Oklahoma licensing exam

Oklahoma Residential Journeyman Electrician Exam: Practice Test & Licensing Guide

The PSI exam for an Oklahoma residential journeyman electrician license: 80 scored questions on the 2023 NEC with Oklahoma amendments for one- to three-family dwellings. Open book, 70% to pass.

Questions
80
Time limit
3.5 hours
Passing score
70%

Full practice test: $19One-time payment · 12 months of access

Try 10 free practice questions

No sign-up. Every answer explains the rule and tells you where to find it in your book.

Question 1 of 10General Knowledge

In the 2023 NEC, which wording marks an action as optional rather than mandatory?

Requirements at a glance

AgencyOklahoma Construction Industries Board (CIB); exams by PSI
Experience4,000 hours of residential electrical experience
Exam80 scored questions, 3.5 hours, 70%
Books allowed2023 NEC as adopted in Oklahoma (bound; no handbooks or spiral-bound copies), 29 CFR 1926, Ugly's (any edition)
Fee$92 to PSI per exam portion (non-refundable), plus CIB application and license fees
Retest30 days after each fail

Electricians applying to the Oklahoma Construction Industries Board for a residential journeyman license after 4,000 hours of documented experience. The Residential Electrical Contractor exam is identical.

How to get licensed, step by step

  1. Register and log your hours

    Register with the CIB as an apprentice and log your hours under a licensed contractor (1 year is 2,000 hours). Have your employer's affidavits notarized.

    Oklahoma Construction Industries Board (CIB) (opens in a new tab)

  2. Apply to the CIB

    Send the CIB your application and notarized experience affidavits. When it approves you, you receive an Ok Con ID.

    Oklahoma Construction Industries Board (CIB) (opens in a new tab)

  3. Schedule with PSI

    Book your exam with PSI online or at (855) 834-8750. Contractor applicants also take the Business and Law portion.

    Schedule with PSI (Oklahoma contractor exams) (opens in a new tab)PSI: Oklahoma CIB Candidate Information Bulletin (effective 9/11/2026) (opens in a new tab)

  4. Pass and get licensed

    After you pass, send the CIB your results and license fee to receive your license.

    Oklahoma Construction Industries Board (CIB) (opens in a new tab)

How to prepare

  • All Oklahoma trade exams are open book, so the skill is finding answers fast: bound books, permanent tabs only, highlighting allowed, no writing.
  • Bring a silent, non-programmable calculator. The exam adds up to 10 unscored experimental questions that count against your time.
  • Focus on one- to three-family dwellings: Articles 210, 220 Part III, 230, 250, 300 series wiring methods, 406 and 680, plus mobile homes and RVs (Articles 550 and 551).
  • General electrical knowledge is 12 of the 80 questions: Ohm's law, power and basic circuit calculations from Ugly's.
  • Start with the free questions above to find your weak topics, then drill those first.
  • Take at least two full timed simulations before exam day. Timing is where most people fail open-book exams.
  • Read every explanation, including for questions you got right, and look the section up in your own book.

Books for this exam

This is an open-book exam: you can bring the references below, and most questions come from the NEC. Tabs and highlighting are allowed. Free online copies are read-only and can't be used in the exam room.

Official reference list (as published by the testing agency)
  • NFPA 70 National Electrical Code, 2023 edition, as revised and adopted by the Oklahoma Uniform Building Code Commission (bound copy; NEC handbooks and spiral-bound copies are not allowed)
  • 29 CFR Part 1926 (OSHA construction), or PSI's selections
  • Ugly's Electrical References, George V. Hart (any edition)

What's on the exam

Official content outline from PSI Services (number of questions per topic):

TopicQuestions
General Knowledge4
General Electrical Knowledge12
Electrical Installation Requirements10
Services, Feeders, and Branch Circuits10
Overcurrent Protection8
Grounding and Bonding8
Conductors and Cables8
Raceways and Boxes6
Special Occupancies and Equipment4
Low Voltage, Alarms, Signaling Systems, and Communications2
Lighting and Signs4
Safety4

Exam day details

  • Administered by PSI Services for the Oklahoma Construction Industries Board (CIB).
  • Fee: $92 to PSI per exam portion, non-refundable. CIB application and license fees are separate.
  • 80 scored questions in 3.5 hours (210 minutes); 70% (56) to pass.
  • Oklahoma adopted the 2023 NEC with small amendments (OAC 748:20-10), including 210.8(F) outdoor-outlet GFCI and 422.16(B)(5) cord-and-plug gas furnaces. Our questions follow the amended text.
  • If you fail, wait 30 days to retest.
  • Open book: bring your own bound copies of the allowed references. You may highlight, underline and index them beforehand with permanent tabs only; no writing and no sticky notes.
  • PSI may add up to 10 unscored experimental questions, which count against your time. A silent, non-printing, non-programmable calculator is allowed.
  • The CIB must approve your application first (you receive an Ok Con ID) before you can schedule with PSI.

Frequently asked questions

What's on the Oklahoma residential journeyman electrician exam?

80 scored questions: general electrical knowledge 12, installation requirements and services/feeders/branch circuits 10 each, overcurrent protection, grounding and bonding and conductors and cables 8 each, raceways and boxes 6, special occupancies (mobile homes, RVs, pools), lighting and signs, general knowledge and safety 4 each, and low voltage 2.

What is the difference between the residential and unlimited exams?

The residential exam has 80 questions in 210 minutes and covers one- to three-family dwellings. The unlimited exam has 100 questions in 240 minutes and adds motors and transformers and more special-occupancy content.

