Requirements at a glance
| Agency | South Dakota Plumbing Commission (Department of Labor and Regulation); state-administered exam |
|---|---|
| Experience | 4 years as an apprentice at 1,900 hours a year (military credit: 1 year per 2 served) |
| Exam | Three parts, 5 hours in all; 70% to pass; question count not published |
| Books allowed | 2024 UPC (Part 1 open book; Part 2 closed book; confirm Part 3 with the Commission) |
| Fees | $100 exam fee, plus application and license fees |
Plumbers applying to the South Dakota Plumbing Commission for a plumber's license after 4 years as an apprentice at 1,900 hours a year (military plumbing earns 1 year of credit for each 2 years served).
Official links
How to get licensed, step by step
Apply to the Commission
Submit the plumbing application with the application fee. The Commission emails you if approved and tells you the next steps.
Schedule your exam
Exams are held in Pierre by appointment, and in Rapid City and Sioux Falls when 8 to 10 candidates apply. The exam fee is $100.
Pass all three parts
Part 1 (2 hours) and Part 2 (2 hours) are code questions; Part 3 (1 hour) is fixture drawings with pipe sizing. If you fail you may retest once every 3 months.
ARSD 20:53:03:07: plumber examination requirements (opens in a new tab)
Get licensed and renew
Plumbing licenses expire every December 31. Licensees who tested in must show continuing education before renewal.
How to prepare
- The Plumbing Commission gives its own exam (no outside vendor is named) in three parts: two code parts and a drawing part where you size stacks, wastes and vents. Part 1 is open book and Part 2 is closed book.
- The code is the 2024 UPC with South Dakota amendments. The Commission sells the 2024 UPC and a 2024 UPC Study Guide. The Commission does not publish question counts or topic weights, so ours are estimates.
- Practice fixture-unit counting and drain, waste and vent sizing from a described layout (UPC Chapters 7 and 9 and the sizing tables), since Part 3 tests it.
- Plumbers need 70% (ARSD 20:53:03:07). Part 3 is a drawing exercise with the code closed, so memorize the common fixture-unit values and trap and vent sizes.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below, and most questions come from the UPC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
Uniform Plumbing Code (UPC), 2024 Edition, IAPMO (with South Dakota amendments)Essential
Part 1 is open book and Part 2 is closed book. The Plumbing Commission sells the 2024 UPC and a 2024 UPC Study Guide.
Plumbing Commission (code book sales) (opens in a new tab)Read free: 2024 UPC (IAPMO) (opens in a new tab)
Official reference list (as published by the testing agency)
- Uniform Plumbing Code (UPC), 2024 Edition (IAPMO) with South Dakota amendments. Part 1 is open book; Part 2 is closed book.
What's on the exam
Estimated topic weighting. No official breakdown is published:
| Topic | Questions | |
|---|---|---|
| Chapter 3: General Regulations | 5 | |
| Chapter 4: Plumbing Fixtures and Fixture Fittings | 8 | |
| Chapter 5: Water Heaters | 5 | |
| Chapter 6: Water Supply and Distribution | 12 | |
| Chapter 7: Sanitary Drainage | 15 | |
| Chapter 8: Indirect Wastes | 3 | |
| Chapter 9: Vents | 15 | |
| Chapter 10: Traps and Interceptors | 5 | |
| Chapter 11: Storm Drainage | 7 | |
| Chapter 12: Fuel Gas Piping | 5 | |
| Pipe Sizing and Drawings | 20 |
Exam day details
- Administered by the South Dakota Plumbing Commission (state-administered exam).
- Fee: $100 exam fee to the Plumbing Commission. Application and license fees are separate.
- Three parts totaling 5 hours; 70% to pass (ARSD 20:53:03:07). Part 1 is open book, Part 2 is closed book and Part 3 does not allow the code.
- The exam has three parts: Part 1 (2 hours, code questions, open book), Part 2 (2 hours, code questions, closed book) and Part 3 (1 hour, fixture drawings where you size stacks, wastes and vents and insert pipe sizes).
- The Commission approves your application first, then you schedule. Exams are given in Pierre by appointment, with Rapid City and Sioux Falls sessions when 8 to 10 candidates apply.
- You may retest once every 3 months after a failure.
- Our questions follow the 2024 UPC. South Dakota amendments could not be checked, so confirm them with the Commission's code book.
Note: The Plumbing Commission does not publish the number of questions or the topic weights, so the question count and topic split here are our estimates. The 2024 UPC is the adopted code, but South Dakota's amendments could not be checked. Confirm details with the Commission.
Frequently asked questions
What's on the South Dakota plumber exam?
Parts 1 and 2 are questions based on the code. Part 3 is fixture drawings where you size stacks, wastes and vents and insert pipe sizes. The Commission publishes no topic weights, so our split (sizing and drawings 20, drainage 15, vents 15, water supply 12) is an estimate.
Which plumbing code does South Dakota use?
The 2024 Uniform Plumbing Code with South Dakota amendments. The Commission sells the 2024 UPC and a 2024 UPC Study Guide.
How often can I retest?
Once every 3 months after a failed exam.
