Requirements at a glance
| Agency | Florida DBPR, Electrical Contractors' Licensing Board (ECLB); Pearson VUE delivers the exams |
|---|---|
| Exams | Electrical Business (50 questions, 2.5 hours, 75%) plus a technical exam |
| Books allowed | Contractors Manual (2021), Florida Statutes Chapters 489 Part II, 440 and 713, Chapter 61G6 FAC and IRS Circular E |
| Fees | $196 application and $67.25 exam fee to DBPR, plus Pearson VUE ($82.50 technical, $41.25 business); $291 certification fee after you pass. Rule 61G6-8.001 |
Every candidate for ECLB certification as an electrical contractor, along with a technical exam.
Official links
How to get licensed, step by step
Apply to the ECLB
Submit your application and experience documentation to DBPR. Confirm the current experience requirements on the DBPR page.
Florida DBPR: electrical examinations (ECLB) (opens in a new tab)Florida Statutes Chapter 489 (contracting) (opens in a new tab)
Schedule with Pearson VUE
After DBPR approves you, schedule the exam with Pearson VUE. Passing is 75%.
Finish licensing
Send your results to DBPR and complete the remaining license requirements such as insurance and financial responsibility.
Florida DBPR: electrical examinations (ECLB) (opens in a new tab)
How to prepare
- The exams are open book, but only the approved, bound references on the January 2026 to December 2026 list are allowed. Underline or highlight, but no handwritten notes and no loose tabs.
- Florida uses the 2023 NEC until August 21, 2027, then the 2026 NEC.
- Payroll and sales tax (6 to 8 questions), estimating and bidding (5 to 7) and contracting laws and rules (5 to 7) are the biggest sections.
- Know Chapter 713 for liens and Chapter 440 for workers' compensation.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below, and most questions come from the Contractors Manual. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
Contractors Manual, Association of Builders and Contractors Institute (ABC)Essential
On the Business and Finance, general contractor and electrical business reference lists. The 2025 edition is used from February 1, 2026.
Florida Statutes Chapter 489 (contracting)
Free online. The law behind CILB and ECLB certification, discipline and contracts.
Florida Statutes Chapter 489 (contracting) (opens in a new tab)
Official reference list (as published by the testing agency)
- Contractors Manual, Association of Builders and Contractors Institute (2021 edition)
- Florida Statutes Chapter 489, Part II, and Chapters 440 and 713
- Florida Administrative Code Chapter 61G6
- IRS Circular E
What's on the exam
Official content outline from Pearson VUE (number of questions per topic):
| Topic | Questions | |
|---|---|---|
| Maintaining Cash Flow | 4 | |
| Estimating and Bidding | 6 | |
| Contracts and Agreements | 5 | |
| Purchasing Control | 1 | |
| Contract Scheduling | 4 | |
| Insurance and Bonding | 5 | |
| Contracting Laws and Rules | 6 | |
| Personnel Management | 4 | |
| Payroll and Sales Tax | 7 | |
| Financial Statements | 5 | |
| Management Accounting | 3 |
Exam day details
- Administered by Pearson VUE for the Florida Electrical Contractors' Licensing Board (ECLB).
- Fee: $196 application fee and $67.25 exam fee to DBPR, plus Pearson VUE's administration fee: $82.50 for the technical/safety exam and $41.25 for the business exam. After you pass, the certification fee is $291 plus a $5 unlicensed-activity fee.
- 50 questions in 2.5 hours; 75% to pass. The board publishes the topics as ranges of questions; the weights here are the midpoints.
- Open book with approved references only. They must be bound and stay bound; underlining and highlighting are allowed, handwritten notes and loose tabs are not. The reference lists change each January.
- A score of 75% is required to pass. Questions are equally weighted and pretest items are not scored.
- DBPR approves your application first, then Pearson VUE schedules and delivers the exam.
- Electrical contractor candidates take a business exam and a technical exam.
- Fees are set by Board rule (61G6-8.001) and DBPR's test-administration fee table; confirm the current amounts with DBPR before you apply.
Frequently asked questions
What is on the Florida electrical business exam?
Payroll and sales tax 6 to 8 questions, estimating and bidding 5 to 7, contracting laws and rules 5 to 7, contracts and agreements 4 to 6, insurance and bonding 4 to 6, financial statements 4 to 6, and smaller sections on cash flow, scheduling, personnel, management accounting and purchasing.
Is this the same as the CILB Business and Finance exam?
No. Electrical contractors take their own shorter business exam from the ECLB. CILB trades take Business and Finance.
Free questions with answers
Show all 10 free questions and answers
A contractor starts the month with $20,000 cash. Expected collections for the month are $35,000 and expected payments (payroll, materials, overhead) are $41,000. What is the projected ending cash balance?
