Requirements at a glance
| Agency | Arizona Registrar of Contractors (ROC); trade exam by PSI |
|---|---|
| Exams | 100 questions, 240 minutes, 70%, plus the online Statutes and Rules Exam (SRE) |
| Books allowed | 2018 IPC, IFGC and IMC, NFPA 13/13D/13R, ADEQ on-site wastewater rules, 29 CFR 1926 |
| Fees | $66 PSI trade exam + $61 SRE, plus ROC license fees and bond |
Qualifying parties for an Arizona C-37 Plumbing (Commercial) or CR-37 Plumbing (dual) contractor license.
Official links
How to get licensed, step by step
Pick your classification and qualifying party
Find your classification on the ROC's list. The qualifying party (an owner or regular employee of the business) must have the required trade experience and takes the exams for the business.
Pass the Statutes and Rules Exam (SRE)
Buy the ROC's online SRE course and exam through GMetrix ($61), work through the course, then take the final exam. 70% to pass, one attempt per purchase.
Buy the Statutes and Rules Exam (GMetrix) (opens in a new tab)
Schedule the C-37 trade exam with PSI
Book online with PSI ($66, or $116 for two exams). Bring the allowed references, bound and tabbed. If you fail, wait 30 days to retake.
Schedule with PSI (Arizona contractors) (opens in a new tab)PSI content outline: C-37/CR-37 Plumbing (Commercial) (opens in a new tab)
Apply to the ROC
Submit your application with your passing score reports within two years of passing, plus the license bond, fees and business documents the ROC asks for.
How to prepare
- Bring the exact code editions on PSI's list. Arizona's trade exams use older editions (2017 NEC, 2018 I-codes); a newer book gives some wrong answers.
- Bind or spiral any printed references, and tab them with permanent tabs before exam day. Sticky notes are removed at check-in.
- Practice finding answers fast. On a 100-question, 4-hour exam you have 2.4 minutes per question, and some of that goes to unscored items.
- Septic and sewer is 11 questions, from ADEQ's rules (AAC R18-9), which most plumbers haven't read. Print and tab them.
- Fuel gas is 11 questions: practice gas pipe sizing with the IFGC tables.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below, and most questions come from the 2018 IPC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
2018 International Plumbing Code (IPC)Essential
Allowed in the exam room. Most drainage, venting, water supply and fixture questions.
ICC store (opens in a new tab)Read free (opens in a new tab)
2018 International Fuel Gas Code (IFGC)
Allowed in the exam room. Gas pipe sizing tables, venting and appliance rules.
ICC store (opens in a new tab)Read free (opens in a new tab)
2018 International Mechanical Code (IMC)
Allowed in the exam room. Ventilation, ducts, combustion air, hydronics and refrigeration.
ICC store (opens in a new tab)Read free (opens in a new tab)
ADEQ on-site wastewater rules (AAC Title 18, Chapter 9, Article 3)
Allowed in the room; source of the septic questions. Print the Article 3 rules and bind them.
ADEQ on-site wastewater rules, AAC Title 18 Chapter 9 (PDF) (opens in a new tab)
NFPA 13 (2016), 13D (2007) and 13R (2007) sprinkler standards
Allowed in the room for the fire sprinkler questions.
29 CFR 1926 (OSHA Construction Standards), sections on your reference list
Trenching, scaffolds, fall protection and ladders. Print just the listed sections.
Official reference list (as published by the testing agency)
- International Plumbing Code (IPC), 2018; International Fuel Gas Code (IFGC), 2018; International Mechanical Code (IMC), 2018 (allowed in the exam room)
- NFPA 13 (2016), NFPA 13D (2007) and NFPA 13R (2007) sprinkler standards (allowed in the exam room)
- ADEQ on-site wastewater rules, Arizona Administrative Code Title 18, Chapter 9 (allowed in the exam room)
- 29 CFR Part 1926, OSHA Construction (allowed in the exam room)
- Mathematics for Plumbers and Pipefitters; IPT's Pipe Trades Handbook; Modern Hydronic Heating; Arizona 811 Blue Stake brochure (not allowed in the room)
What's on the exam
Official content outline from PSI Services (number of questions per topic):
| Topic | Questions | |
|---|---|---|
| Drainage, Waste and Vents | 15 | |
| Indirect Waste | 4 | |
| Water Supply Systems | 12 | |
| Backflow Prevention | 5 | |
| Roof Drains and Storm Drainage | 5 | |
| Plumbing Fixtures and Water Heaters | 6 | |
| General Knowledge | 8 | |
| Specialty Plumbing, Interceptors and Traps | 5 | |
| Fuel Gas | 11 | |
| Septic and Sewer | 11 | |
| Hydronics | 6 | |
| Fire Sprinklers | 6 | |
| Excavation | 6 |
Exam day details
- Administered by PSI Services for the Arizona Registrar of Contractors (ROC).