Free questions with answers
Show all 10 free questions and answers
PEX tubing for a lavatory supply passes through a stud so that less than 1 inch is left between the tube and the exposed face of the framing. What protection does the 2024 UPC require?
Answer: A steel nail plate of at least No. 18 gauge, extending at least 1-1/2 inches beyond the tube outside diameter along the framing member
Section 312.9 requires steel nail plates not less than No. 18 gauge wherever plastic tubing or copper piping comes within 1 inch of the exposed framing, extending at least 1-1/2 inches past the pipe or tube outside diameter. A plastic sleeve does not stop a nail or screw, and plastic tube is not exempt.
Reference: 2024 Uniform Plumbing Code, Section 312.9
Which maximum flow rate applies to a new showerhead under Section 408.3 of the 2024 UPC?
Answer: 2.5 gpm at 80 psi
Section 408.3 limits showerheads to not more than 2.5 gpm at 80 psi. The 0.5 gpm at 60 psi value is the public lavatory limit (Section 407.2.1).
Reference: 2024 Uniform Plumbing Code, Section 408.3
A 40,000 Btu/h gas water heater sits in a room served only by indoor air, where the standard method of Section 506.2.1 applies. What minimum room volume is required?
Answer: 2,000 cubic feet
Section 506.2.1 requires 50 cubic feet per 1,000 Btu/h of input. 40,000 / 1,000 = 40, and 40 x 50 = 2,000 cubic feet. 800 cubic feet results from using 20 cubic feet per 1,000 Btu/h, 1,200 from using 30, and 4,000 from using 100.
Reference: 2024 Uniform Plumbing Code, Section 506.2.1
A copper water system is sized so that cold water in 3/4 inch tube has a velocity of 9 ft/s and hot water has a velocity of 4 ft/s. Under Section 610.12.1, which is correct?
Answer: The cold water is too fast; the hot water is acceptable
Section 610.12.1 limits copper tube systems to 8 ft/s for cold water and 5 ft/s for hot water. Cold water at 9 ft/s exceeds 8 ft/s, while hot water at 4 ft/s is below 5 ft/s.
Reference: 2024 Uniform Plumbing Code, Section 610.12.1
A 3-inch horizontal branch drain joins a larger horizontal drain. Which fitting does Section 706.3 allow for that connection?
Answer: A 45 degree wye branch
Section 706.3 requires horizontal-to-horizontal connections to enter through 45 degree wye branches, combination wye and one-eighth bend branches, or other approved fittings of equivalent sweep. Sanitary tees are allowed only where a horizontal line enters a vertical stack (Section 706.2).
Reference: 2024 Uniform Plumbing Code, Section 706.3
Under Section 904.1, what is the smallest individual vent permitted where the vent connects to a 4-inch drain?
Answer: 2 inches
Section 904.1 says an individual vent may not be smaller than 1-1/4 inches nor smaller than one-half the diameter of the drain it connects to. One-half of 4 inches is 2 inches, which governs over 1-1/4 inches.
Reference: 2024 Uniform Plumbing Code, Section 904.1
A 2-inch trap arm serves a fixture. Using Table 1002.2, what is the maximum developed length from the trap weir to the inner edge of the vent?
Answer: 60 inches
Table 1002.2 lists maximum trap arm lengths of 30 inches for 1-1/4 inch, 42 inches for 1-1/2 inch, 60 inches for 2 inch, 72 inches for 3 inch and 120 inches for 4 inch. The arm must keep 1/4 inch per foot slope.
Reference: 2024 Uniform Plumbing Code, Table 1002.2
What is the minimum cover for underground gas piping under Section 1210.1.1 where external damage is not likely?
Answer: 12 inches
Section 1210.1.1 requires a minimum of 12 inches of cover, increased to 18 inches where external damage to the pipe from outside forces is likely. If 12 inches cannot be provided, the piping must be in conduit.
Reference: 2024 Uniform Plumbing Code, Section 1210.1.1
A contractor wants to tie a roof leader into the sanitary building sewer to save trenching. Under the 2024 UPC this is:
Answer: prohibited, since storm water may not enter sanitary sewers
Section 1101.3 states that storm water shall not be drained into sewers intended for sanitary drainage. Section 1101.2 directs rainwater to a separate storm sewer, or where none exists, to a combined sewer or other place approved by the Authority Having Jurisdiction.
Reference: 2024 Uniform Plumbing Code, Section 1101.3
A house has two bathroom groups (1.6 gpf water closet, lavatory, tub/shower each), a domestic kitchen sink with dishwasher, and a clothes washer. Using Table 702.1, what is the total DFU?
Answer: 17 DFU
Each bathroom group is 3 + 1 + 2 = 6 DFU, so two groups give 12. A domestic kitchen sink with or without a dishwasher is 2 DFU, and the clothes washer is 3 DFU. 12 + 2 + 3 = 17 DFU. Counting the dishwasher separately gives 19, and omitting the washer gives 14.
Reference: 2024 Uniform Plumbing Code, Table 702.1
Sources
- South Dakota Plumbing Commission (opens in a new tab)
- ARSD 20:53:03:07: plumber examination requirements (opens in a new tab)
Questions last verified November 7, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.