Requirements at a glance
| Agency | City of Philadelphia Department of Licenses and Inspections; exam by ICC, delivered by Pearson VUE |
|---|---|
| Exam | ICC 211 Standard Master Electrician: 100 questions, 5 hours, open book |
| Experience | 4 years of electrical work for a licensed company (2 years of education counts as 1), plus 8 hours of NFPA 70 coursework in the prior 12 months |
| Books allowed | 2020 NEC; Ugly's Electrical Reference (any edition) |
| Fees | $115 to Pearson VUE; Philadelphia Electrical Contractor license $262, renews $202 a year (L&I pages, check current fees) |
Electricians applying for a Philadelphia Electrical Contractor license from Licenses and Inspections. Philadelphia has no journeyman electrician license. Pittsburgh, Reading and Allentown also use ICC master electrician exams with the same outline.
Official links
How to get licensed, step by step
Check you qualify
Philadelphia licenses electrical contractors, not journeymen. You need 4 years of electrical work for a licensed company, 8 hours of NFPA 70 coursework in the last 12 months and insurance.
City of Philadelphia: Licenses and Inspections (opens in a new tab)
Schedule exam 211 with Pearson VUE
Book through Pearson VUE ($115). If you fail, wait 10 days to retake.
Schedule with Pearson VUE (ICC exams) (opens in a new tab)ICC: Philadelphia Contractor/Trades Examination Information Bulletin (opens in a new tab)
Pass and apply to L&I
Send your results with your application. Results are valid for 12 months for applying, unless the code edition has changed. You also need a Commercial Activity License.
City of Philadelphia: Licenses and Inspections (opens in a new tab)
How to prepare
- Tab your 2020 NEC before exam day: Article 220 and Annex D load calculations, Chapter 9 tables, Article 310 ampacities and Article 430 motors.
- Philadelphia's code page lists the 2017 NEC, but the exam bulletin lists the 2020 NEC. Study the 2020 edition.
- Pittsburgh's master electrician exam (ICC T16) and Reading's and Allentown's ICC exams use the same national outline.
- Start with the free questions above to find your weak topics, then drill those first.
- Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
- Read every explanation, including for questions you got right, and look the section up in your own book.
Books for this exam
This is an open-book exam: you can bring the references below, and most questions come from the 2020 NEC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.
2020 National Electrical Code (NEC), NFPA 70Essential
Allowed in the exam room. Most of the exam comes from it.
Ugly's Electrical References (any edition)
Allowed in the exam room. Formulas, conductor and conduit tables, motor data.
Official reference list (as published by the testing agency)
- 2020 National Electrical Code, NFPA 70 (open book)
- Ugly's Electrical Reference, any edition (open book)
What's on the exam
Official content outline from International Code Council (ICC), delivered by Pearson VUE (number of questions per topic):
| Topic | Questions | |
|---|---|---|
| General Knowledge and Plan Reading | 12 | |
| Services and Service Equipment | 16 | |
| Feeders | 4 | |
| Branch Circuits and Conductors | 16 | |
| Wiring Methods and Materials | 19 | |
| Equipment and Devices | 10 | |
| Control Devices | 3 | |
| Motors and Generators | 8 | |
| Special Occupancies, Equipment, and Conditions | 12 |
Exam day details
- Administered by International Code Council (ICC), delivered by Pearson VUE for the City of Philadelphia Department of Licenses and Inspections.
- Fee: $115 to Pearson VUE. City of Philadelphia license fees are separate.
- 100 questions in 5 hours, open book. Code questions come from the 2020 NEC; Ugly's helps with theory and calculations.
- Philadelphia's electrical code page lists the 2017 NEC, but the ICC bulletin (effective March 15, 2026) lists the 2020 NEC for this exam. We follow the bulletin.
- To get the Electrical Contractor license you also need 4 years of electrical work for a licensed company (2 years of education counts as 1), 8 hours of NFPA 70 coursework in the prior 12 months, and insurance.
- ICC writes the exam and Pearson VUE delivers it. Every question is four-option multiple choice with one correct answer.
- If you fail, you must wait 10 days before you retake the exam.
- The ICC Philadelphia bulletin does not print a passing score. TODO(verify): confirm the passing score with ICC before you sit.
- Philadelphia's published exam results are valid for 12 months for applying, unless the code edition has changed.
Frequently asked questions
What's on the Philadelphia master electrician exam?
ICC exam 211: wiring methods and materials 19%, services and service equipment 16%, branch circuits and conductors 16%, general knowledge and plan reading 12%, special occupancies 12%, equipment and devices 10%, motors and generators 8%, feeders 4% and control devices 3%.
Which NEC edition does the exam use?
The ICC Philadelphia bulletin lists the 2020 NEC. Ugly's Electrical Reference is also allowed, in any edition.
Is there a Philadelphia journeyman electrician exam?
No. Philadelphia licenses electrical contractors only. Other Pennsylvania cities, such as Reading, license journeyman electricians and use the ICC journeyman exam.
Free questions with answers
Show all 10 free questions and answers
A 7.5 hp motor (746 W per hp) is 90 percent efficient and is supplied by a single-phase, 240-volt circuit at unity power factor. What is the approximate input current?
