay starts timing when the coil is energized and changes contact state only after the delay expires. When the coil is de-energized the contacts return immediately. The pictured behavior of closing immediately then opening describes an off-delay or one-shot timer.
Reference: General electrical practice, Time delay relay
A 15-horsepower, 460-volt, three-phase squirrel-cage motor has a Table 430.250 full-load current of 21 amperes. What is the maximum rating of an inverse-time circuit breaker for branch-circuit short-circuit and ground-fault protection, using Table 430.52 and the exception for a next higher standard size?
Answer: 60 amperes
Table 430.52 permits 250 percent of full-load current for an inverse-time breaker: 21 x 2.5 = 52.5 A. That is not a standard rating, so 430.52(C)(1) Exception 1 permits the next higher standard size, 60 A (Table 240.6(A)). Rounding down to 50 A is a common mistake; 40 A is about 175 percent.
Reference: NEC 2023, 430.52(C)(1) and Table 430.52
What is the full-load primary current of a 50-kVA single-phase transformer with a 480-volt primary?
Answer: About 104 amperes
Single-phase current = VA / E = 50,000 / 480 = 104.2 A. 208 A is the secondary current at 240 V, and 60 A comes from using 1.732 on a single-phase unit.
Reference: General electrical theory, Transformer current formula
A 40,000-sq-ft warehouse is being wired. Using the unit load in NEC 2023 Table 220.42(A), what minimum general lighting load must be used for the feeder calculation?
Answer: 48,000 VA
Table 220.42(A) lists 1.2 VA per sq ft (13 VA per sq m) for a warehouse: 40,000 x 1.2 = 48,000 VA. The table note says the 125 percent continuous-load multiplier is already included, so multiplying again (60,000 VA) double-counts it. 10,000 VA and 12,500 VA use the old 0.25 VA per sq ft storage value from earlier editions.
Reference: NEC 2023, 220.42(A) and Table 220.42(A)
What is the maximum overcurrent protective device rating for an arc welder with a rated primary current of 50 amperes, under 630.12(A)?
Answer: 100 amperes
Overcurrent protection for the welder supply is limited to 200 percent of the rated primary current: 50 x 2.00 = 100 A. A lower rating is allowed but must carry the welder's starting current; 150 A is 300 percent.
Reference: NEC 2023, 630.12(A)
Sources
- PSI: Georgia Electrical Contractors Candidate Information Bulletin (Class I and Class II) (opens in a new tab)
- Georgia State Board of Electrical Contractors (Secretary of State) (opens in a new tab)
- Georgia Rules 121-3 (Construction Industry Licensing Board) (opens in a new tab)
Questions last verified November 14, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.