Answer: $14,000
Ending cash = beginning cash + receipts - disbursements = $20,000 + $35,000 - $41,000 = $14,000. $6,000 ignores beginning cash and reverses the sign, $26,000 adds disbursements and subtracts receipts, and $96,000 adds everything.
Reference: General business practice, Cash-flow forecasting
A takeoff shows 240 feet of EMT is needed. The estimator adds 5 percent for waste and cuts. What quantity goes in the estimate?
Answer: 252 feet
Waste is 240 x 0.05 = 12 feet, so the quantity is 240 + 12 = 252 feet. Adding 5 feet, subtracting the waste, or using the raw takeoff each ignores the allowance correctly applied as a percentage.
Reference: General business practice, Quantity takeoff and waste
A subcontractor signs a progress-payment waiver and release of lien that states it is effective for labor and materials furnished through March 31. On what does the waiver NOT operate?
Answer: Retainage and work furnished after March 31
Under s. 713.20(2), a lien right may be waived only to the extent of labor, services or materials already furnished, and a waiver made in advance is unenforceable. The statutory progress-payment form in s. 713.20(4) states that it does not cover any retention or labor, services or materials furnished after the date specified. Work through March 31 and the payment received are what the waiver releases.
Reference: Florida Statutes (2025), s. 713.20(2), (4)
Using the same network (A 3 days, then B 4 days and C 6 days in parallel, then D 2 days), how much total float does activity B have?
Answer: 2 days
The path through B totals 9 days and the critical path through C totals 11 days, so B can slip 11 - 9 = 2 days without delaying the project. B is not critical (0 is wrong), and 4 and 6 are durations rather than float.
Reference: General business practice, Float on parallel paths
A subcontractor is a corporation whose officer has elected to be exempt from workers' compensation. What must the subcontractor give the contractor under s. 440.10(1)(c)?
Answer: A copy of the officer's certificate of exemption
Section 440.10(1)(c) requires a contractor to demand evidence of workers' compensation from a subcontractor and says a corporate subcontractor with an exempt officer must provide a copy of the certificate of exemption. Without valid proof the contractor risks liability under (1)(b).
Reference: Florida Statutes (2025), s. 440.10(1)(c)
How many classroom hours of continuing education must a licensed electrical contractor complete each biennium for renewal?
Answer: 11 hours
Section 489.517(3)(b) requires electrical contractors to complete at least 11 classroom hours of 50 minutes each per biennium; s. 489.517(4)(b)2. says at least 7 of them must be technical, with 1 hour each on workers' compensation, workplace safety and business practices. The 7-hour figure applies to specialty and alarm system contractors.
Reference: Florida Statutes (2025), s. 489.517(3)(b), (4)(b)2.
Within how many business days after an employee starts work must the employer complete Section 2 of Form I-9 to verify identity and work authorization?
Answer: 3 business days
Under 8 CFR 274a.2(b)(1)(ii), the employer must examine the employee's identity and work-authorization documents and complete Section 2 of Form I-9 within three business days of the hire; the employee completes Section 1 no later than the first day of work. Pub. 15 (Hiring New Employees) reminds employers to complete Form I-9 but refers to USCIS for the rules. 24 hours, 7 business days and 30 days are not the federal deadline.
Reference: 8 CFR (current), 8 CFR 274a.2(b)(1)(ii)
An electrician is paid $30.00 per hour and works 46 hours in a workweek. Overtime is paid at 1.5 times the regular rate for hours over 40. What is gross pay for the week?
Answer: $1,470
Regular pay = 40 x $30 = $1,200. Overtime = 6 hours x ($30 x 1.5 = $45) = $270. Total = $1,470. $1,380 pays all 46 hours at straight time, $2,070 pays all 46 hours at the overtime rate, and $1,290 pays only the half-time premium on the 6 extra hours.
Reference: General business practice, Overtime pay under the FLSA
A company has total assets of $640,000 and total liabilities of $410,000. What is the owner's equity?
Answer: $230,000
Assets = liabilities + equity, so equity = $640,000 - $410,000 = $230,000. $1,050,000 adds the figures, and $410,000 and $640,000 are the liabilities and assets themselves.
Reference: General business practice, The accounting equation
Why should a contractor track job costs by cost code and compare them with the estimate?
Answer: It shows where actual costs differ from the estimate, which improves later bids and job control
Job costing by cost code shows which items ran over or under budget while the work is under way and gives real production rates for future estimates. It supplements, not replaces, payroll records and financial statements.
Reference: General business practice, Job costing
Sources
- Florida DBPR: electrical examinations (ECLB) (opens in a new tab)
- Pearson VUE: Florida electrical exams (opens in a new tab)
- Florida Statutes Chapter 489 (contracting) (opens in a new tab)
Questions last verified November 15, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.