Free questions with answers

Show all 10 free questions and answers
  1. In the 2023 NEC, which wording marks an action as optional rather than mandatory?

    Answer: "Shall be permitted"

    Section 90.5 separates mandatory rules, written with "shall" or "shall not", from permissive rules, written with "shall be permitted" or "shall not be required". An installer may choose whether to use a permissive option, but must follow every mandatory rule.

    Reference: NFPA 70, National Electrical Code, 2023, 90.5(A) and 90.5(B)

  2. A 10-ohm resistor and a 15-ohm resistor are connected in series across a 120-volt source. What is the circuit current?

    Answer: 4.8 A

    Series resistances add: R = 10 + 15 = 25 ohms. I = E / R = 120 / 25 = 4.8 A. Dividing by only the 15-ohm resistor gives 8 A, by only the 10-ohm gives 12 A, and treating them as parallel (6 ohms) gives 20 A.

    Reference: General electrical theory (Ohm's law and power formulas), Series circuit, I = E / R

  3. A 120/240-volt residential panelboard has exposed live parts on one side of the working space and a grounded concrete wall on the other. What is the minimum clear working distance in front of the panel?

    Answer: 3 ft

    Table 110.26(A)(1) lists 3 ft for all three conditions when the nominal voltage to ground is 0 to 150 V, which covers 120/240-volt residential equipment. The larger distances apply only at higher voltages to ground.

    Reference: NFPA 70, National Electrical Code, 2023, Table 110.26(A)(1)

  4. Where a service is permitted more than one service disconnecting means, what is the maximum number of disconnects permitted for that service under 230.71(B)?

    Answer: Six

    Section 230.71(A) sets the general rule of one service disconnecting means, and 230.71(B) permits two to six for each service, grouped in one location. Since the 2020 edition each disconnect must be in a separate enclosure, panelboard, switchgear compartment or switchboard section, so six handles in one load center no longer qualify for new work. Two, four and eight are not Code limits.

    Reference: NFPA 70, National Electrical Code, 2023, 230.71(B)

  5. A 12 AWG aluminum conductor (or copper-clad aluminum) is used for a branch circuit. What is the maximum overcurrent device rating under the small-conductor rule?

    Answer: 15 A

    Section 240.4(D) lists 12 AWG aluminum and copper-clad aluminum at 15 A and 10 AWG aluminum at 25 A. The 20 A limit applies to 12 AWG copper only, and 25 A is the 10 AWG aluminum value. Aluminum 12 AWG therefore needs a 15 A device.

    Reference: NFPA 70, National Electrical Code, 2023, 240.4(D)

  6. A metal underground water pipe is the only grounding electrode available at an existing house. What does 250.53(D)(2) require?

    Answer: A supplemental electrode of a type listed in 250.52(A)

    A metal underground water pipe in direct contact with the earth for 10 ft or more is an electrode, but it must be supplemented by an additional electrode from 250.52(A) (not another water pipe or the gas piping). The bonding connection to the interior piping is made separately.

    Reference: NFPA 70, National Electrical Code, 2023, 250.53(D)(2), 250.52(A)(1)

  7. What is the maximum operating temperature for Type THHN insulation in dry locations?

    Answer: 90 degrees C (194 degrees F)

    Table 310.4(1) (numbered Table 310.104(A) before the 2020 edition) lists THHN as 90 degrees C in dry and damp locations. THWN is rated 75 degrees C in wet or dry locations, and conductors marked THWN-2 are 90 degrees C in either. Terminations often limit the usable ampacity to the 60 or 75 degrees C column.

    Reference: NFPA 70, National Electrical Code, 2023, Table 310.4(1)

  8. A 3 in. x 2 in. x 3 1/2 in. device box (14.0 cubic inches) contains two 14/2 NM cables with ground, no internal clamps, and one single-pole switch. What is the minimum required volume under 314.16(B)?

    Answer: 14.0 cubic inches

    14 AWG allows 2.0 cubic inches per conductor (Table 314.16(B)). Four circuit conductors = 8.0. All equipment grounding conductors together count as one: 2.0. The switch yoke counts as two conductors: 4.0. Total = 8 + 2 + 4 = 14.0 cubic inches. Omitting the yoke gives 10.0, and omitting the grounds gives 12.0.

    Reference: NFPA 70, National Electrical Code, 2023, 314.16(B), Table 314.16(B)

  9. A 240-volt, 15-ampere single-phase branch circuit supplies a pool pump motor outlet at a dwelling. What protection does 680.21 require?

    Answer: GFCI protection

    Section 680.21(C) requires GFCI protection for outlets supplying pool pump motors on branch circuits rated 150 volts or less to ground and 60 amperes or less, whether connected by receptacle or directly. A 240-volt, 15-ampere single-phase circuit is 120 volts to ground, so it is covered. Grounding the motor is still required but does not replace GFCI protection, and AFCI protection is not the requirement here.

    Reference: NFPA 70, National Electrical Code, 2023, 680.21(C)

  10. How high above the floor may the center of the operating handle of a snap switch be, when in its highest position, under 404.8(A)?

    Answer: 6 ft 7 in.

    Section 404.8(A) requires switches to be operable from a readily accessible place, with the center of the grip of the operating handle in its highest position not higher than 6 ft 7 in. above the floor or working platform.

    Reference: NFPA 70, National Electrical Code, 2023, 404.8(A)

Sources

Questions last verified November 3, 2026. Licensing rules change. Always confirm current requirements with the licensing agency before you apply.