- Fee: $66 to PSI ($116 for two exams taken together). The ROC license application fee is separate.
- 100 scored questions in 240 minutes, 70% to pass.
- Open book: bring your own bound copies of the allowed references. You may highlight and add permanent tabs beforehand, but not write in them during the exam.
- PSI adds 5 to 10 unscored trial questions, which count against your time.
- If you fail, wait 30 days to retake; after a third failure the wait is 90 days. Submit your ROC application within two years of passing.
- You also need Arizona's Statutes and Rules Exam (SRE), taken online through the ROC. The ROC can waive the trade exam if you were the qualifying party on a license in the same classification in the last five years.
Frequently asked questions
What's on the Arizona C-37 plumbing exam?
100 questions: drainage, waste and vents 15, water supply 12, fuel gas 11, septic and sewer 11, general knowledge 8, and smaller sections on hydronics, fire sprinklers, excavation, backflow, storm drainage, fixtures and water heaters, interceptors and indirect waste.
Which plumbing code does the Arizona exam use?
The 2018 International Plumbing Code, with the 2018 IFGC and IMC, the NFPA 13, 13D and 13R sprinkler standards, and ADEQ's on-site wastewater rules (AAC Title 18, Chapter 9).
Does Arizona license journeyman plumbers?
Not statewide. The ROC licenses plumbing contractors; the qualifying party takes this exam. Check your city for any local requirements.
Free questions with answers
Show all 10 free questions and answers
A 4-bedroom single-family dwelling on a conventional septic system has these fixtures: three 1.6-gpf water closets, three single lavatories, one double lavatory in the master bedroom, two bathtubs, one single-stall shower, a kitchen sink with dishwasher, a clothes washer, a bar sink and a utility tub. Using the ADEQ septic tank sizing criteria, what are the minimum design liquid capacity and the design flow?
Answer: 1250 gallons and 600 gal/day
Fixture count from R18-9-A314(4)(a)(ii): water closets 3 x 3 = 9, single lavatories 3 x 1 = 3, double master lavatory 1, bathtubs 2 x 2 = 4, shower 2, kitchen sink with dishwasher 2, clothes washer 2, bar sink 1, utility tub 2, for a total of 26. In the table, a 4-bedroom home with 28 fixture units or less needs a 1250-gallon tank and has a 600 gal/day design flow. The 1500-gallon / 750 gal/day line applies only above 28 fixture units. The 1000-gallon / 450 gal/day line is for a 3-bedroom home.
Reference: Ariz. Admin. Code Title 18, Ch. 9 (ADEQ on-site wastewater rules), R18-9-A314(4)(a)
A sewer trench in Type B soil is 10 feet deep with a 4-foot-wide bottom. It will be protected by sloping both sides at the maximum allowable simple slope from OSHA Appendix B. What is the minimum width at the top of the excavation?
Answer: 24 feet
Appendix B, Table B-1 and Figure B-1.2 allow a maximum simple slope of 1:1 (H:V) in Type B soil for excavations 20 feet deep or less. Each side sets back 1 x 10 = 10 feet, so the top width = 4 + 10 + 10 = 24 feet. Using the Type A slope of 3/4:1 gives 4 + 7.5 + 7.5 = 19 feet. Using the Type C slope of 1-1/2:1 gives 34 feet. Sloping only one side gives 14 feet.
Reference: 29 CFR 1926 Subpart P, Appendix B (Sloping and Benching), Table B-1; Figure B-1.2
A 12,000 sq ft flat roof is designed for a 100-year, 1-hour rainfall rate of 3 inches per hour. One inch per hour on one square foot equals about 0.0104 gpm. Using IPC Table 1106.2, what is the minimum size of the horizontal building storm drain at 1/4 inch per foot slope?
Answer: 6 inches
Flow = 12,000 sq ft x 3 in/hr x 0.0104 = about 374 gpm. In Table 1106.2, the 1/4 in/ft column gives 5-inch = 234 gpm (too small) and 6-inch = 487 gpm, so 6 inches is the minimum. The 8-inch answer comes from reading the 1/8 in/ft column, where 6-inch carries only 344 gpm. Section 1106.1 says the 100-year hourly rainfall rate (or approved local data) is the sizing basis.
Reference: 2018 International Plumbing Code, Section 1106.1; Table 1106.2
An office building (Group B) has a total occupant load of 240, split evenly between the sexes. Using IPC Table 403.1, how many water closets are required for each sex?
Answer: 4
Under 403.1.1, half the occupant load is used for each sex: 240 / 2 = 120. The Business ratio is 1 per 25 for the first 50 and 1 per 50 for the remainder: 50 / 25 = 2.0, plus (120 - 50) / 50 = 1.4, for 3.4. Fractions round up, so 4 water closets per sex. Rounding down gives 3. Applying 1 per 25 to all 120 gives 4.8, or 5. Using the full 240 at 1 per 25 gives 10.