Answer: 25.9 A
Output = 7.5 x 746 = 5,595 W. Input = 5,595 / 0.90 = 6,217 W. I = 6,217 / 240 = 25.9 A. 23.3 A ignores efficiency, 21.0 A multiplies by efficiency instead of dividing, and 51.8 A divides by 120 volts.
Reference: Electrical theory, Motor efficiency and power formulas (Ugly's Electrical References)
Under 230.71(B), where a service uses more than one disconnecting means (separate enclosures each with a main disconnect, panelboards each with a main, or separate switchboard sections), what is the maximum number of service disconnects permitted for each service?
Answer: Six
The 2020 NEC requires one service disconnecting means unless 230.71(B) is met, which permits two to six disconnects, each in its own enclosure, panelboard with a main, or separate vertical switchboard section. Six main breakers in one common enclosure, allowed in earlier editions, is no longer permitted. A seventh disconnect would need a separate service where 230.2 permits one.
Reference: 230.71(B), 230.71(B) Two to Six Service Disconnecting Means
A feeder is protected by a 600-ampere overcurrent device. A 10-ft feeder tap is made with field-installed conductors that leave the enclosure and are protected from physical damage in a raceway. What is the minimum ampacity of the tap conductors under 240.21(B)(1)?
Answer: 60 A
Where a 10-ft tap leaves the enclosure, 240.21(B)(1) requires its ampacity to be at least one-tenth of the rating of the overcurrent device protecting the feeder (and not less than the load it supplies): 600 x 0.10 = 60 A. 200 A is the one-third value used for 25-ft taps, and 300 A is half of the device rating.
Reference: 240.21(B)(1), 240.21(B)(1)
A branch circuit supplies a 24 A continuous load and a 10 A noncontinuous load. Equipment terminals are rated 75 degrees C. Using Table 310.16, what is the smallest THWN copper conductor permitted?
Answer: 8 AWG
Under 210.19(A)(1) the minimum conductor ampacity is the noncontinuous load plus 125 percent of the continuous load: 10 + (1.25 x 24) = 40 A. In the 75 degree C column of Table 310.16, 10 AWG copper is 35 A (too small) and 8 AWG is 50 A, so 8 AWG is the smallest. (In the 2017 NEC this table was numbered 310.15(B)(16).)
Reference: 210.19(A)(1), 210.19(A)(1); Table 310.16
Using Table 314.16(A), what is the maximum number of 12 AWG conductors permitted in a 4 in. x 1-1/2 in. square metal box (21.0 cu in.)?
Answer: 9
Table 314.16(A) lists 21.0 cu in. for a 4 in. x 1-1/2 in. square box. Each 12 AWG conductor takes 2.25 cu in., so 21.0 / 2.25 = 9.3, which rounds down to 9 as listed in the table. 10 would be correct for 14 AWG, and 8 for 10 AWG.
Reference: Table 314.16(A), Table 314.16(A)
A pull box is used for a straight pull of 6 AWG and larger conductors. The largest raceway entering the box is 2-1/2 inches. What is the minimum length of the box under 314.28(A)(1)?
Answer: 20 inches
For straight pulls, 314.28(A)(1) requires the box length to be at least 8 times the trade size of the largest raceway: 8 x 2.5 = 20 inches. 24 inches would be 8 times a 3-inch raceway, and 15 inches is 6 times the trade size.
Reference: 314.28(A)(1), 314.28(A)(1)
What is the minimum width of the working space in front of electrical equipment under 110.26(A)(2)?
Answer: 30 inches, or the width of the equipment if greater
Section 110.26(A)(2) requires working space width of at least 30 inches or the width of the equipment, whichever is greater. The space need not be centered on the equipment.
Reference: 110.26(A)(2), 110.26(A)(2)
Which of these is an acceptable motor disconnecting means under 430.109(A)?
Answer: A listed motor-circuit switch rated in horsepower
Section 430.109(A) lists acceptable disconnecting means, including a motor-circuit switch rated in horsepower, a molded-case circuit breaker, a molded-case switch, an instantaneous-trip breaker in a listed combination controller, and in some cases a general-use switch. A motor-circuit switch rated in horsepower is the most direct choice.
Reference: 430.109(A), 430.109(A)
A single 15 hp, 208-volt, 3-phase continuous-duty induction motor has a Table 430.250 full-load current of 46.2 A. What is the minimum ampacity of the branch-circuit conductors under 430.22?
Answer: 57.8 A
Section 430.22 requires conductors for a single continuous-duty motor to have an ampacity of at least 125 percent of the Table 430.250 full-load current: 46.2 x 1.25 = 57.8 A. 46.2 A omits the 125 percent factor, 52.5 A uses the 230-volt table value (42 A), and 69.3 A applies 150 percent.
Reference: 430.22, 430.22; Table 430.250
Under 517.18(A), what is required for each patient bed location in a general care (Category 2) space?
Answer: At least two branch circuits, one from the critical branch and one from the normal system
Section 517.18(A) requires each patient bed location in general care (Category 2) spaces to be supplied by at least two branch circuits, one from the critical branch of the essential electrical system and one from the normal system. All branch circuits from the normal system must originate in the same panelboard.
Reference: 517.18(A), 517.18(A)
Sources
- ICC: Philadelphia Contractor/Trades Examination Information Bulletin (3/15/2026) (opens in a new tab)
- Pearson VUE: ICC exams (opens in a new tab)