Reference: 2018 International Plumbing Code, Section 403.1.1; Table 403.1 (No. 2, Business)
A storage water heater's cold supply passes through a pressure-reducing valve and a backflow preventer. Where must the thermal expansion control device connect?
Answer: On the cold supply, downstream of all check valves, PRVs and backflow devices
IPC 607.3 requires a thermal expansion control device on the water heater's cold water supply whenever that supply passes through a check valve, pressure-reducing valve or backflow preventer. It must connect downstream of all those devices so it can absorb the expanded water trapped between them and the heater. The tank must be sized so system pressure stays within 604.8. The T&P valve may never be used for thermal expansion control (504.4).
Reference: 2018 International Plumbing Code, Section 607.3
A building drain carries 300 drainage fixture units and is installed at 1/8 inch per foot. Using IPC Table 710.1(1), what is its minimum size?
Answer: 5 inches
In the 1/8 in/ft column of Table 710.1(1), a 4-inch drain carries 180 dfu and a 5-inch drain carries 390 dfu. 300 dfu is over 180, so 5 inches is the minimum. Even at steeper slopes a 4-inch drain would be too small, since it carries only 216 dfu at 1/4 in/ft and 250 dfu at 1/2 in/ft. Choosing 6 inches oversizes the drain.
Reference: 2018 International Plumbing Code, Section 710.1; Table 710.1(1)
A 2-inch trap serves a commercial floor sink, and its fixture drain slopes 1/4 inch per foot. Using IPC Table 909.1, what is the maximum developed length from the trap weir to the vent fitting?
Answer: 8 feet
Table 909.1 allows 8 feet for a 2-inch trap at 1/4 in/ft. Other values: 1-1/4 inch = 5 ft, 1-1/2 inch = 6 ft, 3 inch = 12 ft at 1/8 in/ft, and 4 inch = 16 ft at 1/8 in/ft. 909.2 also limits the total fall in the fixture drain to one pipe diameter. Except for water closets, the vent connection may not be below the trap weir.
Reference: 2018 International Plumbing Code, Section 909.1; Table 909.1
A natural gas system at an elevation below 2,000 feet (under 2 psi, 0.5 in. w.c. drop, 0.60 specific gravity, Schedule 40 steel) serves a 400,000 Btu/h rooftop unit, a 199,000 Btu/h water heater and a 120,000 Btu/h range. The longest run from the meter to the most remote outlet is 80 feet. Using 1,000 Btu per cubic foot and IFGC Table 402.4(2), what size is the first section, which carries the full load?
Answer: 2 inch
Total load = 400,000 + 199,000 + 120,000 = 719,000 Btu/h, or 719 cfh at 1,000 Btu/cu ft (402.2 uses the full connected load). Under the longest length method (402.4.1), use the 80-ft row of Table 402.4(2): 1-1/4 in = 452 cfh, 1-1/2 in = 677 cfh, 2 in = 1,300 cfh. 677 is less than 719, so 2-inch pipe is required. Picking 1-1/2 inch because 677 is close is the usual mistake.
Reference: 2018 International Fuel Gas Code, Sections 402.2 and 402.4.1; Table 402.4(2)
A commercial hot water heating loop has a maximum system design pressure of 80 psi. What hydrostatic test does the IMC require?
Answer: 120 psi for 15 minutes
IMC 1208.1 requires hydronic piping to be tested hydrostatically at 1-1/2 times the maximum system design pressure, but never less than 100 psi, for at least 15 minutes. Here 1.5 x 80 = 120 psi, which is above the 100 psi floor, so 120 psi governs. 100 psi would be correct only for systems designed at 66.7 psi or less. A compressed-gas test is an alternative only for PEX systems where every manufacturer permits it.
Reference: 2018 International Mechanical Code, Section 1208.1
A wet-pipe automatic sprinkler system with a fire department connection is supplied from the building's potable water service. No antifreeze or additives are used. Which backflow protection does the IPC accept on the potable supply?
Answer: A double check or RP fire protection assembly
IPC 608.17.4 requires the potable supply to automatic sprinkler and standpipe systems to be protected by a double check backflow prevention assembly, a double check fire protection backflow prevention assembly, or a reduced pressure principle fire protection backflow prevention assembly. Isolation is not required for systems installed as part of the water distribution system with no fire department connection, or for deluge, preaction or dry pipe systems. Neither exception applies here, because there is an FDC.
Reference: 2018 International Plumbing Code, Section 608.17.4
Sources
- PSI: C-37/CR-37 Plumbing (Commercial) content outline (PDF) (opens in a new tab)
- PSI: Arizona ROC Candidate Information Bulletin (Feb 2026) (opens in a new tab)
- Arizona ROC: Applying for a license (opens in a new tab)
Questions last verified October 19, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.